Contractor dossier
108 projects on file, including joint ventures this contractor is part of.
Total projects
108
Total budget
₱3.1B
Average progress
96.8%
Completion rate
84.3%
Average risk score
44.2
Medium risk on average, out of 100
Flagged as unusual
3
2.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 60 | ₱1.3B | 41.4 | 0 | 99.9% |
| Region VII | 47 | ₱1.8B | 48.0 | 3 | 92.9% |
| Region XIII | 1 | ₱10.9M | 35.5 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 48 | ₱1.5B | 44.6 | 0 | 98.1% |
| Water Provision and Storage | 22 | ₱630.2M | 45.3 | 2 | 98.1% |
| Buildings and Facilities | 17 | ₱257.8M | 36.5 | 0 | 97.5% |
| Bridges | 12 | ₱259.2M | 45.8 | 0 | 97.4% |
| Flood Control and Drainage | 9 | ₱436.6M | 52.1 | 1 | 85.5% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23HO0281CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BRGY. STO. NIÑO, MALABUYOC, CEBU | Region VII | Cebu 7th DEO | On-Going | ₱48M | 0% | High risk79 | Flagged0.077 |
| 22HA0087CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAINWATER COLLECTOR SYSTEM - CONSTRUCTION OF BALILIHAN WATERWORKS PROJECT (PHASE II), BALILIHAN, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱67.5M | 57% | High risk67 | Flagged0.033 |
| 25HO0078CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE, PACKAGE 2, BARANGAY STO NIÑO - BARANGAY MINDANAO, MALABU | Region VII | Cebu 7th DEO | On-Going | ₱97.5M | 86% | High risk64 | —-0.012 |
| 21H00008LOCAL PROGRAM, CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/FACILITIES, CONSTRUCTION OF THE REGIONAL CULTURAL HUB, PHASE I, TAGBILARAN CITY, BOHOL PROVINCE | Region VII | Region VII | On-Going | ₱135.1M | 79% | High risk61 | —-0.001 |
| 21HG0188CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) - AS PER R.A. 11239, CONSTRUCTION AND INSTALLATION OF SOLAR STREETLIGHTS, SAFETY SIGNS AND DEVICES - K0065+000 - K0072+000, ARGAO, CEBU | Region VII | Cebu 2nd DEO | Completed | ₱96.5M | 100% | High risk60 | —-0.083 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23HO0281CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BRGY. STO. NIÑO, MALABUYOC, CEBU | Region VII | Cebu 7th DEO | On-Going | ₱48M | 0% | High risk79 | Flagged0.077 |
| 22HA0087CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAINWATER COLLECTOR SYSTEM - CONSTRUCTION OF BALILIHAN WATERWORKS PROJECT (PHASE II), BALILIHAN, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱67.5M | 57% | High risk67 | Flagged0.033 |
| 22HG0047CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM, WATER SUPPLY SYSTEM, IMPROVEMENT OF ARGAO WATER SUPPLY SYSTEM (LEVEL III), ARGAO, CEBU | Region VII | Cebu 2nd DEO | On-Going | ₱49M | 100% | Medium risk53 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 23HO0281CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BRGY. STO. NIÑO, MALABUYOC, CEBU | Region VII | Cebu 7th DEO | On-Going | ₱48M | 0% | High risk79 | Flagged0.077 |
| 2 | 22HA0087CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAINWATER COLLECTOR SYSTEM - CONSTRUCTION OF BALILIHAN WATERWORKS PROJECT (PHASE II), BALILIHAN, BOHOL | Region VII | Bohol 1st DEO | On-Going | ₱67.5M | 57% | High risk67 | Flagged0.033 |
| 3 | 25HO0078CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE, PACKAGE 2, BARANGAY STO NIÑO - BARANGAY MINDANAO, MALABU | Region VII | Cebu 7th DEO | On-Going | ₱97.5M | 86% | High risk64 | —-0.012 |
| 4 | 21H00008LOCAL PROGRAM, CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/FACILITIES, CONSTRUCTION OF THE REGIONAL CULTURAL HUB, PHASE I, TAGBILARAN CITY, BOHOL PROVINCE | Region VII | Region VII | On-Going | ₱135.1M | 79% | High risk61 | —-0.001 |
| 5 | 21HG0188CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) - AS PER R.A. 11239, CONSTRUCTION AND INSTALLATION OF SOLAR STREETLIGHTS, SAFETY SIGNS AND DEVICES - K0065+000 - K0072+000, ARGAO, CEBU | Region VII | Cebu 2nd DEO | Completed | ₱96.5M | 100% | High risk60 | —-0.083 |
| 6 | 18IF0051ROAD WIDENING PALOMPON - ISABEL - MERIDA - ORMOC ROAD K1098+000 - K1101+416 | Region VIII | Leyte 4th DEO | Completed | ₱96.5M | 100% | Medium risk58 | —-0.084 |
| 7 | 17IF0042REHAB./RECONST./UPGRADING OF DAMAGED PAVED NAT'L. RDS. INCLUDING DRAINAGE BASED ON PAVEMENT ALONG PALOMPON-ISABEL-MERIDA-ORMOC RD, K1093+000-K1094+000, K1094+235-K1095+000, K1002+000-K1103+000; K1111+153-K1111+207, K1111+225-K1111+279, K1116+749-K1116+827 | Region VIII | Leyte 4th DEO | Completed | ₱83.8M | 100% | Medium risk57 | —-0.052 |
