Contractor dossier
177 projects on file, including joint ventures this contractor is part of.
Total projects
177
Total budget
₱8.1B
Average progress
96.7%
Completion rate
89.3%
Average risk score
50.0
Medium risk on average, out of 100
Flagged as unusual
7
4.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region I | 115 | ₱4.5B | 49.4 | 2 | 97.4% |
| National Capital Region | 44 | ₱1.5B | 47.6 | 0 | 100.0% |
| Region VI | 11 | ₱949.4M | 63.4 | 3 | 74.1% |
| Region VII | 4 | ₱757.2M | 60.1 | 1 | 97.8% |
| Region III | 3 | ₱307.7M | 47.4 | 1 | 99.2% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 78 | ₱3.7B | 51.3 | 3 | 98.1% |
| Roads | 61 | ₱2.7B | 47.6 | 0 | 96.8% |
| Buildings and Facilities | 19 | ₱686.8M | 45.3 | 1 | 95.7% |
| OTHER | 7 | ₱463.3M | 68.2 | 2 | 90.3% |
| Bridges | 7 | ₱259.9M | 50.6 | 1 | 85.7% |
| Water Provision and Storage | 3 | ₱157.7M | 46.7 | 0 | 100.0% |
| Bridges, Roads | 2 | ₱141.6M | 60.9 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24G00009CONSTRUCTION OF FLOOD CONTROL STRUCTURE IN MAAYON, CAPIZ | Region VI | Region VI | On-Going | ₱145.5M | 81% | High risk83 | Flagged0.025 |
| 24C00233CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRA/FACILITIES-CONST. OF SEAWALL PROTECTION STRUCTURES (PHASE I), ORION, BATAAN, PROVINCE OF BATAAN | Region III | Region III | On-Going | ₱241.2M | 98% | High risk80 | Flagged0.003 |
| 23A00151CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LINGAYEN-BINMALEY BYPASS ROAD, BINMALEY SIDE, PANGASINAN | Region I | Region I | On-Going | ₱100.4M | 50% | High risk79 | Flagged0.034 |
| 24GD0043CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG PANAY/MAMBUSAO RIVER BASIN, AMBILAY RIVER CONTROL, PANITAN, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱67.7M | 58% | High risk75 | Flagged0.006 |
| 24GD0039CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG PANAY/MAMBUSAO RIVER BASIN, AGBALO RIVER CONTROL, PANAY, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱72.4M | 71% | High risk75 | Flagged0.003 |
| 24GD0040CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG PANAY/MAMBUSAO RIVER BASIN, PANITAN RIVER CONTROL (DOWNSTREAM), PANITAN, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱68.9M | 80% | High risk75 | —-0.002 |
| 17A00043CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS ALONG POBLACION-SABANGAN ROAD LEADING TO UMBRELLA ROCKS AND ABAGATANEN WHITE BEACH, INCLUDING BRIDGE, AGNO, PANGASINAN | Region I | Region I | Completed | ₱92.6M | 100% | High risk74 | —-0.018 |
| 17AH0173CONSTRUCTION OF WATER SUPPLY SYSTEM AT BRGYS. BOLO & DULIG, LABRADOR, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱27.5M | 100% | High risk70 | —-0.023 |
| 17AG0062IMPROVEMENT/WIDENING OF NATIONAL ROADS SECONDARY ROADS INCLUDING DRAINAGE ALAMINOS-LUCAP RD-(KO323+4 | Region I | Pangasinan 1st DEO | Completed | ₱32.5M | 100% | High risk70 | —-0.025 |
| 17AG0061OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE-SECONDARY ROADS PANGASINAN-ZAMBALES RD -(KO268+000-KO | Region I | Pangasinan 1st DEO | Completed | ₱40.7M | 100% | High risk69 | —-0.025 |
| 17A00011ASSET PRESERVATION PREVENTIVE MAINTENANCE BASED ON PAVEMENT MANAGEMENT SYSTEM / HIGHWAY DEVELOPMENT AND MANAGEMENT-4 (HDM-4) MANGALDAN-MANAOAG-BINALONAN ROAD,K0191+027-K0194+000; K0194+000-K0195+000; K0195+000-K0196+000; K0196+000-K0196+332; K0196+372-K01 | Region I | Region I | Completed | ₱101.6M | 100% | High risk68 | —-0.042 |
| 24G00007CONSTRUCTION OF RIVER CONTROL AT BARANGAY POBLACION ILAYA TO POBLACION ILAWOD, MAAYON, CAPIZ | Region VI | Region VI | On-Going | ₱146.7M | 74% | High risk68 | —-0.005 |
| 18OD0181CONSTRUCTION OF REVETMENT WALL ALONG POLO RIVER, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱210.6M | 100% | High risk67 | —-0.051 |
| 17A00014CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, ACCESS ROAD LEADING TO ANGEL CAVE AND ALICUPEN BEACH, BANI, PANGASINAN 1ST LD | Region I | Region I | Completed | ₱96.5M | 100% | High risk67 | —-0.037 |
