Contractor dossier
252 projects on file, including joint ventures this contractor is part of.
Total projects
252
Total budget
₱6.1B
Average progress
90.6%
Completion rate
81.0%
Average risk score
47.5
Medium risk on average, out of 100
Flagged as unusual
15
6.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 210 | ₱4.4B | 46.0 | 9 | 92.4% |
| Region III | 29 | ₱1.5B | 55.2 | 1 | 89.0% |
| Region IV-A | 12 | ₱237.4M | 54.8 | 4 | 62.1% |
| Region V | 1 | ₱18.7M | 48.1 | 1 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 96 | ₱1.5B | 42.9 | 1 | 94.1% |
| Flood Control and Drainage | 81 | ₱3.3B | 48.6 | 1 | 94.5% |
| Buildings and Facilities | 44 | ₱510.9M | 44.8 | 1 | 85.6% |
| OTHER | 15 | ₱345.4M | 53.3 | 3 | 89.1% |
| GAA 2025 SSP | 8 | ₱180.4M | 87.8 | 7 | 58.0% |
| Bridges | 6 | ₱108.8M | 45.5 | 1 | 86.5% |
| GAA 2025 OO-2 | 2 | ₱161.2M | 88.5 | 1 | 31.2% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DN0053CONSTRUCTION OF ROAD AT BLK. 21-23, 25-28, 30-32, PUROK 5, LUPANG ARENDA, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱42.8M | 44% | High risk94 | Flagged0.008 |
| 25OD0110CONSTRUCTION OF ROAD AND DRAINAGE SYSTEM ALONG BARUGO ROAD, BARANGAY 171 AND BARANGAY 175, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱48.2M | 36% | High risk92 | Flagged0.020 |
| 25OB0100CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, NICANOR IBUNA ELEMENTARY SCHOOL, SAN JUAN CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱9.8M | 85% | High risk92 | Flagged0.004 |
| 25OD0154CONSTRUCTION OF ROADS AND DRAINAGE SYSTEMS ALONG BARANGAY 171 AND BARANGAY 175, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱48.1M | 71% | High risk92 | Flagged0.011 |
| 25OD0085REHABILITATION OF MULTI-PURPOSE BUILDING, CALOOCAN NORTH ELEMENTARY SCHOOL, BARANGAY 178, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱4.9M | 22% | High risk90 | Flagged0.023 |
| 25OD0228CONSTRUCTION OF ROADS AND DRAINAGE SYSTEMS ALONG DALIAH ST., FRANVILLE 5, BRGY. 177, CALOOCAN CITY (PHASE 2) | National Capital Region | Metro Manila 3rd DEO | Completed | ₱18.9M | 100% | High risk89 | —-0.029 |
| 25OD0312CONSTRUCTION OF FLOOD CONTROL WALL ALONG BARANGAY 179, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱69.1M | 17% | High risk89 | Flagged0.000 |
| 25OC0015CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BARANGAY LA HUERTA,PARAÑAQUE CITY, METRO MANILA | National Capital Region | Metro Manila 2nd DEO | On-Going | ₱92.2M | 46% | High risk88 | —-0.003 |
| 25OD0281CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY 187, ZONE 16, DISTRICT 3, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱4.8M | 26% | High risk85 | Flagged0.020 |
| 24D00277CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - CARMONA SUPER HEALTH CENTER, CAVITE | Region IV-A | Region IV-A | On-Going | ₱11.7M | 46% | High risk83 | Flagged0.050 |
| 24CC0046CO9NSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY CATULINAN, BALIUAG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱99M | 100% | High risk80 | —-0.050 |
| 23CC0570CONSTRUCTION/IMPROVEMENT OF FLOOD CONTROL PROJECT AND REHABILITATION OF WATERWAYS ALONG BALAGTAS RIVER SAN JUAN SECTION BALAGTAS, BULACAN STA. 012+850 TO STA. 013+000 | Region III | Bulacan 1st DEO | Completed | ₱72.4M | 100% | High risk76 | —-0.005 |
| 24CC0274CONSTRUCTION OF REINFORCED CONCRETE FLOOD CONTROL STRUCTURE, BARANGAY CAMBAOG (SITIO TEODORO TO PUROK 4), BUSTOS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱77.2M | 100% | High risk76 | —-0.061 |
| 24CC0190CONSTRUCTION OF REINFORCED CONCRETE FLOOD CONTROL STRUCTURE, BARANGAY FRANCES (PUROK 4 TO PUROK 5), CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱77.2M | 100% | High risk76 | —-0.060 |
| 25CC0065CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE (PACKAGE B) AT BARANGAY PIEL (PUROK 6), BALIUAG, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱74.1M | 91% | High risk76 | —-0.030 |
| 25CC0064CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE (PACKAGE A) AT BARANGAY PIEL (PUROK 6), BALIUAG, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱74.1M | 94% | High risk76 | —-0.031 |
