95 projects on file, including joint ventures this contractor is part of.
Total projects
95
Total budget
₱5.4B
Average progress
91.9%
Completion rate
62.1%
Below 70%
Average risk score
52.1
Medium risk on average, out of 100
Flagged as unusual
10
10.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 95 | ₱5.4B | 52.1 | 10 | 91.9% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 74 | ₱4.6B | 51.9 | 10 | 93.7% |
| Roads | 13 | ₱557.6M | 53.5 | 0 | 76.4% |
| Buildings and Facilities | 6 | ₱55.4M | 38.9 | 0 | 100.0% |
| GAA 2025 OO-2 | 2 | ₱193M | 91.0 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CD0036CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MEYCAUAYAN RIVER, LIPUTAN - NAGBALON SECTION, STA. 05+375 - STA. 05+475, MEYCAUAYAN, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱96.5M | 100% | High risk91 | —-0.018 |
| 25CD0035CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MEYCAUAYAN RIVER, LIPUTAN - NAGBALON SECTION, STA. 05+475 - STA. 05+575, MEYCAUAYAN, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱96.5M | 100% | High risk91 | —-0.018 |
| 24CC0589CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER, PACKAGE J, PUROK 4, BARANGAY SAN JUAN, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.7M | 90% | High risk84 | Flagged0.035 |
| 24CC0590CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER, PACKAGE J, SITIO SULOK, BARANGAY PANGINAY, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.6M | 100% | High risk84 | Flagged0.030 |
| 24CC0580CONSTRUCTION OF RIVER WALL ALONG ANGAT RIVER, PACKAGE H, BARANGAY TANAWAN, BUSTOS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.6M | 0% | High risk83 | Flagged0.057 |
| 24CC0581CONSTRUCTION OF RIVER WALL ALONG ANGAT RIVER, PACKAGE I, BARANGAY TANAWAN, BUSTOS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.6M | 0% | High risk83 | Flagged0.057 |
| 24CC0591CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER, PACKAGE K, SITIO SULOK, BARANGAY PANGINAY, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱96.5M | 100% | High risk83 | Flagged0.030 |
| 24CC0596CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER (PACKAGE C), PUROK 2, BARANGAY SANTOL, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱96.5M | 100% | High risk83 | Flagged0.030 |
| 24CC0546CONSTRUCTION OF FLOOD CONTROL STRUCTURE INCLUDING PUMPING STATION AND FLOOD GATE AT BARANGAY MEYTO, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.7M | 0% | High risk81 | Flagged0.008 |
| 24CC0550CONSTRUCTION OF FLOOD CONTROL STRUCTURE WITH WATER PUNMPING STATION AT BARANGAY PANGINAY, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱96.5M | 74% | High risk79 | —-0.015 |
| 25CC0139CONSTRUCTION OF REINFORCED CONCRETE SLOPE PROTECTION STRUCTURE ALONG BALAGTAS RIVER (PACKAGE C), BARANGAY PANGINAY (SITIO SULOK), BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱96.5M | 94% | High risk79 | —-0.023 |
| 24CC0644CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY POBLACION (PUROK 3), GUIGUINTO, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱77.2M | 61% | High risk78 | Flagged0.035 |
| 24C00158ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-TERTIARY ROADS-MEYCAUAYAN-CAMALIG-BAHAY PARI ROAD, PROVINCE OF BULACAN | Region III | Region III | On-Going | ₱174.2M | 67% | High risk77 | —-0.002 |
| 25CC0462SIPAG - INTERJURISDICTIONAL ROADS AND/OR BRIDGES 9ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) PULILAN-BALIUAG BYPASS ROAD - BARANGAY SANTA PEREGRINA (PHASE 2), CHAINAGE 1300-CHAINAGE 3890, PULILAN, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.6M | 25% | High risk76 | —-0.012 |
| 25CC0457SIPAG - INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) - PULILAN-BALIUAG BYPASS ROAD - DULONG MALABON, CHAINAGE 0-CHAINAGE 1300, PULILAN, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.6M | 53% | High risk76 | —-0.020 |
| 25CD0178CONSTRUCTION OF BARANGAY ROADS, BRGY. CAYSIO, CAYPOMBO AND MAG-ASAWANG SAPA, SANTA MARIA, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱96M | 0% | High risk76 | —-0.007 |
| 24CC0168CONSTRUCTION OF REINFORCED CONCRETE FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER, BARANGAY PANGINAY (SITIO SULOK), BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱78.2M | 100% | High risk76 | —-0.058 |
| 25CC0140CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG BALAGTAS RIVER (PACKAGE B), BARANGAY PANGINAY (PUROK 6), BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱74.1M | 92% | High risk76 | —-0.031 |
| 25CC0136CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG BALAGTAS RIVER, BARANGAY PANGINAY (SITIO SULOK), BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱74.1M | 92% | High risk76 | —-0.031 |
