Contractor dossier
169 projects on file, including joint ventures this contractor is part of.
Total projects
169
Total budget
₱9.5B
Average progress
92.6%
Completion rate
85.8%
Average risk score
48.8
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 139 | ₱7.4B | 49.1 | 0 | 93.6% |
| Region III | 18 | ₱976.6M | 37.3 | 0 | 100.0% |
| Region IV-A | 6 | ₱548.9M | 62.5 | 0 | 49.4% |
| Negros Island Region | 6 | ₱586.5M | 62.1 | 0 | 89.9% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 79 | ₱5.2B | 50.4 | 0 | 94.6% |
| Buildings and Facilities | 58 | ₱3.2B | 45.6 | 0 | 86.2% |
| Roads | 27 | ₱807.6M | 48.1 | 0 | 100.0% |
| GAA 2025 OO-2 | 2 | ₱142.6M | 78.5 | 0 | 84.8% |
| OTHER | 2 | ₱108.5M | 57.4 | 0 | 100.0% |
| Bridges | 1 | ₱9.5M | 46.8 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25OD0206CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ESTERO DE MAYPAJO, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱48M | 70% | High risk89 | —-0.016 |
| 24CC0078CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG ANGAT RIVER, BARANGAY CAMBAOG, BUSTOS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | High risk79 | —-0.052 |
| 25OB0127CONSTRUCTION OF SLOPE PROTECTION ALONG C-6 OPEN CHANNEL (PHASE 17), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱94.6M | 100% | High risk68 | —-0.043 |
| 25OD0217INSTALLATION OF NEW UNIT PUMPS WITH FLOOD GATE AT WAWANG PULO PUMPING STATION WITH CONSTRUCTION OF PUMP HOUSE, BARANGAY WAWANG PULO, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱190.5M | 49% | High risk68 | —-0.017 |
| 24OB0187CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG C-6 OPEN CHANNEL, (PHASE 1), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱141.8M | 100% | High risk67 | —-0.064 |
| 24OB0189CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG C-6 OPEN CHANNEL, (PHASE 3), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱141.9M | 100% | High risk67 | —-0.064 |
| 24OB0188CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG C-6 OPEN CHANNEL, (PHASE 2), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱141.8M | 100% | High risk67 | —-0.066 |
| 23OD0231CONSTRUCTION OF MULTI-PURPOSE BUILDING BRGY. PASO DE BLAS, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱190.1M | 93% | High risk66 | —-0.021 |
| 24OD0280CONSTRUCTION OF MULTI-PURPOSE BUILDING, LAON, VEINTE REALES, VALENZUELA CITY (SHFC) | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱292.2M | 20% | High risk66 | —-0.001 |
| 21OD0133CONSTRUCTION OF LEGISLATIVE AND PEOPLE'S BUILDING VALENZUELA CITY HALL, KARUHATAN, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱334.9M | 100% | High risk66 | —-0.013 |
| 24OD0281CONSTRUCTION OF MULTI-PURPOSE BUILDING, (DEPED BUILDING) MALINTA, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱219.4M | 29% | High risk66 | —-0.012 |
| 23OD0229CONSTRUCTION OF LEGISLATIVE BUILDING & PEOPLES BUILDING (PHASE II) VALENZUELA CITY HALL, BRGY. KARUHATAN, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱157.8M | 53% | High risk66 | —-0.014 |
| 21OD0130CONSTRUCTION (COMPLETION) OF PAMANTASAN NG LUNGSOD NG VALENZUELA (SATELLITE BUILDING), BARANGAY MALINTA, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱148.7M | 100% | High risk66 | —-0.068 |
| 25OD0340CONSTRUCTION OF MULTI-PURPOSE BUILDING (RESSETLEMENT PROGRAM FOR ISFS), VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱191.2M | 5% | High risk65 | —-0.006 |
| 23CC0546CONSTRUCTION OF RIVER CONTROL SYSTEM AND REHABILITATION OF WATERWAYS ALONG BALAGTAS RIVER BRGY. PANGINAY BALAGTAS, BULACAN (STA. 15+538 TO STA. 15+742) | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | High risk65 | —-0.016 |
| 24OD0029CONSTRUCTION OF REINFORCED CONCRETE BOX CULVERT ALONG 8TH STREET, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱94.2M | 100% | High risk65 | —-0.077 |
| 24OD0084CONSTRUCTION OF FLOOD CONTROL WALL ALONG POLO RIVER (PHASE 11), VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱94.1M | 100% | High risk65 | —-0.070 |
| 23OD0090CONSTRUCTION OF FLOOD CONTROL WALL ALONG LINGUNAN CREEK, VEINTE REALES, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱94.3M | 100% | High risk65 | —-0.072 |
| 21OD0132CONSTRUCTION OF FLOOD CONTROL WALL ALONG MEYCAUAYAN RIVER, BARANGAY BIGNAY, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱94.1M | 100% | High risk65 | —-0.075 |
| 24OD0083CONSTRUCTION OF FLOOD CONTROL WALL ALONG POLO RIVER (PHASE 10), VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱94.1M | 100% | High risk65 | —-0.024 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25OD0206CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ESTERO DE MAYPAJO, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱48M | 70% | High risk89 | —-0.016 |
