Opening the dossier…
Opening the dossier…
Contractor dossier
2 projects on file, including joint ventures this contractor is part of.
Total projects
2
Total budget
₱214.9M
Average progress
100.0%
Completion rate
100.0%
Average risk score
61.3
High risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XI | 2 | ₱214.9M | 61.3 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Bridges, Roads | 1 | ₱131.4M | 66.2 | 0 | 100.0% |
| Roads | 1 | ₱83.5M | 56.5 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 18L00080IMPVT./CONC. OF NRJ SAGAYEN-SONLON RD INCLUDING CONST. OF MADGAO BRIDGE CONNECTING ASUNCION OVERLAND | Region XI | Region XI | Completed | ₱131.4M | 100% | High risk66 | —-0.020 |
| 2 | 18L00049CONC./WIDENING OF JCT. MATTI (ALONG DAVAO-COT. RD)-JCT. AURORA (ALONG DIGOS MAKAR RD) BYPASS RD INCL | Region XI | Region XI | Completed | ₱83.5M | 100% | Medium risk56 | —-0.059 |