| 17AJ0037CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG MARUSAY RIVER AT BRGY. TALIBAEW AND BRGY. BUENLAG, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱40.2M | 100% | High risk65 | —-0.045 |
| 17AJ0057CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG MARUSAY RIVER AT BRGY. GABON, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱29.5M | 100% | High risk65 | —-0.045 |
| 17AJ0065CONSTRUCTION OF PROTECTION WORKS ALONG AGNO RIVER, GUELEW SECTION, SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱28.9M | 100% | High risk65 | —-0.046 |
| 17AJ0026CONSTRUCTION OF PROTECTION WORKS ALONG SINUCALAN RIVER, DALONGUE SECTION, STA. BARBARA, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱27.4M | 100% | High risk65 | —-0.045 |
| 17AJ0017CONSTRUCTION OF PROTECTION WORKS ALONG MARUSAY RIVER, BRGY. NALSIAN, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱24.6M | 100% | High risk65 | —-0.046 |
| 17AJ0025CONSTRUCTION OF PROTECTION WORKS ALONG MARUSAY RIVER, POBLACION, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱23M | 100% | High risk65 | —-0.046 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 21H00075AVIATION INFRASTRUCTURE PROGRAM, LOCALLY-FUNDED PROJECTS, CONSTRUCTION/REHABILITATION AND IMPROVEMENT OF OTHER TRANSPORTATION INFRASTRUCTURE-AVIATION, SIQUIJOR AIRPORT, SIQUIJOR | Region VII | Region VII | On-Going | ₱435M | 91% | High risk62 | Flagged0.052 |
| 23A00151CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LINGAYEN-BINMALEY BYPASS ROAD, BINMALEY SIDE, PANGASINAN | Region I | Region I | On-Going | ₱100.4M | 50% | High risk79 | Flagged0.034 |
| 24G00009CONSTRUCTION OF FLOOD CONTROL STRUCTURE IN MAAYON, CAPIZ | Region VI | Region VI | On-Going | ₱145.5M | 81% | High risk83 | Flagged0.025 |
| 24A00363SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF BRIDGE CONNECTING BARANGAY PANGAPISAN NORTH AND BARANGAY CAPANDANAN, LINGAYEN, PANGASINAN | Region I | Region I | On-Going | ₱93.6M | 0% | High risk62 | Flagged0.017 |
| 24GD0043CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG PANAY/MAMBUSAO RIVER BASIN, AMBILAY RIVER CONTROL, PANITAN, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱67.7M | 58% | High risk75 | Flagged0.006 |
| 24GD0039CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG PANAY/MAMBUSAO RIVER BASIN, AGBALO RIVER CONTROL, PANAY, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱72.4M | 71% | High risk75 | Flagged0.003 |
| 24C00233CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRA/FACILITIES-CONST. OF SEAWALL PROTECTION STRUCTURES (PHASE I), ORION, BATAAN, PROVINCE OF BATAAN | Region III | Region III | On-Going | ₱241.2M | 98% | High risk80 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 16OE0126MFO-2 FLOOD MANAGEMENT SERVICES-CONSTRUCTION OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-BANK IMPROVEMENT (STEEL SHEET PILE), ESTERO DE SUNOG APOG, MANILA CITY, TONDO, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱46.5M | 100% | Medium risk48 | —-0.063 |
| 77 | 22OD0191CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 143, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱4.8M | 100% | Medium risk48 | —-0.102 |
| 78 | 18AG0102CONVERGENCE AND SPECIAL SUPPORT-CONST./IMPROV T OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS POBLACION SAN JOSE-NAMAGBAGAN-IMBO TONDOL ROAD LEADING TO TONDOL BEACH, INCL. BRIDGE, ANDA, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱49M | 100% | Medium risk48 | —-0.057 |
| 79 | 22OD0151CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 159, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱4.8M | 100% | Medium risk48 | —-0.102 |
| 80 | 22OD0229CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 156, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱4.8M | 100% | Medium risk48 | —-0.103 |
