Contractor dossier
177 projects on file, including joint ventures this contractor is part of.
Total projects
177
Total budget
₱8.1B
Average progress
96.7%
Completion rate
89.3%
Average risk score
50.0
Medium risk on average, out of 100
Flagged as unusual
7
4.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region I | 115 | ₱4.5B | 49.4 | 2 | 97.4% |
| National Capital Region | 44 | ₱1.5B | 47.6 | 0 | 100.0% |
| Region VI | 11 | ₱949.4M | 63.4 | 3 | 74.1% |
| Region VII | 4 | ₱757.2M | 60.1 | 1 | 97.8% |
| Region III | 3 | ₱307.7M | 47.4 | 1 | 99.2% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 78 | ₱3.7B | 51.3 | 3 | 98.1% |
| Roads | 61 | ₱2.7B | 47.6 | 0 | 96.8% |
| Buildings and Facilities | 19 | ₱686.8M | 45.3 | 1 | 95.7% |
| OTHER | 7 | ₱463.3M | 68.2 | 2 | 90.3% |
| Bridges | 7 | ₱259.9M | 50.6 | 1 | 85.7% |
| Water Provision and Storage | 3 | ₱157.7M | 46.7 | 0 | 100.0% |
| Bridges, Roads | 2 | ₱141.6M | 60.9 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24G00009CONSTRUCTION OF FLOOD CONTROL STRUCTURE IN MAAYON, CAPIZ | Region VI | Region VI | On-Going | ₱145.5M | 81% | High risk83 | Flagged0.025 |
| 24C00233CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRA/FACILITIES-CONST. OF SEAWALL PROTECTION STRUCTURES (PHASE I), ORION, BATAAN, PROVINCE OF BATAAN | Region III | Region III | On-Going | ₱241.2M | 98% | High risk80 | Flagged0.003 |
| 23A00151CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LINGAYEN-BINMALEY BYPASS ROAD, BINMALEY SIDE, PANGASINAN | Region I | Region I | On-Going | ₱100.4M | 50% | High risk79 | Flagged0.034 |
| 24GD0043CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG PANAY/MAMBUSAO RIVER BASIN, AMBILAY RIVER CONTROL, PANITAN, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱67.7M | 58% | High risk75 | Flagged0.006 |
| 24GD0039CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG PANAY/MAMBUSAO RIVER BASIN, AGBALO RIVER CONTROL, PANAY, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱72.4M | 71% | High risk75 | Flagged0.003 |
| 24GD0040CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG PANAY/MAMBUSAO RIVER BASIN, PANITAN RIVER CONTROL (DOWNSTREAM), PANITAN, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱68.9M | 80% | High risk75 | —-0.002 |
| 17A00043CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS ALONG POBLACION-SABANGAN ROAD LEADING TO UMBRELLA ROCKS AND ABAGATANEN WHITE BEACH, INCLUDING BRIDGE, AGNO, PANGASINAN | Region I | Region I | Completed | ₱92.6M | 100% | High risk74 | —-0.018 |
| 17AH0173CONSTRUCTION OF WATER SUPPLY SYSTEM AT BRGYS. BOLO & DULIG, LABRADOR, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱27.5M | 100% | High risk70 | —-0.023 |
| 17AG0062IMPROVEMENT/WIDENING OF NATIONAL ROADS SECONDARY ROADS INCLUDING DRAINAGE ALAMINOS-LUCAP RD-(KO323+4 | Region I | Pangasinan 1st DEO | Completed | ₱32.5M | 100% | High risk70 | —-0.025 |
| 17AG0061OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE-SECONDARY ROADS PANGASINAN-ZAMBALES RD -(KO268+000-KO | Region I | Pangasinan 1st DEO | Completed | ₱40.7M | 100% | High risk69 | —-0.025 |
