Contractor dossier
74 projects on file, including joint ventures this contractor is part of.
Total projects
74
Total budget
₱2.2B
Average progress
94.2%
Completion rate
71.6%
Average risk score
43.2
Medium risk on average, out of 100
Flagged as unusual
12
16.2% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XIII | 74 | ₱2.2B | 43.2 | 12 | 94.2% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 22 | ₱775.3M | 37.8 | 0 | 99.2% |
| Buildings and Facilities | 18 | ₱153.4M | 23.9 | 1 | 94.4% |
| Flood Control and Drainage | 12 | ₱612.1M | 40.2 | 0 | 99.0% |
| Water Provision and Storage | 7 | ₱22.7M | 16.6 | 0 | 100.0% |
| GAA 2025 SSP | 4 | ₱107.5M | 95.0 | 4 | 89.8% |
| GAA 2025 OO-2 | 4 | ₱318.2M | 91.9 | 1 | 81.0% |
| OTHER | 4 | ₱86.1M | 77.0 | 3 | 75.5% |
| GAA 2025 OO-1 | 3 | ₱105.8M | 92.4 | 3 | 71.1% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25NB0022CONSTRUCTION OF ROAD, BARANGAY POBLACION TO BARANGAY VILLANGIT, SIBAGAT, AGUSAN DEL SUR, SIBAGAT, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | On-Going | ₱19.8M | 100% | High risk95 | Flagged0.010 |
| 25NB0046CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. DEL MONTE, TALACOGON, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | On-Going | ₱28.9M | 83% | High risk95 | Flagged0.017 |
| 25NB0023CONSTRUCTION OF NRJ KOLAMBUGAN TO TOGHONGON ROAD, SIBAGAT, AGUSAN DEL SUR, SIBAGAT, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | On-Going | ₱49M | 76% | High risk95 | Flagged0.019 |
| 25NB0044CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. VILLA UNDAYON, BAYUGAN CITY, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | On-Going | ₱9.9M | 100% | High risk95 | Flagged0.010 |
| 25NC0016REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG BUTUAN CITY-TALACOGON-LORETO-VERUELA-STA. JOSEFA RD - K1342+402 - K1342+545, LA PAZ, AGUSAN DEL SUR | Region XIII | Agusan del Sur 2nd DEO | On-Going | ₱65.9M | 89% | High risk94 | Flagged0.006 |
| 25N00026MAHARLIKA HIGHWAY (AGUSAN-DAVAO SECT)- K1241+040 -K1241+498, K1242+983 - K1243+530 | Region XIII | Region XIII | On-Going | ₱30M | 49% | High risk92 | Flagged0.015 |
| 25NB0002CONSTRUCTION OF BANK PROTECTION ALONG AGUSAN RIVER (POBLACION-ESPERANZA SECTION), ESPERANZA, AGUSAN DEL SUR, ESPERANZA, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | On-Going | ₱77.1M | 80% | High risk92 | —-0.005 |
| 25NC0017REHABILITATION OF SLOPE PROTECTION STRUCTURE, ADGAWAN RIVER ALONG BUTUAN CITY-TALACOGON-LORETO-VERUELA-STA. JOSEFA ROAD, LA PAZ, AGUSAN DEL SUR | Region XIII | Agusan del Sur 2nd DEO | On-Going | ₱76.7M | 89% | High risk92 | —-0.005 |
| 25NB0033CONSTRUCTION OF BANK PROTECTION ALONG WAWA RIVER, PACKAGE 1, BARANGAY MAYGATASAN, BAYUGAN CITY, AGUSAN DEL SUR, BAYUGAN CITY, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | On-Going | ₱67.9M | 64% | High risk92 | Flagged0.000 |
| 25NB0016CONSTRUCTION OF BANK PROTECTION ALONG WAWA RIVER (DOWNSTREAM), PHASE IV, BARANGAY MAHAGCOT, ESPERANZA, AGUSAN DEL SUR, ESPERANZA, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | On-Going | ₱96.4M | 90% | High risk92 | —-0.003 |
