Opening the dossier…
Opening the dossier…
Contractor dossier
169 projects on file, including joint ventures this contractor is part of.
Total projects
169
Total budget
₱9.5B
Average progress
92.6%
Completion rate
85.8%
Average risk score
48.8
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 139 | ₱7.4B | 49.1 | 0 | 93.6% |
| Region III | 18 | ₱976.6M | 37.3 | 0 | 100.0% |
| Region IV-A | 6 | ₱548.9M | 62.5 | 0 | 49.4% |
| Negros Island Region | 6 | ₱586.5M | 62.1 | 0 | 89.9% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 79 | ₱5.2B | 50.4 | 0 | 94.6% |
| Buildings and Facilities | 58 | ₱3.2B | 45.6 | 0 | 86.2% |
| Roads | 27 | ₱807.6M | 48.1 | 0 | 100.0% |
| GAA 2025 OO-2 | 2 | ₱142.6M | 78.5 | 0 | 84.8% |
| OTHER | 2 | ₱108.5M | 57.4 | 0 | 100.0% |
| Bridges | 1 | ₱9.5M | 46.8 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25OD0206CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ESTERO DE MAYPAJO, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱48M | 70% | High risk89 | —-0.016 |
| 24CC0078CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG ANGAT RIVER, BARANGAY CAMBAOG, BUSTOS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | High risk79 | —-0.052 |
| 25OB0127CONSTRUCTION OF SLOPE PROTECTION ALONG C-6 OPEN CHANNEL (PHASE 17), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱94.6M | 100% | High risk68 | —-0.043 |
| 25OD0217INSTALLATION OF NEW UNIT PUMPS WITH FLOOD GATE AT WAWANG PULO PUMPING STATION WITH CONSTRUCTION OF PUMP HOUSE, BARANGAY WAWANG PULO, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱190.5M | 49% | High risk68 | —-0.017 |
| 24OB0187CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG C-6 OPEN CHANNEL, (PHASE 1), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱141.8M | 100% | High risk67 | —-0.064 |
| 24OB0189CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG C-6 OPEN CHANNEL, (PHASE 3), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱141.9M | 100% | High risk67 | —-0.064 |
| 24OB0188CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG C-6 OPEN CHANNEL, (PHASE 2), TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱141.8M | 100% | High risk67 | —-0.066 |
| 23OD0231CONSTRUCTION OF MULTI-PURPOSE BUILDING BRGY. PASO DE BLAS, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱190.1M | 93% | High risk66 | —-0.021 |
| 24OD0280CONSTRUCTION OF MULTI-PURPOSE BUILDING, LAON, VEINTE REALES, VALENZUELA CITY (SHFC) | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱292.2M | 20% | High risk66 | —-0.001 |
| 21OD0133CONSTRUCTION OF LEGISLATIVE AND PEOPLE'S BUILDING VALENZUELA CITY HALL, KARUHATAN, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱334.9M | 100% | High risk66 | —-0.013 |
| 24OD0281CONSTRUCTION OF MULTI-PURPOSE BUILDING, (DEPED BUILDING) MALINTA, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱219.4M | 29% | High risk66 | —-0.012 |
| 23OD0229CONSTRUCTION OF LEGISLATIVE BUILDING & PEOPLES BUILDING (PHASE II) VALENZUELA CITY HALL, BRGY. KARUHATAN, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱157.8M | 53% | High risk66 | —-0.014 |
| 21OD0130CONSTRUCTION (COMPLETION) OF PAMANTASAN NG LUNGSOD NG VALENZUELA (SATELLITE BUILDING), BARANGAY MALINTA, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱148.7M | 100% | High risk66 | —-0.068 |
| 25OD0340CONSTRUCTION OF MULTI-PURPOSE BUILDING (RESSETLEMENT PROGRAM FOR ISFS), VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱191.2M | 5% | High risk65 | —-0.006 |
| 23CC0546CONSTRUCTION OF RIVER CONTROL SYSTEM AND REHABILITATION OF WATERWAYS ALONG BALAGTAS RIVER BRGY. PANGINAY BALAGTAS, BULACAN (STA. 15+538 TO STA. 15+742) | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | High risk65 | —-0.016 |
| 24OD0029CONSTRUCTION OF REINFORCED CONCRETE BOX CULVERT ALONG 8TH STREET, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱94.2M | 100% | High risk65 | —-0.077 |
| 24OD0084CONSTRUCTION OF FLOOD CONTROL WALL ALONG POLO RIVER (PHASE 11), VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱94.1M | 100% | High risk65 | —-0.070 |
| 23OD0090CONSTRUCTION OF FLOOD CONTROL WALL ALONG LINGUNAN CREEK, VEINTE REALES, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱94.3M | 100% | High risk65 | —-0.072 |
| 21OD0132CONSTRUCTION OF FLOOD CONTROL WALL ALONG MEYCAUAYAN RIVER, BARANGAY BIGNAY, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱94.1M | 100% | High risk65 | —-0.075 |
| 24OD0083CONSTRUCTION OF FLOOD CONTROL WALL ALONG POLO RIVER (PHASE 10), VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱94.1M | 100% | High risk65 | —-0.024 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 22OD0198CONSTRUCTION OF COLOONG ROAD, BARANGAY COLOONG, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱80.8M | 100% | Medium risk55 | —-0.086 |