| 17A00011ASSET PRESERVATION PREVENTIVE MAINTENANCE BASED ON PAVEMENT MANAGEMENT SYSTEM / HIGHWAY DEVELOPMENT AND MANAGEMENT-4 (HDM-4) MANGALDAN-MANAOAG-BINALONAN ROAD,K0191+027-K0194+000; K0194+000-K0195+000; K0195+000-K0196+000; K0196+000-K0196+332; K0196+372-K01 | Region I | Region I | Completed | ₱101.6M | 100% | High risk68 | —-0.042 |
| 24G00007CONSTRUCTION OF RIVER CONTROL AT BARANGAY POBLACION ILAYA TO POBLACION ILAWOD, MAAYON, CAPIZ | Region VI | Region VI | On-Going | ₱146.7M | 74% | High risk68 | —-0.005 |
| 18OD0181CONSTRUCTION OF REVETMENT WALL ALONG POLO RIVER, VALENZUELA CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱210.6M | 100% | High risk67 | —-0.051 |
| 17A00014CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, ACCESS ROAD LEADING TO ANGEL CAVE AND ALICUPEN BEACH, BANI, PANGASINAN 1ST LD | Region I | Region I | Completed | ₱96.5M | 100% | High risk67 | —-0.037 |
| 17AJ0037CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG MARUSAY RIVER AT BRGY. TALIBAEW AND BRGY. BUENLAG, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱40.2M | 100% | High risk65 | —-0.045 |
| 17AJ0057CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG MARUSAY RIVER AT BRGY. GABON, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱29.5M | 100% | High risk65 | —-0.045 |
| 17AJ0065CONSTRUCTION OF PROTECTION WORKS ALONG AGNO RIVER, GUELEW SECTION, SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱28.9M | 100% | High risk65 | —-0.046 |
| 17AJ0026CONSTRUCTION OF PROTECTION WORKS ALONG SINUCALAN RIVER, DALONGUE SECTION, STA. BARBARA, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱27.4M | 100% | High risk65 | —-0.045 |
| 17AJ0017CONSTRUCTION OF PROTECTION WORKS ALONG MARUSAY RIVER, BRGY. NALSIAN, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱24.6M | 100% | High risk65 | —-0.046 |
| 17AJ0025CONSTRUCTION OF PROTECTION WORKS ALONG MARUSAY RIVER, POBLACION, CALASIAO, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱23M | 100% | High risk65 | —-0.046 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 21H00075AVIATION INFRASTRUCTURE PROGRAM, LOCALLY-FUNDED PROJECTS, CONSTRUCTION/REHABILITATION AND IMPROVEMENT OF OTHER TRANSPORTATION INFRASTRUCTURE-AVIATION, SIQUIJOR AIRPORT, SIQUIJOR | Region VII | Region VII | On-Going | ₱435M | 91% | High risk62 | Flagged0.052 |
| 23A00151CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LINGAYEN-BINMALEY BYPASS ROAD, BINMALEY SIDE, PANGASINAN | Region I | Region I | On-Going | ₱100.4M | 50% | High risk79 | Flagged0.034 |
| 24G00009CONSTRUCTION OF FLOOD CONTROL STRUCTURE IN MAAYON, CAPIZ | Region VI | Region VI | On-Going | ₱145.5M | 81% | High risk83 | Flagged0.025 |
| 24A00363SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF BRIDGE CONNECTING BARANGAY PANGAPISAN NORTH AND BARANGAY CAPANDANAN, LINGAYEN, PANGASINAN | Region I | Region I | On-Going | ₱93.6M | 0% | High risk62 | Flagged0.017 |
| 24GD0043CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG PANAY/MAMBUSAO RIVER BASIN, AMBILAY RIVER CONTROL, PANITAN, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱67.7M | 58% | High risk75 | Flagged0.006 |
