Opening the dossier…
Opening the dossier…
Contractor dossier
37 projects on file, including joint ventures this contractor is part of.
Total projects
37
Total budget
₱304.8M
Average progress
100.0%
Completion rate
100.0%
Average risk score
39.1
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 37 | ₱304.8M | 39.1 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 21 | ₱195.3M | 38.7 | 0 | 100.0% |
| Roads | 15 | ₱104.7M | 39.1 | 0 | 100.0% |
| Flood Control and Drainage | 1 | ₱4.8M | 47.3 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Nothing to report.
No high-risk projects here.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 22DH0063CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN PABLO NORTE, STA. CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱4.8M | 100% | Medium risk51 | —-0.105 |
| 2 | 21DH0059CONSTRUCTION OF MULTI PURPOSE BUILDING (COVERED COURT) BRGY. BURLUNGAN, MAGDALENA, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱4.8M | 100% | Medium risk50 | —-0.105 |
| 3 | 21DH0061CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. SAN ISIDRO, PAGSANJAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱4.8M | 100% | Medium risk50 | —-0.104 |
| 4 | 18DH0021CONSTRUCTION OF MULTI PURPOSE COVERED COURT, BRGY. STO. ANGEL NORTE, STA. CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱6.2M | 100% | Medium risk50 | —-0.106 |
| 5 | 23DH0075CONSTRUCTION OF MULTI-PURPOSE BUILDING (RECS VILLAGE) AT BRGY. BUBUKAL, STA. CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱9.9M | 100% | Medium risk50 | —-0.106 |
| 6 | 19DH0048CONSTRUCTION OF MULTI PURPOSE BUILDING (COVERED COURT), BRGY. DUHAT, CAVINTI, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱7.2M | 100% | Medium risk49 | —-0.106 |
| 7 | 18DH0018CONSTRUCTION OF MULTI PURPOSE COVERED COURT, BRGY. BAGONG POOK, STA. MARIA, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱5.1M | 100% | Medium risk49 | —-0.095 |
| 8 | 19DH0058CONSTRUCTION OF MULTI PURPOSE BUILDING (COVERED COURT), BRGY. CALIOS, STA. CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱5M | 100% | Medium risk48 | —-0.105 |
| 9 | 20DH0120WIDENING OF BRGY. ROAD AT BRGY. BAGUMBAYAN, STA. CRUZ, LAGUNA TO BRGY. BUBUKAL, STA. CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱22.4M | 100% | Medium risk48 | —-0.052 |
| 10 | 20DH0072CONSTRUCTION OF RETAINING WALL ALONG NIA ROAD, BRGY. BUBUKAL, STA. CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱4.8M | 100% | Medium risk47 | —-0.088 |
| 11 | 18DH0117CONSTRUCTION OF FOUR (4) STOREY, SIXTEEN (16) CLASSROOM SCHOOL BUILDING, GATID E/S, STA. CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱36.9M | 100% | Medium risk47 | —-0.053 |
| 12 | 21DH0054CONCRETING OF LOCAL ROADS, BRGY. CALLIOS, SANTA CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱4.8M | 100% | Medium risk47 | —-0.107 |
| 13 | 20DH0082CONCRETING/CONSTRUCTION OF LOCAL ROAD, BRGY. CALLIOS, STA. CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱4.8M | 100% | Medium risk47 | —-0.107 |
| 14 | 22DH0018CONSTRUCTION OF ROAD, BARANGAY RIZAL, MAJAYJAY, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱17.5M | 100% | Medium risk46 | —-0.110 |
| 15 | 22DH0029CONSTRUCTION OF ROAD, BARANGAY WAWA, LUMBAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱9.6M | 100% | Medium risk46 | —-0.108 |
| 16 | 18DH0108CONSTRUCTION OF THREE (3) STOREY, NINE (9) CLASSROOM SCHOOL BUILDING, DUHAT E/S, SANTA CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱24.6M | 100% | Medium risk45 | —-0.056 |
| 17 | 18DH0115CONSTRUCTION OF FOUR (4) STOREY, EIGHT (8) CLASSROOM SCHOOL BUILDING, PANSOL E/S, PILA, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱17.2M | 100% | Medium risk45 | —-0.057 |
| 18 | 19DH0089CONSTRUCTION OF FOUR (4) STOREY, EIGHT (8) CLASSROOM SCHOOL BUILDING, FAMY NATIONAL HIGH SCHOOL, FAMY, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱18.3M | 100% | Medium risk44 | —-0.056 |
| 19 | 18DH0101CONSTRUCTION OF THREE (3) STOREY, NINE (9) CLASSROOM SCHOOL BUILDING, BUROL E/S, CAVINTI, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱24.6M | 100% | Medium risk44 | —-0.056 |
| 20 | 19DH0105CONCRETING OF BRGY. DINGIN-BRGY. LAYUGAN FARM TO MARKET ROAD, BRGY. DINGIN AND BRGY. LYUGAN, PAGSANJAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱9.9M | 100% | Medium risk43 | —-0.057 |
| 21 | 18DH0065CONCRETING OF BRGY. BUCAL FMR, BRGY. BUCAL, MAGDALENA, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱4.8M | 100% | Medium risk43 | —-0.054 |
| 22 | 18DH0067OPENING AND CONCRETING OF BRGY. SABANG FMR, BRGY. SABANG, PAGSANJAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱4.8M | 100% | Medium risk43 | —-0.056 |
| 23 | 18DH0069OPENING AND CONCRETING OF SITIO POON, BRGY. SAN ISIDRO FMR, BRGY. SAN ISIDRO, LUISIANA, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱6.8M | 100% | Medium risk42 | —-0.056 |
| 24 | 18DH0064CONCRETING OF BRGY. CONCEPCION FMR, BRGY. CONCEPCION, LUMBAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱6.8M | 100% | Medium risk42 | —-0.055 |
| 25 | 18DH0092CONCRETING OF BARANGAY KAPATALAN FMR (WITH DRAINAGE), BRGY. KAPATALAN, SINILOAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱4.8M | 100% | Medium risk42 | —-0.051 |