| 25N00024MAHARLIKA HIGHWAY (AGUSAN-DAVAO SECT)- K1241+(-321) - K1241+040 | Region XIII | Region XIII | On-Going | ₱9.9M | 76% | High risk91 | Flagged0.007 |
| 25NB0056CONCRETING OF BRGY. AFGA TO BRGY. SAN ISIDRO II FMR, SIBAGAT, AGUSAN DEL SUR, SIBAGAT, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | On-Going | ₱14.6M | 71% | High risk87 | Flagged0.050 |
| 24N00228CONSTRUCTION OF EVACUATION CENTER | Region XIII | Region XIII | On-Going | ₱42.2M | 41% | High risk74 | Flagged0.022 |
| 25NC0012CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES OF BUHISAN-MANLAWIGAN-CALASIAN-PADIGUSAN ROAD CONNECTING OIL PALM, RICE AND CORN FARMS AND NATIONAL ROAD JUNCTION IN SUPPORT TO OIL PALM, RICE, AND CORN FARMS INDUS | Region XIII | Agusan del Sur 2nd DEO | Completed | ₱9.7M | 100% | High risk74 | —-0.022 |
| 25NB0006ACCESS ROAD IN SUPPORT OF MATCH FACTORY, TALACOGON, AGUSAN DEL SUR, TALACOGON, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | On-Going | ₱19.5M | 90% | High risk74 | Flagged0.005 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25NB0056CONCRETING OF BRGY. AFGA TO BRGY. SAN ISIDRO II FMR, SIBAGAT, AGUSAN DEL SUR, SIBAGAT, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | On-Going | ₱14.6M | 71% | High risk87 | Flagged0.050 |
| 24N00197DOH HEALTH FACILITIES ENHANCEMENT PROGRAM (HFEP), LGU HOSPITALS, BAYUGAN COMMUNITY HOSPITAL, AGUSAN DEL SUR | Region XIII | Region XIII | On-Going | ₱29.8M | 0% | Medium risk33 | Flagged0.026 |
| 24N00228CONSTRUCTION OF EVACUATION CENTER | Region XIII | Region XIII | On-Going | ₱42.2M | 41% | High risk74 | Flagged0.022 |
| 25NB0023CONSTRUCTION OF NRJ KOLAMBUGAN TO TOGHONGON ROAD, SIBAGAT, AGUSAN DEL SUR, SIBAGAT, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | On-Going | ₱49M | 76% | High risk95 | Flagged0.019 |
| 25NB0046CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. DEL MONTE, TALACOGON, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | On-Going | ₱28.9M | 83% | High risk95 | Flagged0.017 |
| 25N00026MAHARLIKA HIGHWAY (AGUSAN-DAVAO SECT)- K1241+040 -K1241+498, K1242+983 - K1243+530 | Region XIII | Region XIII | On-Going | ₱30M | 49% | High risk92 | Flagged0.015 |
| 25NB0044CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. VILLA UNDAYON, BAYUGAN CITY, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | On-Going | ₱9.9M | 100% | High risk95 | Flagged0.010 |
| 25NB0022CONSTRUCTION OF ROAD, BARANGAY POBLACION TO BARANGAY VILLANGIT, SIBAGAT, AGUSAN DEL SUR, SIBAGAT, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | On-Going | ₱19.8M | 100% | High risk95 | Flagged0.010 |
| 25N00024MAHARLIKA HIGHWAY (AGUSAN-DAVAO SECT)- K1241+(-321) - K1241+040 | Region XIII | Region XIII | On-Going | ₱9.9M | 76% | High risk91 | Flagged0.007 |
| 25NC0016REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG BUTUAN CITY-TALACOGON-LORETO-VERUELA-STA. JOSEFA RD - K1342+402 - K1342+545, LA PAZ, AGUSAN DEL SUR | Region XIII | Agusan del Sur 2nd DEO | On-Going | ₱65.9M | 89% | High risk94 | Flagged0.006 |
