239 projects on file, including joint ventures this contractor is part of.
Total projects
239
Total budget
₱3B
Average progress
91.2%
Completion rate
77.8%
Average risk score
37.6
Medium risk on average, out of 100
Flagged as unusual
12
5.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region I | 239 | ₱3B | 37.6 | 12 | 91.2% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 106 | ₱700.5M | 28.6 | 0 | 92.8% |
| Roads | 69 | ₱531.5M | 37.8 | 4 | 90.8% |
| Flood Control and Drainage | 44 | ₱1.4B | 46.6 | 0 | 96.2% |
| GAA 2025 SSP | 6 | ₱75.1M | 90.8 | 5 | 61.1% |
| Water Provision and Storage | 5 | ₱14.6M | 25.2 | 0 | 99.1% |
| OTHER | 4 | ₱59.6M | 78.3 | 3 | 25.0% |
| GAA 2025 OO-2 | 3 | ₱185.6M | 89.4 | 0 | 95.6% |
| Bridges | 2 | ₱3.7M | 19.8 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25AJ0122CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG INGALERA RIVER, BARANGAY TALOSPATANG, MALASIQUI, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱47.2M | 55% | High risk95 | Flagged0.027 |
| 25AH0138CONSTRUCTION OF ROAD, BRGY. PALAPAD, SAN FABIAN, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱14.4M | 64% | High risk95 | Flagged0.022 |
| 25AH0137CONCRETING ROAD BARANGAY POGO CHICO, DAGUPAN CITY, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱4.8M | 49% | High risk95 | Flagged0.027 |
| 25AH0004CONSTRUCTION OF RIVERBANK PROTECTION ALONG SINUCALAN RIVER BARANGAY BACAYAO SUR, DAGUPAN CITY, PANGA | Region I | Pangasinan 2nd DEO | On-Going | ₱94.6M | 94% | High risk91 | —-0.001 |
| 25AH0007CONSTRUCTION OF RIVERBANK PROTECTION ALONG SINUCALAN RIVER, BARANGAY POGO CHICO,DAGUPAN CITY, PANGAS | Region I | Pangasinan 2nd DEO | On-Going | ₱48.5M | 92% | High risk90 | —-0.009 |
| 25AH0045CONSTRUCTION(COMPLETION) OF MULTI-PURPOSE BUILDING,BARANGAY ALITAYA,MANGALDAN,PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 58% | High risk90 | Flagged0.025 |
| 25AH0063CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING,(COVERED COURT)BARANGAY SALAPINGAO,DAGUPAN CITY,PA | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 41% | High risk89 | Flagged0.029 |
| 25AJ0055CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG ANGALACAN RIVER BANK, BARANGAY PIAS TO BARANGAY POBLACION, MAPANDAN, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱42.5M | 100% | High risk87 | —-0.013 |
| 23AH0181CONSTRUCTION OF ROAD AT BRGY. ANONANG, SAN FABIAN, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱4.8M | 0% | High risk86 | Flagged0.079 |
| 25AH0050CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING,BARANGAY BAGUINAY,MANAOAG, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱2.9M | 100% | High risk82 | —-0.021 |
| 23AH0175COMPLETION OF MULTI-PURPOSE BUILDING BIKERS DEN BRGY. LOBONG,SAN JACINTO,PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 0% | High risk78 | Flagged0.079 |
| 23AH0179CONSTRUCTION(COMPLETION) OF MULTI-PURPOSE BUILDING AT BRGY. PUGARO, DAGUPAN CITY, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱3.9M | 0% | High risk75 | Flagged0.079 |
| 23AJ0027CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG ANGALACAN RIVER, PIAS, MAPANDAN, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱48M | 100% | High risk74 | —-0.031 |