| 25CK0014CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (PHASE II), LA PAZ, TARLAC | Region III | Tarlac 2nd DEO | On-Going | ₱72.4M | 86% | High risk75 | —-0.028 |
| 24CC0119CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CAINGIN, MALOLOS CITY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱19.3M | 81% | High risk74 | —-0.028 |
| 24CD0279CONSTRUCTION OF SANTA MARIA-PANDI BYPASS ROAD (PHASE III), SANTA MARIA SECTION, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱48.9M | 50% | High risk73 | —-0.023 |
| 25CC0114CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SILING BATA, PANDI, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱12.5M | 100% | High risk72 | —-0.046 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24D00277CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - CARMONA SUPER HEALTH CENTER, CAVITE | Region IV-A | Region IV-A | On-Going | ₱11.7M | 46% | High risk83 | Flagged0.050 |
| 21DF0219CONCRETING OF BRGY. DIANE 2 TO BRGY. DAINE 1 FMR, BRGY. DIANE 2 AND DIANE 1, INDANG, CAVITE | Region IV-A | Cavite 1st DEO | On-Going | ₱11.6M | 0% | Medium risk43 | Flagged0.040 |
| 25OD0085REHABILITATION OF MULTI-PURPOSE BUILDING, CALOOCAN NORTH ELEMENTARY SCHOOL, BARANGAY 178, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱4.9M | 22% | High risk90 | Flagged0.023 |
| 25OD0281CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY 187, ZONE 16, DISTRICT 3, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱4.8M | 26% | High risk85 | Flagged0.020 |
| 25OD0110CONSTRUCTION OF ROAD AND DRAINAGE SYSTEM ALONG BARUGO ROAD, BARANGAY 171 AND BARANGAY 175, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱48.2M | 36% | High risk92 | Flagged0.020 |
| 24D00283CONSTRUCTION OF NEW SUPER HEALTH CENTERS / RHU BARAS SUPER HEALTH CENTER, RIZAL | Region IV-A | Region IV-A | On-Going | ₱11.7M | 10% | Medium risk44 | Flagged0.017 |
| 24CK0194CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG PARUA RIVER, BARANGAY SAN VICENTE SECTION, PHASE 1, CONCEPCION, TARLAC | Region III | Tarlac 2nd DEO | On-Going | ₱48.2M | 74% | Medium risk44 | Flagged0.014 |
| 17FN0078CONSTRUCTION OF BRIDGE, BARANGAY PALASPAS, DEL GALLEGO, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱18.7M | 100% | Medium risk48 | Flagged0.011 |
| 25OD0154CONSTRUCTION OF ROADS AND DRAINAGE SYSTEMS ALONG BARANGAY 171 AND BARANGAY 175, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱48.1M | 71% | High risk92 | Flagged0.011 |
| 25DN0053CONSTRUCTION OF ROAD AT BLK. 21-23, 25-28, 30-32, PUROK 5, LUPANG ARENDA, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱42.8M | 44% | High risk94 | Flagged0.008 |
| 25OD0309CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, UNIVERSITY OF CALOOCAN CITY (UCC) CONGRESSIONAL CAMPUS, BARANGAY 173, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱2.9M | 80% | High risk68 | Flagged0.006 |
| 25OB0100CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, NICANOR IBUNA ELEMENTARY SCHOOL, SAN JUAN CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱9.8M | 85% | High risk92 | Flagged0.004 |
| 25OD0040CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROAD LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) MALARIA ROAD TO VICTORIA WAVE SPECIAL ECONOMIC ZONE, CALOOCAN CITY, METRO MANILA | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱28.8M | 27% | Medium risk58 | Flagged0.003 |
| 24OD0224CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 144, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱29.2M | 64% | Medium risk56 | Flagged0.000 |
| 25OD0312CONSTRUCTION OF FLOOD CONTROL WALL ALONG BARANGAY 179, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱69.1M | 17% | High risk89 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 151 | 21OD0111CONSTRUCTION OF ROADS, PATHWALKS, AND DRAINAGE SYSTEMS ALONG BARANGAY 178, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱4.8M | 100% | Medium risk46 | —-0.097 |
| 152 | 20OD0034IMPROVEMENT/ UPGRADING OF FLOOD CONTROL WALL ALONG THE BANKS OF MACAWILI CREEKS, BRGY. 167, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱27.9M | 100% | Medium risk46 | —-0.088 |
| 153 | 19OD0303CONSTRUCTION OF FLOOD CONTROL WALL ALONG THE BANKS, BRGY. 167, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱28M | 100% | Medium risk46 | —-0.088 |