| 25NB0006ACCESS ROAD IN SUPPORT OF MATCH FACTORY, TALACOGON, AGUSAN DEL SUR, TALACOGON, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | On-Going | ₱19.5M | 90% | High risk74 | Flagged0.005 |
| 25NB0033CONSTRUCTION OF BANK PROTECTION ALONG WAWA RIVER, PACKAGE 1, BARANGAY MAYGATASAN, BAYUGAN CITY, AGUSAN DEL SUR, BAYUGAN CITY, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | On-Going | ₱67.9M | 64% | High risk92 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 21NB0035CONSTRUCTION/COMPLETION OF INFRASTRUCTURE FACILITIES/ PUBLIC BUILDING (DPWH BUILDING BAC & CONFERENCE), DPWH 1ST DEO, PATIN AY, PROSPERIDAD, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | Completed | ₱9.6M | 100% | Medium risk34 | —-0.076 |
| 52 | 22NB0052CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHILIPPINE NORMAL UNIVERSITY (PNU), PROSPERIDAD, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | Completed | ₱6.9M | 100% | Medium risk34 | —-0.078 |
| 53 | 21NB0074CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. LA PURISIMA, PROSPERIDAD, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | Completed | ₱4.9M | 100% | Medium risk33 | —-0.079 |
| 54 | 24N00197DOH HEALTH FACILITIES ENHANCEMENT PROGRAM (HFEP), LGU HOSPITALS, BAYUGAN COMMUNITY HOSPITAL, AGUSAN DEL SUR | Region XIII | Region XIII | On-Going | ₱29.8M | 0% | Medium risk33 | Flagged0.026 |
| 55 | 21NB0069IMPROVEMENT OF DEO BUILDING, BRGY. PATIN-AY, PROSPERIDAD, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | Completed | ₱4.8M | 100% | Medium risk33 | —-0.077 |
| 56 | 18NI0052CONCRETING OF SITIO ANUNANG FMR, BRGY. GAMUT, BAROBO, SURIGAO DEL SUR | Region XIII | Surigao del Sur 2nd DEO | Completed | ₱6.9M | 100% | Medium risk32 | —-0.027 |
| 57 | 19NB0060CONSTRUCTION OF CLASSROOMS (2STY 10CL), SAN VICENTE ES, PROSPERIDAD, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | Completed | ₱27.3M | 100% | Medium risk32 | —-0.032 |
| 58 | 25N00017MAHARLIKA HIGHWAY (AGUSAN-DAVAO SECT)- K1274+363-K1274+414 | Region XIII | Region XIII | On-Going | ₱4.7M | 100% | Low risk20 | —-0.053 |
| 59 | 25NB0054CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS) CY2025, UNDER AGUSAN DEL SUR 1ST DISTRICT ENGINEERING OFFICE 1. LAS NAVAS ES, PROSPERIDAD, AGUSAN DEL SUR, 2. WEST PROSPERIDAD CES, PROSPERIDAD, AGUSAN DEL SUR,3. PATIN-AY NHS, PATIN-AY, PROSPERIDAD, | Region XIII | Agusan del Sur 1st DEO | Completed | ₱2.6M | 100% | Low risk17 | —-0.040 |
| 60 | 20NB0056CONSTRUCTION OF RAINWATER COLLECTION SYSTEM, UNDER DPWH 1ST DEO, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | Completed | ₱4M | 100% | Low risk17 | —-0.046 |
| 61 | 22NB0062CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM, UNDER AGUSAN DEL SUR 1ST DEO,1. BARANGAY HALL, SAN AGUSTIN, TALACOGON, AGUSAN DEL SUR2. 26TH IB, ZAMORA, TALACOGON, AGUSAN DEL SUR3. MARBON, TALACOGON, AGUSAN DEL SUR4. BARANGAY HALL, SALVACION, PROSPERI | Region XIII | Agusan del Sur 1st DEO | Completed | ₱2.9M | 100% | Low risk17 | —-0.042 |