| 8 | 17IF0044NETWORK DEVELOPMENT - IMPROVEMENT/ WIDENING OF NATIONAL ROADS - SECONDARY PALOMPON - ISABEL - MERIDA - ORMOC ROAD, K1107+093 - K1108+605, K1108+605 - K1110+134 | Region VIII | Leyte 4th DEO | Completed | ₱84.8M | 100% | Medium risk57 | —-0.052 |
| 9 | 17IA0085REHABILITATION OF ACCESS ROAD LEADING TO NAVAL PORT INCLUDING ROW, NAVAL, PROVINCE OF BILIRAN | Region VIII | Biliran DEO | Completed | ₱37.1M | 100% | Medium risk56 | —-0.053 |
| 10 | 23I00025CONSTRUCTION OF SHORELINE PROTECTION STRUCTURES - JCT. HIMAY-ANGAN - SILAGO - ABUYOG BDRY. RD. (S00228LT) - ALONG ST. BERNARD SECTION, SOUTHERN LEYTE | Region VIII | Region VIII | On-Going | ₱89.8M | 94% | Medium risk56 | —-0.014 |
| 11 | 17IF0032ASSET PRESERVATION OF NATIONAL ROADS - REHABILITATION/ RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE, COLLAPSE AND LANDSLIDE, KANANGA - TUNGONAN HOT SPRING ROAD, S00165LT, K0996+649 - K0996+849 | Region VIII | Leyte 4th DEO | Completed | ₱18.1M | 100% | Medium risk56 | —-0.060 |
| 12 | 17IF0006ASSET PRESERVATION OF NATIONAL ROAD - REHAB/ RECONSTRUCTION OF NATIONAL ROAD WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY LIBUNGAO - MATAG-OB - PALOMPON ROAD, K1001+363 - K1001+445, K1001+466 - K1001+500 | Region VIII | Leyte 4th DEO | Completed | ₱5.9M | 100% | Medium risk55 | —-0.059 |
| 13 | 17IG0038REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG DAANG MAHARLIKA (LT) K0970+900-K0971+150, K0976+900-K0977+050, K0977+520-K0977+620, K0978+100-K0978+253, K0978+710-K0978+790, K0994+020-K0994+200 | Region VIII | Leyte 5th DEO | Completed | ₱34.9M | 100% | Medium risk54 | —-0.059 |
| 14 | 23HE0117CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR PAVEMENTS STUDS ALONG CEBU SOUTH COASTAL RD K0011+(-572) TO K0016+372 (ASCENDING) AND K0015+(-1259) - K0011+598 (DES | Region VII | Cebu 1st DEO | Completed | ₱62.7M | 100% | Medium risk54 | —-0.093 |
| 15 | 17IG0008IMPROVEMENT/WIDENING OF NATIONAL ROADS - ORMOC - BAYBAY - SOUTHERN LEYTE BDRY ROAD K1094+340 - K1096+000, HINDANG, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱40M | 100% | Medium risk54 | —-0.060 |
| 16 | 23I00030CONSTRUCTION OF SHORELINE PROTECTION STRUCTURE - JCT. HIMAY-ANGAN - SILAGO - ABUYOG BDRY. RD. - (S00228LT) ALONG SAN JUAN SECTION, SOUTHERN LEYTE | Region VIII | Region VIII | On-Going | ₱85.6M | 100% | Medium risk53 | —-0.022 |
| 17 | 22HG0047CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM, WATER SUPPLY SYSTEM, IMPROVEMENT OF ARGAO WATER SUPPLY SYSTEM (LEVEL III), ARGAO, CEBU | Region VII | Cebu 2nd DEO | On-Going | ₱49M | 100% | Medium risk53 | Flagged0.001 |
| 18 | 21HC0191CONSTRUCTION/ INSTALLATION OF SOLAR STREET LIGHTS WITH SAFETY SIGN AND DEVICES IN TAGBILARAN EAST RD (TAGBILARAN-JAGNA) K0122+(076) -K0153+569, (INTERMITTENT), UBAY-TRINIDAD, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱85.1M | 100% | Medium risk52 | —-0.077 |
| 19 | 21HC0192CONSTRUCTION/ INSTALLATION OF SOLAR LIGHTS WITH SAFETY SIGN AND DEVICES IN TAGBILARAN NORTH RD (TAGBILARAN-JETAFE SECT) K0058+(-118) - K0121+954 (INTERMITTENT), JETAFE-CLARIN- INABANGA, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱85.1M | 100% | Medium risk52 | —-0.085 |
| 20 | 22IG0011CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, HINDANG BY-PASS/DIVERSION ROAD, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱48.4M | 100% | Medium risk52 | —-0.087 |
| 21 | 23IG0062NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - HINDANG BY-PASS ROAD, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱48.5M | 100% | Medium risk52 | —-0.093 |
| 22 | 20HA0083CONSTRUCTION OF WATER SUPPLY SYSTEM IN BALILIHAN, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱81.9M | 100% | Medium risk51 | —-0.027 |
| 23 | 18IG0019NETWORK DEVELOPMENT-ROAD WIDENING-SECONDARY ROADS ALONG ORMOC-BAYBAY-SOUTHERN LEYTE BDRY. ROAD K1096+290-K1097+800 | Region VIII | Leyte 5th DEO | Completed | ₱49M | 100% | Medium risk51 | —-0.093 |
| 24 | 21HC0190CONSTRUCTION/ INSTALLATION OF SOLAR LIGHTS WITH SAFETY SIGN AND DEVICES IN LOAY INTERIOR ROAD (LIR), K0122+040 - K0152+705 (INTERMITTENT), TRINIDAD, SAN MIGUEL AND DAGOHOY, BOHOL | Region VII | Bohol 2nd DEO | Completed | ₱85.1M | 100% | Medium risk51 | —-0.069 |
| 25 | 25HO0038ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF REVETMENT WALL, BARANGAY MINDANAO TO BARANGAY LABRADOR, M | Region VII | Cebu 7th DEO | On-Going | ₱48.3M | 76% | Medium risk51 | —-0.033 |