| 22AJ0004CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG AGNO RIVER, BRGY. GUELEW, SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱48.8M | 100% | High risk69 | —-0.044 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23AH0181CONSTRUCTION OF ROAD AT BRGY. ANONANG, SAN FABIAN, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱4.8M | 0% | High risk86 | Flagged0.079 |
| 23AH0175COMPLETION OF MULTI-PURPOSE BUILDING BIKERS DEN BRGY. LOBONG,SAN JACINTO,PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 0% | High risk78 | Flagged0.079 |
| 23AH0179CONSTRUCTION(COMPLETION) OF MULTI-PURPOSE BUILDING AT BRGY. PUGARO, DAGUPAN CITY, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱3.9M | 0% | High risk75 | Flagged0.079 |
| 21AH0148CONCRETING OF BRGY.BUENLAG TO BRGY.ALITAYA FMR,BRGY.BUENLAG AND BRGY.ALITAYA,MANGALDAN,PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱12.2M | 0% | Medium risk60 | Flagged0.078 |
| 21AH0160CONCRETING OF BRGY. ARAMAL FMR, BRGY. ARAMAL, SAN FABIAN, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱11.8M | 0% | Medium risk59 | Flagged0.077 |
| 21AH0150CONCRETING OF BRGY.MAASIN FMR, BRGY. MAASIN, MANGALDAN, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱13.1M | 0% | Medium risk60 | Flagged0.077 |
| 25AH0063CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING,(COVERED COURT)BARANGAY SALAPINGAO,DAGUPAN CITY,PA | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 41% | High risk89 | Flagged0.029 |
| 25AH0137CONCRETING ROAD BARANGAY POGO CHICO, DAGUPAN CITY, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱4.8M | 49% | High risk95 | Flagged0.027 |
| 25AJ0122CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG INGALERA RIVER, BARANGAY TALOSPATANG, MALASIQUI, PANGASINAN | Region I | Pangasinan 4th DEO | On-Going | ₱47.2M | 55% | High risk95 | Flagged0.027 |
| 25AH0045CONSTRUCTION(COMPLETION) OF MULTI-PURPOSE BUILDING,BARANGAY ALITAYA,MANGALDAN,PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱2.9M | 58% | High risk90 | Flagged0.025 |
| 25AH0138CONSTRUCTION OF ROAD, BRGY. PALAPAD, SAN FABIAN, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱14.4M | 64% | High risk95 | Flagged0.022 |
| 25AH0174CONCRETING OF BRGY. SALAAN FMR,BRGY. SALAAN,MANGALDAN,PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱14.5M | 80% | Medium risk44 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 101 | 19AH0231CONST'N.OF TWO(2)STOREY-EIGHT(8) CLASSROOM SB AT SANITAS ELEM.SCHOOL, SAN FABIAN,PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱18.6M | 100% | Medium risk43 | —-0.042 |
| 102 | 24AH0112CONSTRUCTION OF ROAD AND DRAINAGE, BRGY. BANAOANG, MANGALDAN, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱4.9M | 100% | Medium risk43 | —-0.090 |
| 103 | 24AH0037CONSTRUCTION OF ROAD AT BARANGAY TOCOC-ARAMAL, SAN FABIAN, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱9.8M | 100% | Medium risk43 | —-0.090 |
| 104 | 25AH0020CONSTRUCTION OF ACCESS ROAD LEADING TO THE ANGALACAN RIVER ECOTOURISM PARK,MANGALDAN,PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱9.8M | 100% | Medium risk43 | —-0.085 |
| 105 | 24AH0053CONSTRUCTION OF ROAD INCLUDING DRAINAGE SYSTEM AT BARANGAY NIBALIW, MANGALDAN, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱5M | 100% | Medium risk43 | —-0.089 |
| 106 | 24AH0042CONSTRUCTION OF ROAD AND DRAINAGE SYSTEM AT BARANGAY EMBARCADERO, MANGALDAN, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱5M | 100% | Medium risk43 | —-0.090 |