| 24GD0039CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG PANAY/MAMBUSAO RIVER BASIN, AGBALO RIVER CONTROL, PANAY, CAPIZ | Region VI | Capiz 1st DEO | On-Going | ₱72.4M | 71% | High risk75 | Flagged0.003 |
| 24C00233CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRA/FACILITIES-CONST. OF SEAWALL PROTECTION STRUCTURES (PHASE I), ORION, BATAAN, PROVINCE OF BATAAN | Region III | Region III | On-Going | ₱241.2M | 98% | High risk80 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 151 | 22AG0001ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - ALAMINOS-BOLINAO RD - K0340 + 000 - K0340 + 246 | Region I | Pangasinan 1st DEO | Completed | ₱24.1M | 100% | Medium risk43 | —-0.083 |
| 152 | 18AG0199CONSTRUCTION OF STANDARD 2-STOREY 4-CLASSROOM SCHOOL BUILDING @ LINMANSANGAN ES, ALAMINOS CITY, PANGASINAN (9.5M X 23M) AT BRGY. LINMANSANGAN, ALAMINOS CITY, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱8.9M | 100% | Medium risk43 | —-0.039 |
| 153 | 18AG0103NETWORK DEVELOPMENT-OFF CARRIAGEWAY IMPROVEMENT-TERTIARY ROADS-BANI-AGNO ROAD (KO341+000-KO344+000, KO344+783-KO345+000 AT AGNO, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱26M | 100% | Medium risk43 | —-0.080 |
| 154 | 21A00070CONSTRUCTION OF MISSING LINKS/ NEW ROADS- BOLINAO - DASOL COASTAL ROAD, PANGASINAN | Region I | Region I | Completed | ₱26M | 100% | Medium risk43 | —-0.080 |
| 155 | 19A00055CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, ACCESS ROAD LEADING TO ANGEL CAVE AND ALICUPEN BEACH, BANI, PANGASINAN | Region I | Region I | Completed | ₱19.3M | 100% | Medium risk43 | —-0.081 |
| 156 | 19A00052CONSTRUCTION / IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES, BRGY. COLAYO ROAD CONNECTING ALAMINOS ROAD IN SUPPORT OF CASSAVA, PEANUT, AND CORN PRODUCTION AND PROCESSING, BANI PANGASINAN | Region I | Region I | Completed | ₱21.2M | 100% | Medium risk43 | —-0.082 |
| 157 | 18AG0044REHAB./RECONSTN. OF NATL. ROADS W/ SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS BURGOS AGNO ROAD KO303+527-KO303+600_KO308+279-KO308+385 AT BANGAN ODA, AGNO PANGASINAN AND CARANGLAAN, MABINI, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱24.2M | 100% | Medium risk43 | —-0.082 |
| 158 | 18AG0017REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, SECONDARY ROADS ALAMINOS-BOLINAO ROAD (K0351+100 - K0351+170) AT CULANG, BOLINAO, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱18.6M | 100% | Medium risk43 | —-0.083 |
| 159 | 23AG0001ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - ALAMINOS-BOLINAO RD - K0328 + 000 - K0329 + 205 AT ALAMINOS CITY, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱12.1M | 100% | Medium risk42 | —-0.082 |
| 160 | 18AG0195CONSTRUCTION OF STANDARD 2-STOREY 4-CLASSROOM SCHOOL BUILDING @ QUIBUAR ES, ALAMINOS CITY, PANGASINAN (9.5M X 23M) AT BRGY. QUIBUAR, ALAMINOS CITY, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱8.9M | 100% | Medium risk42 | —-0.039 |
| 161 | 18AG0196CONSTRUCTION OF STANDARD 2-STOREY 4-CLASSROOM SCHOOL BUILDING @ TANGCARANG ES, ALAMINOS CITY, PANGASINAN (9.5M X 23M) AT BRGY. TANGCARANG, ALAMINOS CITY, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱8.9M | 100% | Medium risk42 | —-0.039 |