| 52 | 22OD0199CONSTRUCTION OF ROAD AND DRAINAGE AT COLOONG, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱80.9M | 100% | Medium risk55 | —-0.086 |
| 53 | 20OD0083IMPROVEMENT OF ROADS AND DRAINAGE OF A. CASIMIRO ST. & SIDE STREETS, BRGY. LAWAMG BATO, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱58.6M | 100% | Medium risk54 | —-0.089 |
| 54 | 24OB0215CONSTRUCTION OF SLOPE PROTECTION ALONG PINAGSAMA RIVER, TAGUIG CITY (PHASE 3) | National Capital Region | Metro Manila 1st DEO | Completed | ₱90.7M | 100% | Medium risk54 | —-0.079 |
| 55 | 24OB0216CONSTRUCTION OF SLOPE PROTECTION ALONG PINAGSAMA RIVER, TAGUIG CITY (PHASE 4) | National Capital Region | Metro Manila 1st DEO | Completed | ₱90.7M | 100% | Medium risk54 | —-0.079 |
| 56 | 21OD0179CONSTRUCTION (COMPLETION) OF VALPOLY BUILDING BARANGAY PARADA, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱38.5M | 100% | Medium risk53 | —-0.096 |
| 57 | 25DI0101CONSTRUCTION OF RIVER PROTECTION STRUCTURE ALONG STA. ROSA RIVER, (NEAR STA. ROSA-BINAN BOUNDARY BRIDGE), STA. ROSA SIDE, STA. ROSA CITY LAGUNA (PHASE 2) | Region IV-A | Laguna 2nd DEO | On-Going | ₱63.1M | 11% | Medium risk53 | —-0.021 |
| 58 | 23OD0096CONSTRUCTION OF FLOOD CONTROL WALL ALONG POLO RIVER (PHASE 3), VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱86.9M | 100% | Medium risk53 | —-0.067 |
| 59 | 19OD0181CONSTRUCTION OF FLOOD CONTROL WALL ALONG LINGAHAN CREEK, BRGY. MALANDAY, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱59.5M | 100% | Medium risk53 | —-0.084 |
| 60 | 18OD0080DREDGING OF MEYCAUAYAN RIVER, WAWANG POLO SIDE, STA. 1+260 TO STA.1+810, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱88.3M | 100% | Medium risk53 | —-0.079 |
| 61 | 19OD0185CONSTRUCTION/ REHABILITATION OF RIVERWALL ALONG TULLAHAN RIVER, STA. 7+140 TO STA. 7+394, BRGY. MARULAS, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱79M | 100% | Medium risk53 | —-0.084 |
| 62 | 19OD0198CONSTRUCTION OF FLOOD CONTROL WALL ALONG LINGAHAN CREEK, STA. 0+450 TO STA. 0+880, BRGY. COLOONG, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱55.8M | 100% | Medium risk52 | —-0.085 |
| 63 | 21OA0043CONSTRUCTION OF DPWH MALABON-NAVOTAS DEO PROPERTY (PHASE 2) MALABON CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱33.6M | 100% | Medium risk52 | —-0.097 |
| 64 | 18OD0224CONSTRUCTION OF 4 STOREY 20 CLASSROOM SCHOOL BUILDING GREGORIA DE JESUS ES, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱50M | 100% | Medium risk52 | —-0.032 |
| 65 | 21OF0068REHABILITATION OF PHILIPPINE ORTHOPEDIC CENTER BUILDING, BANAWE STREET, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱38.4M | 100% | Medium risk52 | —-0.096 |
| 66 | 20OE0175REHABILITATION / UPGRADING OF MULTI - PURPOSE BUILDING, GAT ANDRES BONIFACIO MEMORIAL | National Capital Region | North Manila DEO | Completed | ₱29M | 100% | Medium risk51 | —-0.087 |
| 67 | 19OD0180CONSTRUCTION OF FLOOD CONTROL STRUCTURE RIVERWALL ALONG POLO RIVER (OMEGA TO I. SANTIAGO), BRGY. MALINTA, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱54.9M | 100% | Medium risk51 | —-0.087 |
| 68 | 20OE0171REHABILITATION OF MULTI-PURPOSE BUILDING, ZONE 1-3, BARANGAY 1-47, MANILA | National Capital Region | North Manila DEO | Completed | ₱14.4M | 100% | Medium risk50 | —-0.044 |
| 69 | 18OD0230CONSTRUCTION OF 4 STOREY 16 CLASSROOM SCHOOL BUILDING PASOLO ELEMENTARY SCHOOL, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱53.9M | 100% | Medium risk50 | —-0.039 |
| 70 | 21OD0097REHABILITATION OF CANUMAY-MAYSAN CREEK (PHASE 2) BARANGAY CANUMAY EAST, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱47.5M | 100% | Medium risk50 | —-0.086 |
| 71 | 18OD0229CONSTRUCTION OF 4 STOREY 16 CLASSROOM SCHOOL BUILDING MALANDAY NHS, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱53.1M | 100% | Medium risk50 | —-0.041 |
| 72 | 22OF0061CONSTRUCTION OF NURSES HOME AT VETERANS MEMORIAL MEDICAL CENTER, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱19M | 100% | Medium risk49 | —-0.098 |
| 73 | 22OF0062REHABILITATION OF DUNGEON BUILDING AT VETERANS MEMORIAL MEDICAL CENTER, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱19M | 100% | Medium risk49 | —-0.099 |
| 74 | 20OD0183CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DALANDANAN, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱14.4M | 100% | Medium risk49 | —-0.101 |
| 75 | 23OD0098CONSTRUCTION OF FLOOD CONTROL WALL ALONG POLO RIVER (PHASE 5), VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱47.2M | 100% | Medium risk49 | —-0.085 |