| 2 | 24CC0078CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG ANGAT RIVER, BARANGAY CAMBAOG, BUSTOS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | High risk79 | —-0.052 |
| 3 | 25OB0127CONSTRUCTION OF SLOPE PROTECTION ALONG C-6 OPEN CHANNEL (PHASE 17), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱94.6M | 100% | High risk68 | —-0.043 |
| 4 | 25OD0217INSTALLATION OF NEW UNIT PUMPS WITH FLOOD GATE AT WAWANG PULO PUMPING STATION WITH CONSTRUCTION OF PUMP HOUSE, BARANGAY WAWANG PULO, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱190.5M | 49% | High risk68 | —-0.017 |
| 5 | 24OB0187CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG C-6 OPEN CHANNEL, (PHASE 1), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱141.8M | 100% | High risk67 | —-0.064 |
| 6 | 24OB0189CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG C-6 OPEN CHANNEL, (PHASE 3), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱141.9M | 100% | High risk67 | —-0.064 |
| 7 | 24OB0188CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG C-6 OPEN CHANNEL, (PHASE 2), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱141.8M | 100% | High risk67 | —-0.066 |
| 8 | 23OD0231CONSTRUCTION OF MULTI-PURPOSE BUILDING BRGY. PASO DE BLAS, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱190.1M | 93% | High risk66 | —-0.021 |
| 9 | 24OD0280CONSTRUCTION OF MULTI-PURPOSE BUILDING, LAON, VEINTE REALES, VALENZUELA CITY (SHFC) | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱292.2M | 20% | High risk66 | —-0.001 |
| 10 | 21OD0133CONSTRUCTION OF LEGISLATIVE AND PEOPLE'S BUILDING VALENZUELA CITY HALL, KARUHATAN, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱334.9M | 100% | High risk66 | —-0.013 |
| 11 | 24OD0281CONSTRUCTION OF MULTI-PURPOSE BUILDING, (DEPED BUILDING) MALINTA, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱219.4M | 29% | High risk66 | —-0.012 |
| 12 | 23OD0229CONSTRUCTION OF LEGISLATIVE BUILDING & PEOPLES BUILDING (PHASE II) VALENZUELA CITY HALL, BRGY. KARUHATAN, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱157.8M | 53% | High risk66 | —-0.014 |
| 13 | 21OD0130CONSTRUCTION (COMPLETION) OF PAMANTASAN NG LUNGSOD NG VALENZUELA (SATELLITE BUILDING), BARANGAY MALINTA, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱148.7M | 100% | High risk66 | —-0.068 |
| 14 | 25OD0340CONSTRUCTION OF MULTI-PURPOSE BUILDING (RESSETLEMENT PROGRAM FOR ISFS), VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱191.2M | 5% | High risk65 | —-0.006 |
| 15 | 23CC0546CONSTRUCTION OF RIVER CONTROL SYSTEM AND REHABILITATION OF WATERWAYS ALONG BALAGTAS RIVER BRGY. PANGINAY BALAGTAS, BULACAN (STA. 15+538 TO STA. 15+742) | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | High risk65 | —-0.016 |
| 16 | 24OD0029CONSTRUCTION OF REINFORCED CONCRETE BOX CULVERT ALONG 8TH STREET, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱94.2M | 100% | High risk65 | —-0.077 |
| 17 | 24OD0084CONSTRUCTION OF FLOOD CONTROL WALL ALONG POLO RIVER (PHASE 11), VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱94.1M | 100% | High risk65 | —-0.070 |
| 18 | 23OD0090CONSTRUCTION OF FLOOD CONTROL WALL ALONG LINGUNAN CREEK, VEINTE REALES, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱94.3M | 100% | High risk65 | —-0.072 |
| 19 | 21OD0132CONSTRUCTION OF FLOOD CONTROL WALL ALONG MEYCAUAYAN RIVER, BARANGAY BIGNAY, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱94.1M | 100% | High risk65 | —-0.075 |
| 20 | 24OD0083CONSTRUCTION OF FLOOD CONTROL WALL ALONG POLO RIVER (PHASE 10), VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱94.1M | 100% | High risk65 | —-0.024 |
| 21 | 24DI0116CONSTRUCTION OF RIVER PROTECTION STRUCTURE NEAR SOUTH LUZON EXPRESSWAY (SLEX) MALITLIT BRIDGE, STA. ROSA CITY, LAGUNA (PHASE 1) | Region IV-A | Laguna 2nd DEO | On-Going | ₱96.3M | 53% | High risk64 | —-0.027 |
| 22 | 24DI0117CONSTRUCTION OF RIVER PROTECTION STRUCTURE NEAR SOUTH LUZON EXPRESSWAY (SLEX) MALITLIT BRIDGE, STA. ROSA CITY, LAGUNA (PHASE II) | Region IV-A | Laguna 2nd DEO | On-Going | ₱96.3M | 66% | High risk64 | —-0.031 |
| 23 | 24OB0171CONSTRUCTION OF SLOPE PROTECTION ALONG C-6 OPEN CHANNEL (PHASE 11), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱94.6M | 100% | High risk64 | —-0.077 |
| 24 | 25DI0102CONSTRUCTION OF RIVER PROTECTION STRUCTURE ALONG STA. ROSA RIVER, (NEAR STA. ROSA-BINAN BOUNDARY BRIDGE), STA. ROSA SIDE, STA. ROSA CITY LAGUNA (PHASE 1) | Region IV-A | Laguna 2nd DEO | On-Going | ₱97.1M | 0% | High risk64 | —-0.018 |
| 25 | 25DI0103REHABILITATION OF FLOOD CONTROL PHASE 1 ALONG BRGY. SANTO DOMINGO, STA. ROSA, LAGUNA | Region IV-A | Laguna 2nd DEO | On-Going | ₱97.1M | 67% | High risk64 | —-0.035 |