| 107 | 20AH0134CONST'N.OF MODIFIED STANDARD TWO(2)STOREY,EIGHT(8)CL,S/B AT TALOGTOG E/S MANGALDAN,PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱20M | 100% | Medium risk43 | —-0.036 |
| 108 | 19AH0238CONST'N.OF TWO(2)STOREY-FOUR(4)CLASSROOM SB AT JOSE N. JUGUILON ELEM.SCHOOL,SAN FABIAN,PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱10.2M | 100% | Medium risk43 | —-0.045 |
| 109 | 19AH0237CONST'N.OF TWO(2)STOREY-FOUR(4)CLASSROOM SB AT RABON ELEM. SCHOOL, SAN FABIAN, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱10.2M | 100% | Medium risk42 | —-0.045 |
| 110 | 24AH0111CONSTRUCTION OF ROAD AND DRAINAGE, BRGY. TALOGTOG, MANGALDAN, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱4.9M | 100% | Medium risk42 | —-0.089 |
| 111 | 23AH0038CONSTRUCTION OF ROAD AT BARANGAY SALAAN, MANGALDAN, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱4.9M | 100% | Medium risk42 | —-0.089 |
| 112 | 18AH0272CONSTRUCTION OF TWO(2)STOREY,SIX(6)CL/SB AT SUIT ELEM.SCHOOL, DAGUPAN CITY,PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱12.1M | 100% | Medium risk42 | —-0.045 |
| 113 | 21AH0149CONCRETING OF BRGY. LANAS TO BRGY. SALAY FARM-TO-MARKET ROAD,MANGALDAN,PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱14.1M | 100% | Medium risk42 | —-0.035 |
| 114 | 24AH0049CONSTRUCTION OF ROAD INCLUDING DRAINAGE SYSTEM AT BARANGAY BONUAN BINLOC, DAGUPAN CITY, PANGASINAN | Region I | Pangasinan 2nd DEO | On-Going | ₱4.9M | 6% | Medium risk42 | —-0.014 |
| 115 | 24AH0113CONSTRUCTION OF ROAD AND DRAINAGE BARANGAY POBLACION, SAN FABIAN, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱4.9M | 100% | Medium risk42 | —-0.089 |
| 116 | 23AH0035CONSTRUCTION OF ROAD AT BARANGAY NIBALIW EAST, SAN FABIAN, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱4.9M | 100% | Medium risk42 | —-0.089 |
| 117 | 24AH0114CONSTRUCTION OF ROAD AND DRAINAGE, BRGY. CAYANGA, SAN FABIAN, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱4.9M | 100% | Medium risk42 | —-0.090 |
| 118 | 23AH0083CONSTRUCTION OF ROAD, BRGY. ANGIO, SAN FABIAN, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱4.9M | 100% | Medium risk42 | —-0.091 |
| 119 | 23AH0084CONSTRUCTION OF ROAD IN BARANGAY PALAPAD, SAN FABIAN, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱4.9M | 100% | Medium risk42 | —-0.091 |
| 120 | 23AH0033CONSTRUCTION OF ROAD AT BRGY. GOMOT, SAN FABIAN, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱4.9M | 100% | Medium risk42 | —-0.091 |
| 121 | 20AH0229CONCRETING OF BRGY. LUCAO FMR, BRGY. LUCAO, DAGUPAN CITY, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱9.4M | 100% | Medium risk40 | —-0.033 |
| 122 | 17AH0316CONST'N. OF 3 STOREY,12 CL S/B (K TO 10)AT WEST CENTRAL ELEM.SCHOOL II,DAGUPAN CITY,PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱28.4M | 100% | Medium risk40 | —-0.012 |
| 123 | 19AH0243CONCRETING OF BRGY. MERMER FMR, BRGY. MERMER, MANAOAG, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱5.9M | 100% | Medium risk40 | —-0.033 |
| 124 | 19AH0242CONCRETING OF BRGY. MERMER FMR, BRGY. MERMER, MANAOAG, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱5.9M | 100% | Medium risk40 | —-0.033 |
| 125 | 24AH0150CONCRETING OF BRGY. MAASIN FMR, BRGY. MAASIN, MANGALDAN, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱9.9M | 100% | Medium risk40 | —-0.035 |