| 81 | 20OD0201IMPROVEMENT OF DRAINAGE AND REHABILITATION OF ROADS ALONG 6TH AVENUE, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱33.6M | 100% | Medium risk47 | —-0.097 |
| 82 | 21OD0108REHABILITATION OF ROADS AND DRAINAGE ALONG BARANGAYS 40, 41, 45 & 48, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱28.7M | 100% | Medium risk47 | —-0.099 |
| 83 | 18AJ0109REHABILITATION/RECONSTRUCTION OF SLOPE PROTECTION WORKS ALONG INGALERA RIVER AT BRGY. LUMBANG, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱29.1M | 100% | Medium risk47 | —-0.017 |
| 84 | 18AJ0110REHABILITATION/RECONSTRUCTION OF SLOPE PROTECTION WORKS ALONG INGALERA RIVER AT BRGY. LONGOS, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱29.2M | 100% | Medium risk47 | —-0.017 |
| 85 | 18AG0112BRIDGE-WIDENING OF PERMANENT BRIDGES-QUARTEL BR. (B00715LZ) ALONG PANGASINAN-ZAMBALES ROAD KO339+070, BRGY. POBLACION, SUAL, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱5.6M | 100% | Medium risk46 | —-0.047 |
| 86 | 19A00056REHABILITATION/ MAJOR REPAIR OF PERMANENT BRIDGES, BANOG BR. 1 (B04486LZ) ALONG PANGASINAN-ZAMBALES RD. (PHASE II) | Region I | Region I | Completed | ₱13.1M | 100% | Medium risk46 | —-0.045 |
| 87 | 18AJ0051CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG INGALERA RIVER AT DOYONG-SONGKOY, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱40.8M | 100% | Medium risk46 | —-0.070 |
| 88 | 18AJ0050CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG INGALERA RIVER AT BRGY. NANSANGAAN, MALASIQUI, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱40.8M | 100% | Medium risk46 | —-0.071 |
| 89 | 20OD0200IMPROVEMENT OF ROADS AND DRIANAGE ALONG NADURATA STREET, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱14.4M | 100% | Medium risk46 | —-0.101 |
| 90 | 18AG0163BRIDGE-REPLACEMENT OF PERMANENT WEAK BRIDGES CATO BRIDGE (BO690LZ) ALONG PANGASINAN-ZAMABLES ROAD (PHASE 1) AT INFANTA, PANGASINAN KO271+260 | Region I | Pangasinan 1st DEO | Completed | ₱9.3M | 100% | Medium risk46 | —-0.049 |
| 91 | 19AG0083CONSTRUCTION OF FLOOD CONTROL MITIGATION FACILITIES ALONG NAYOM RIVER, BRGY. MAYA, INFANTA, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱46.5M | 100% | Medium risk46 | —-0.063 |
| 92 | 18OB0258CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ALONG C-6, TAGUIG-PATEROS, TAGUIG CITY | National Capital Region | Metro Manila 1st DEO | Completed | ₱18.3M | 100% | Medium risk46 | —-0.095 |
| 93 | 21OD0053UPGRADING/ REHABILITATION OF ROADS AND DRAINAGE BRGYS. 61, 62 & 71, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱19.1M | 100% | Medium risk46 | —-0.100 |
| 94 | 18OD0050CONSTRUCTION / REHABILITATION OF RIVERWALL ALONG TULLAHAN RIVER, STA. 4+896 - 4+989, RIGHT BANK, BRGY. MARULAS, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱34.5M | 100% | Medium risk46 | —-0.087 |
| 95 | 19OA0035CONST. OF RIVERWALL ALONG MALABON-TULLAHAN RIVER (PHASE II) BRGY. NBBS DAGAT-DAGATAN NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱32.4M | 100% | Medium risk46 | —-0.088 |
| 96 | 19AG0082CONSTRUCTION OF FLOOD CONTROL MITIGATION FACILITIES ALONG BAYAMBANG RIVER, BARANGAY BAYAMBANG, INFANTA, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱46.5M | 100% | Medium risk46 | —-0.063 |
| 97 | 19OD0228CONSTRUCTION OF CONCRETE CANAL (OPEN CHANNEL) ALONG MAYER'S CREEK, BRGY. LINGUNAN, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱32M | 100% | Medium risk46 | —-0.080 |
| 98 | 18OD0049CONSTRUCTION / REHABILITATION OF RIVERWALL ALONG TULLAHAN RIVER, STA. 5+816 - 5+920, BRGY. MARULAS, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱36.4M | 100% | Medium risk46 | —-0.087 |
| 99 | 18OD0056CONSTRUCTION OF ROAD DIKE ALONG THE MEYCAUAYAN RIVER, POLO AREA, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱45.4M | 100% | Medium risk46 | —-0.087 |
| 100 | 21OD0119REHABILITATION OF MAYPAJO CREEK, BARANGAYS 34 & 35, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱31.6M | 100% | Medium risk46 | —-0.089 |