35 projects on file, including joint ventures this contractor is part of.
Total projects
35
Total budget
₱174.5M
Average progress
92.8%
Completion rate
71.4%
Average risk score
37.0
Medium risk on average, out of 100
Flagged as unusual
1
2.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VI | 35 | ₱174.5M | 37.0 | 1 | 92.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 28 | ₱115.3M | 36.1 | 1 | 90.9% |
| Roads | 4 | ₱28.3M | 33.0 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱7.5M | 80.5 | 0 | 100.0% |
| Flood Control and Drainage | 1 | ₱19.9M | 46.3 | 0 | 100.0% |
| Bridges | 1 | ₱3.5M | 25.8 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25GA0089COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY ARGAO, MALAY, AKLAN | Region VI | Aklan DEO | Completed | ₱7.5M | 100% | High risk81 | —-0.018 |
| 25GA0073CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT/EVACUATION CENTER), BARANGAY TALANGBAN, MADALAG, AKLAN | Region VI | Aklan DEO | On-Going | ₱4.9M | 100% | High risk71 | —-0.034 |
| 25GA0068CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT/EVACUATION CENTER), BARANGAY CABILAWAN, MADALAG, AKLAN | Region VI | Aklan DEO | On-Going | ₱4.9M | 100% | High risk71 | —-0.035 |
| 24GA0122CONSTRUCTION OF MPB (COVERED COURT) BRGY. PANIPIASON, MADALAG, AKLAN | Region VI | Aklan DEO | Completed | ₱4.9M | 100% | High risk70 | —-0.061 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 24GA0053CONSTRUCTION (COMPLETION) OF MPB BRGY. CALANGCANG, MAKATO, AKLAN | Region VI | Aklan DEO | Completed | ₱2M | 100% | Low risk24 | —-0.081 |
| 27 | 24GA0080CONSTRUCTION (COMPLETION) OF MPB CAJILO, MAKATO, AKLAN | Region VI | Aklan DEO | Completed | ₱2M | 100% | Low risk24 | —-0.082 |
| 28 | 25GA0076CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BARANGAY PALALE, BANGA, AKLAN | Region VI | Aklan DEO | Completed | ₱2M | 100% | Low risk24 | —-0.083 |
| 29 | 25GA0057CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, SAMPAGUITA STREET, BARANGAY POBLACION, BANGA, AKLAN | Region VI | Aklan DEO | On-Going | ₱1.9M | 4% | Low risk24 | —-0.019 |
| 30 | 24GA0036REHABILITATION OF ROAD BARANGAY SITIO SENTRO TO SITIO ILAYA, DUMGA, MAKATO, AKLAN | Region VI | Aklan DEO | Completed | ₱2M | 100% | Low risk22 | —-0.083 |
| 31 | 21GA0285CONSTRUCTION/COMPLETION OF 2STY4CL CALIZO NHS, BALETE, AKLAN | Region VI | Aklan DEO | Completed | ₱223.5K | 100% | Low risk14 | —-0.041 |
| 32 | 21GA0282CONSTRUCTION/COMPLETION OF 2STY4CL FATHER JULIAN C. RAGO MEMORIAL NHS, BALETE, AKLAN | Region VI | Aklan DEO | Completed | ₱391K | 100% | Low risk13 | —-0.041 |
| 33 | 21GA0286CONSTRUCTION (COMPLETION) OF 2STY4CL BALETE ES, BALETE, AKLAN | Region VI | Aklan DEO | Completed | ₱250.2K | 100% | Low risk13 | —-0.041 |
| 34 | 21GA0284CONSTRUCTION (COMPLETION) OF 2STY4CL JOSE BORROMEO LEGASPI MEMORIAL NHS, BALETE, AKLAN | Region VI | Aklan DEO | Completed | ₱354K | 100% | Low risk13 | —-0.042 |
| 35 | 21GA0283CONSTRUCTION/COMPLETION OF 2STY4CL FATHER JULIAN C. RAGO MEMORIAL NHS, BALETE, AKLAN | Region VI | Aklan DEO | Completed | ₱489K | 100% | Low risk13 | —-0.041 |