142 projects on file, including joint ventures this contractor is part of.
Total projects
142
Total budget
₱1.5B
Average progress
99.7%
Completion rate
97.9%
Average risk score
17.2
Low risk on average, out of 100
Flagged as unusual
2
1.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XII | 127 | ₱1.4B | 17.0 | 2 | 99.7% |
| Region XI | 14 | ₱34.4M | 17.8 | 0 | 98.9% |
| Region X | 1 | ₱5.4M | 40.1 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 77 | ₱380M | 11.9 | 0 | 99.8% |
| Roads | 41 | ₱761.8M | 22.3 | 0 | 100.0% |
| Water Provision and Storage | 17 | ₱54.4M | 13.5 | 0 | 100.0% |
| Flood Control and Drainage | 2 | ₱50.8M | 35.1 | 0 | 100.0% |
| Bridges | 2 | ₱37.6M | 30.8 | 0 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱71.9M | 94.1 | 1 | 71.4% |
| GAA 2025 SSP | 1 | ₱4.9M | 81.3 | 0 | 100.0% |
| OTHER | 1 | ₱95.4M | 81.0 | 1 | 95.2% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25MC0077ROAD WIDENING ALONG DAVAO-COTABATO RD (JCT DIGOS-COTABATO SECT) - K1625 + 817 - K1626 + 558, K1630 + 986 - K1632 + 430, KIDAPAWAN CITY, NORTH COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱71.9M | 71% | High risk94 | Flagged0.017 |
| 25MD0044CONSTRUCTION OF ROAD, SITIO PINAMULAAN - BARANGAY NORTH MANUANGAN - BARANGAY SOUTH MANUANGAN, PIGCAWAYAN, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱4.9M | 100% | High risk81 | —-0.021 |
| 24M00066REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - DAVAO-COTABATO RD (JCT DIGOS-COTABATO SECT) - K1603+607 - K1605+863, K1623+389 - K1623+793, K1626+534 - K1626+854, K1628+400 - K1629+320, K1632+420 - K1633+393, MAKILALA, NORTH COTABATO | Region XII | Region XII | On-Going | ₱95.4M | 95% | High risk81 | Flagged0.011 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25MC0077ROAD WIDENING ALONG DAVAO-COTABATO RD (JCT DIGOS-COTABATO SECT) - K1625 + 817 - K1626 + 558, K1630 + 986 - K1632 + 430, KIDAPAWAN CITY, NORTH COTABATO | Region XII | Cotabato 2nd DEO | On-Going | ₱71.9M | 71% | High risk94 | Flagged0.017 |
| 24M00066REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - DAVAO-COTABATO RD (JCT DIGOS-COTABATO SECT) - K1603+607 - K1605+863, K1623+389 - K1623+793, K1626+534 - K1626+854, K1628+400 - K1629+320, K1632+420 - K1633+393, MAKILALA, NORTH COTABATO | Region XII | Region XII | On-Going | ₱95.4M | 95% | High risk81 | Flagged0.011 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 126 | 18MD0013CONST. OF MULTI-PURPOSE BUILDING (BRGY. HALL), PARUAYAN, ALAMADA, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱1.9M | 100% | Low risk5 | —-0.088 |
| 127 | 19MD0076CONSTRUCTION OF MULTI-PURPOSE BUILDING (MPB), BRGY. RANGABAN, MIDSAYAP, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱1.9M | 100% | Low risk5 | —-0.086 |
| 128 | 17MD0167CONST. OF 1STY 3CL SCHOOL BUILDING (TOILET ATTACHED), KISULAO ES, ALAMADA, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱3.5M | 100% | Low risk5 | —-0.021 |
| 129 | 18MD0011CONST. OF MULTI-PURPOSE BUILDING, BULUAN, KABACAN, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱1.9M | 100% | Low risk5 | —-0.089 |
| 130 | 21MC0052CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), SITIO SAN MIGUEL, BARANGAY SIKITAN, KIDAPAWAN CITY, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱986.8K | 100% | Low risk4 | —-0.085 |
| 131 | 18MD0217COMPLETION OF 2STY 6CL SCHOOL BUILDING, LIBUNGAN NHS, LIBUNGAN, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱1.4M | 100% | Low risk4 | —-0.044 |
| 132 | 18MD0230COMPLETION OF 2STY 6CL SCHOOL BUILDING 2, DUALING HS, ALEOSAN, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱1.4M | 100% | Low risk4 | —-0.043 |
| 133 | 18MD0228COMPLETION OF 2STY 6CL SCHOOL BUILDING, KIMAGANGO NHS, MIDSAYAP, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱1.5M | 100% | Low risk4 | —-0.045 |
| 134 | 16MD0117REPAIR/RENOVATION/IMPVT OF RHU, POBLACION, PIGCAWAYAN, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱1.9M | 100% | Low risk3 | —-0.017 |
| 135 | 17MD0161CONST. OF 1STY 3CL SCHOOL BUILDING (TOILET ATTACHED), RARADANGAN ES, ALAMADA, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱3.6M | 100% | Low risk3 | —-0.020 |
| 136 | 17MD0169CONST. OF 1STY 3CL SCHOOL BUILDING (TOILET ATTACHED), DUNGUAN-MATANOG NHS PAGANGAN HS EXT., ALEOSAN, | Region XII | Cotabato 1st DEO | Completed | ₱3.5M | 100% | Low risk3 | —-0.016 |
| 137 | 17MD0214COMPLETION OF 3STY 9CL SCHOOL BUILDING, VILLARICA HS, MIDSAYAP, NORTH COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱2M | 100% | Low risk3 | —-0.020 |
| 138 | 17MD0164CONST. OF 1STY 3CL SCHOOL BUILDING (TOILET ATTACHED), BARONGIS ES, LIBUNGAN, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱3.5M | 100% | Low risk3 | —-0.020 |
| 139 | 17MD0136CONST. OF 1STY 2CL SCHOOL BUILDING (TOILET ATTACHED), UPPER BAO ES, ALAMADA, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱2.5M | 100% | Low risk3 | —-0.021 |
| 140 | 17MD0182CONST. OF 1STY 2CL SCHOOL BLDG (TOILET ATTACHED), FORT PIKIT ES, PIKIT, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱2.5M | 100% | Low risk3 | —-0.019 |
| 141 | 17MD0198CONST. OF 1STY 2CL SB (TOILET ATTACHED), MALINGAO ES, MIDSAYAP, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱2.5M | 100% | Low risk2 | —-0.020 |
| 142 | 17MD0193CONST. OF 1STY 2CL SB (TOILET ATTCHED), DATU GUILEM PIANG ES, MIDSAYAP, COTABATO | Region XII | Cotabato 1st DEO | Completed | ₱2.6M | 100% | Low risk2 | —-0.019 |