| 162 | 19AG0066CONSTRUCTION/ IMPROVEMENT OF POBLACION SAN JOSE NAMAGBANGAN-IMBO TONDOL ROAD LEADING TO TONDOL BEACH, ANDA, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱9.3M | 100% | Medium risk42 | —-0.085 |
| 163 | 23AG0069BASIC INFRASTRUCTURE PROGRAM - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, SITIO RIVERSIDE, ILOG-MALINO, BOLINAO, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱4.9M | 100% | Medium risk41 | —-0.080 |
| 164 | 18AG0229CONSTRUCTION OF STANDARD 2-STOREY 8-CLASSROOM SCHOOL BUILDING @ LUCAP ES, ALAMINOS CITY, PANGASINAN (9.5M X 46.00M) AT BRGY. LUCAP, ALAMINOS CITY, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱17M | 100% | Medium risk41 | —-0.037 |
| 165 | 18AG0205CONSTRUCTION OF STANDARD 2-STOREY 8-CLASSROOM SCHOOL BUILDING @ BUED ES, ALAMINOS CITY, PANGASINAN (9.5M X 46.00M) AT BRGY. BUED, ALAMINOS CITY, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱17M | 100% | Medium risk41 | —-0.038 |
| 166 | 18AG0189CONSTRUCTION OF STANDARD 2-STOREY 4-CLASSROOM SCHOOL BUILDING @ AMANDIEGO ES, ALAMINOS CITY, PANGASINAN (9.5M X 23M) AT BRGY. AMANDIEGO, ALAMINOS CITY, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱9.1M | 100% | Medium risk41 | —-0.038 |
| 167 | 18AG0197CONSTRUCTION OF STANDARD 2-STOREY 4-CLASSROOM SCHOOL BUILDING@ TAWINTAWIN ES, ALAMINOS CITY, PANGASINAN (9.5M X 23M) AT BRGY. TAWINTAWIN, ALAMINOS CITY, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱8.9M | 100% | Medium risk41 | —-0.039 |
| 168 | 19AH0214CONCRETING OF SITIO LOCOT, BRGY. BAUG FMR, BRGY. BAUG URBIZTONDO, PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱11.6M | 100% | Medium risk40 | —-0.036 |
| 169 | 19AH0213CONCRETING OF BRGY. REAL-BRGY.CAMAMBUGAN FMR, BRGY.REAL AND BRGY.CAMAMBUGAN, URBIZTONDO,PANGASINAN | Region I | Pangasinan 2nd DEO | Completed | ₱11.6M | 100% | Medium risk40 | —-0.036 |
| 170 | 19AH0212CONCRETING OF BRGY. ANGATEL-BRGY.SALAVANTE FMR,BRGY.ANGATEL AND BRGY.SALAVANTE, URBIZTONDO,PANGASINA | Region I | Pangasinan 2nd DEO | Completed | ₱11.6M | 100% | Medium risk40 | —-0.033 |
| 171 | 18AG0190CONSTRUCTION OF STANDARD 2-STOREY 4-CLASSROOM SCHOOL BUILDING @ AMANGBANGAN ES, ALAMINOS CITY, PANGASINAN (99.5M X23M) AT BRGY. AMANGBANGAN, ALAMINOS CITY, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱9.1M | 100% | Medium risk40 | —-0.039 |
| 172 | 18AG0219CONSTRUCTION OF STANDARD 2-STOREY 6-CLASSROOM SCHOOL BUILDING @ ARNEDO NHS, BOLINAO, PANGASINAN (9.5M X32M) AT BRGY. ARNEDO, BOLINAO, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱11.6M | 100% | Medium risk40 | —-0.039 |
| 173 | 18AG0226CONSTRUCTION OF STANDARD 3-STOREY 6-CLASSROOM SCHOOL BUILDING @ LUNA NHS, BOLINAO, PANGASINAN AT BRGY. LUNA, BOLINAO, PANGASINAN | Region I | Pangasinan 1st DEO | Completed | ₱13.9M | 100% | Medium risk40 | —-0.038 |
| 174 | 18CL0026REHABILITATION/ IMPROVEMENT OF LAUIS RIVER WITH SLOPE PROTECTION WORKS, CANDELARIA, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱28.2M | 100% | Medium risk32 | —-0.083 |
| 175 | 18CL0023CONSTRUCTION OF SLOPE PROTECTION/ FLOOD CONTROL ALONG PAMATAWAN RIVER, PHASE IV, STA. 1+369.50- STA. 2+051, SAN ANTONIO, ZAMBALES | Region III | Zambales 1st DEO | Completed | ₱38.2M | 100% | Medium risk31 | —-0.087 |