| 62 | 22NB0061CONSTRUCTION OF RAINWATER COLLECTION SYSTEM, UNDER DPWH AGUSAN DEL SUR 1ST DEO, 1) MAYGATASAN ELEM. SCH.,BAYUGAN CITY (2 STAINLESS TANK), 2) NATO NHS, ESPERANZA (2 STAINLESS TANK), 3) NATO ELEM. SCH.,ESPERANZA (2 STAINLESS TANK), 4)LTO BLDG., PATIN-AY, PR | Region XIII | Agusan del Sur 1st DEO | Completed | ₱4.4M | 100% | Low risk17 | —-0.040 |
| 63 | 19NB0065CONSTRUCTION OF RAINWATER COLLECTION SYSTEM, UNDER DPWH AGUSAN DEL SUR 1ST DEO | Region XIII | Agusan del Sur 1st DEO | Completed | ₱3.6M | 100% | Low risk17 | —-0.040 |
| 64 | 24NB0056CONSTRUCTION OF RAINWATER COLLECTORS IN PUBLIC FACILITIES 1. STA. MARIA ES, SIBAGAT 2. SAN VICENTE ES, SIBAGAT 3. MAGSAYSAY ES, SIBAGAT 4. CAUSWAGAN ES, SIBAGAT 5. NEW DEMAR ES, MARCELINA, BAYUGAN CITY 6. PATIN-AY, PROSPERIDAD 7. LUCENA ES, POSPERIDAD | Region XIII | Agusan del Sur 1st DEO | Completed | ₱2.9M | 100% | Low risk17 | —-0.040 |
| 65 | 19ND0005CONCRETING OF ROAD, PUROK 8, BRGY. OBRERO, BUTUAN CITY, AGUSAN DEL NORTE | Region XIII | Butuan City DEO | Completed | ₱1.9M | 100% | Low risk16 | —-0.081 |
| 66 | 23NB0046CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM, UNDER AGUSAN DEL SUR 1ST DEO (TALACOGON CES, 544TH ENG'G. BRIGADE, BAYUGAN CITY SENIOR HS-STAND ALONE, SAN TORIBIO ES, ANISLAGAN ES, DEL MONTE NHS, AZPETIA NHS, TALACOGON NHS, ILIHAN ES...) | Region XIII | Agusan del Sur 1st DEO | Completed | ₱2.3M | 100% | Low risk16 | —-0.041 |
| 67 | 19ND0100CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY BAAN RIVERSIDE, BUTUAN CITY | Region XIII | Butuan City DEO | Completed | ₱2.9M | 100% | Low risk12 | —-0.081 |
| 68 | 24NB0034CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAGUMA, BAYUGAN CITY, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | Completed | ₱3.5M | 100% | Low risk12 | —-0.080 |
| 69 | 23NB0007CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. BALIT, SAN LUIS, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | Completed | ₱4M | 100% | Low risk12 | —-0.079 |
| 70 | 23NB0008CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. SANTIAGO, SAN LUIS, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | Completed | ₱4M | 100% | Low risk12 | —-0.079 |
| 71 | 23NB0009CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. SAN LORENZO, PROSPERIDAD, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | Completed | ₱4M | 100% | Low risk12 | —-0.077 |
| 72 | 20NB0024CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAGUMA, BAYUGAN CITY, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | Completed | ₱2.9M | 100% | Low risk11 | —-0.079 |
| 73 | 19NB0049CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. ANOLINGAN, ESPERANZA, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | Completed | ₱2.4M | 100% | Low risk11 | —-0.079 |
| 74 | 19NB0052CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. DONIA MAXIMA, SAN LUIS, AGUSAN DEL SUR | Region XIII | Agusan del Sur 1st DEO | Completed | ₱2.4M | 100% | Low risk11 | —-0.079 |