| 154 | 23OB0074REHABILITATION OF DRAINAGE SYSTEM ALONG ESGUERRA ST., BARANGAY PINAGBUHATAN AND VICINITY, PASIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱7.9M | 100% | Medium risk46 | —-0.089 |
| 155 | 23OB0078REHABILITATION OF DRAINAGE SYSTEM ALONG INTERIOR ROADS VILLA ALEGRE, BARANGAY PINAGBUHATAN AND VICINITY, PASIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱13.5M | 100% | Medium risk46 | —-0.089 |
| 156 | 18OB0145CONSTRUCTION OF PATEROS RIVER DARINAGE OUTFALL INCLUDING LATERALS AT BRGY. SAN PEDRO, PATEROS, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱13.7M | 100% | Medium risk46 | —-0.090 |
| 157 | 23OD0034CONSTRUCTION OF ROAD INCLUDING DRAINAGE ALONG BRGY. 188, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱19.1M | 100% | Medium risk46 | —-0.097 |
| 158 | 23OD0032CONSTRUCTION OF ROAD INCLUDING DRAINAGE ALONG CHERRY BLOSSOM SEGMENT 1, BRGY. 187, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱19.1M | 100% | Medium risk46 | —-0.097 |
| 159 | 18OD0112CONSTRUCTION OF RIVERWALL ALONG TULLAHAN RIVER, LIBIS BAESA (PHASE II), CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱27.2M | 100% | Medium risk46 | —-0.088 |
| 160 | 20OD0203CONSTRUCTION OF BOX CULVERT AT BRGY. MARULAS, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱9.6M | 100% | Medium risk46 | —-0.088 |
| 161 | 18OD0110CONSTRUCTION OF RIVERWALL ALONG TULLAHAN RIVER, BRGY. 164, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱18.2M | 100% | Medium risk46 | —-0.088 |
| 162 | 21OD0031IMPROVEMENT/ UPGRADING OF FLOOD CONTROL WALL/ RIPRAPPING ALONG BANK OF VARIOUS CREEKS IN BARANGAY 2 TO BARANGAY 4, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱19.1M | 100% | Medium risk46 | —-0.088 |
| 163 | 19OB0128CONSTRUCTION OF DRAINAGE OUTFALL INCLUDING LATERALS (PHASE II), PAGADLING CREEK, BRGY. CALZADA, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱9.1M | 100% | Medium risk46 | —-0.089 |
| 164 | 18OD0014IMPROVEMENT OF ROADS AND DRAINAGE ALONG MACOPA ST., ATIS ST., AND BIGNAY ST., BRGY. GEN. T. DE LEON, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱5.2M | 100% | Medium risk46 | —-0.097 |
| 165 | 24OD0250REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, KAYBIGA RD - K0019 + (-328) - K0019 + (-128) | National Capital Region | Metro Manila 3rd DEO | Completed | ₱9.7M | 100% | Medium risk46 | —-0.097 |
| 166 | 19OD0148IMPROVEMENT OF ROADS AND DRAINAGE ALONG MARIANO LAUREL ST,]., BRGY. PASO DE BLAS, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱6.6M | 100% | Medium risk46 | —-0.098 |
| 167 | 20OD0050IMPROVEMENT/ REHABILITATION OF DRAINAGE SYSTEM ALONG TANDANG SORA EXTENSION, BRGY. 163, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱5.7M | 100% | Medium risk46 | —-0.098 |
| 168 | 21OB0064REHABILITATION OF ONYX ROAD, ORTIGAS CENTER, PASIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱7M | 100% | Medium risk46 | —-0.098 |
| 169 | 22OD0097CONSTRUCTION OF ROAD INCLUDING DRAINAGE SYSTEM ALONG ROAD 8, BRGY. 164, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱9.6M | 100% | Medium risk46 | —-0.100 |
| 170 | 22OD0150CONSTRUCTION OF ROAD INCLUDING DRAINAGE SYSTEM ALONG REPARO ST., BRGY. 78, CONNECTING TO MAC ARTHUR HIGHWAY, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱9.5M | 100% | Medium risk46 | —-0.100 |
| 171 | 21OD0152CONSTRUCTION OF ROADS AND DRAINAGE SYSTEMS ALONG BARANGAY 138 AND 139, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱9.5M | 100% | Medium risk46 | —-0.100 |
| 172 | 20OA0006CONST. OF RIVERWALL AND ROAD DIKE ALONG BATASAN RIVER (PHASE 1) BRGY. DAMPALIT, MAL. CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱36.1M | 100% | Medium risk46 | —-0.085 |
| 173 | 25OB0196REHABILITATION OF ROAD AT BARANGAY MAHARLIKA, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | On-Going | ₱9.2M | 57% | Medium risk46 | —-0.056 |
| 174 | 24OB0294REHABILITATION OF ROAD AT BARANGAY MAHARLIKA, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱9M | 100% | Medium risk46 | —-0.098 |
| 175 | 25OD0333CONSTRUCTION OF ROADS AND DRAINAGE SYSTEMS ALONG TAAS EXTENSION, BRGY. 171, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | On-Going | ₱9.5M | 0% | Medium risk46 | —-0.038 |