| 25CC0138CONSTRUCTION OF RIVERBANK PROTECTION STRUCTUREALONG BALAGTAS RIVER (PACKAGE A), BARANGAY PANGINAY (PUROK 6), BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱74.1M | 92% | High risk76 | —-0.031 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24CC0580CONSTRUCTION OF RIVER WALL ALONG ANGAT RIVER, PACKAGE H, BARANGAY TANAWAN, BUSTOS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.6M | 0% | High risk83 | Flagged0.057 |
| 24CC0581CONSTRUCTION OF RIVER WALL ALONG ANGAT RIVER, PACKAGE I, BARANGAY TANAWAN, BUSTOS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.6M | 0% | High risk83 | Flagged0.057 |
| 24CC0644CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY POBLACION (PUROK 3), GUIGUINTO, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱77.2M | 61% | High risk78 | Flagged0.035 |
| 24CC0589CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER, PACKAGE J, PUROK 4, BARANGAY SAN JUAN, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.7M | 90% | High risk84 | Flagged0.035 |
| 24CC0591CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER, PACKAGE K, SITIO SULOK, BARANGAY PANGINAY, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱96.5M | 100% | High risk83 | Flagged0.030 |
| 24CC0590CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER, PACKAGE J, SITIO SULOK, BARANGAY PANGINAY, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.6M | 100% | High risk84 | Flagged0.030 |
| 24CC0596CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER (PACKAGE C), PUROK 2, BARANGAY SANTOL, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱96.5M | 100% | High risk83 | Flagged0.030 |
| 24CC0546CONSTRUCTION OF FLOOD CONTROL STRUCTURE INCLUDING PUMPING STATION AND FLOOD GATE AT BARANGAY MEYTO, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱92.7M | 0% | High risk81 | Flagged0.008 |
| 24CD0292CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MEYCAUAYAN RIVER AND ITS TRIBUTARIES, BARANGAY SALUYSOY, MEYCAUAYAN, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱39.6M | 100% | Medium risk50 | Flagged0.002 |
| 24CD0284REHABILITATION OF LONGOS PUMPING STATION, MEYCAUAYAN CITY, BULACAN, PHASE I | Region III | Bulacan 2nd DEO | On-Going | ₱23.4M | 100% | Medium risk53 | Flagged0.000 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 25CC0359CONSTRUCTIION OF ROAD AT BARANGAY PUNGO, CALUMPIT, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱19.3M | 49% | High risk70 | —-0.026 |
| 27 | 25CD0229REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG MEYCAUAYAN RIVER (BRGY. LONGOS TO BRGY. ZAMORA) STA 06+700 STA 06+750, MEYCAUAYAN, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱17M | 100% | High risk69 | —-0.037 |
| 28 | 24CC0106IMPROVEMENT OF ROAD, BRGY. BONGA MENOR, BUSTOS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱14.5M | 100% | High risk69 | —-0.070 |
| 29 | 25CD0231CONSTRUCTION OF LONGOS PUMPING STATION ALONG MEYCAUAYAN RIVER, MEYCAUAYAN CITY, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱93.6M | 61% | High risk65 | —-0.037 |
| 30 | 25CD0083CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BOCAUE - SANTA MARIA RIVER AND ITS TRIBUTARIES (TABON CREEK) STA. 04+900 - STA. 05+050, ABANGAN NORTE, MARILAO, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱93.6M | 93% | High risk63 | —-0.048 |
| 31 | 24CD0201CONCRETING OF SENTINELA, BRGY. ENCANTO FMR, BRGY. ENCANTO, ANGAT, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱14.7M | 100% | High risk61 | —-0.014 |
| 32 | 24CD0108REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG MEYCAUAYAN RIVER, BARANGAY TAWIRAN TO WAWANG PULO, STA. 02+496 STA. 02+636, OBANDO, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱96.5M | 100% | Medium risk60 | —-0.081 |
| 33 | 24CD0060CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MARILAO RIVER AND ITS TRIBUTARIES TABON CREEK, STA. 04+200 STA. 04+525, BARANGAY NAGBALON, MARILAO, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱94.6M | 100% | Medium risk59 | —-0.080 |
| 34 | 24CD0061CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MARILAO RIVER AND ITS TRIBUTARIES TABON CREEK, STA. 04+525 STA. 04+925, BARANGAY NAGBALON, MARILAO, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱106.1M | 100% | Medium risk58 | —-0.077 |
| 35 | 22CC0294CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER, LUMANGBAYAN SECTION, STA. 00+576 TO STA. 00+991, PLARIDEL, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱95.5M | 100% | Medium risk57 | —-0.078 |
| 36 | 21CD0095CONSTRUCTION OF SLOPE PROTECTION, BRGY. GUMAOC, CITY OF SAN JOSE DEL MONTE, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱96.5M | 100% | Medium risk56 | —-0.076 |
| 37 | 23CC0162CONSTRUCTION OF RIVERWALL ALONG GUIGUINTO RIVER, TABANG (TRIBUTARY) SECTION, STA. 01+370 TO STA. 01+730, GUIGUINTO, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | Medium risk56 | —-0.081 |
| 38 | 24CC0006CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG BALAGTAS RIVER, BARANGAY SAN JUAN, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | Medium risk56 | —-0.080 |
| 39 | 24CC0003CONSTRUICTION OF RIVERBANK PROTECTION STRUCTURE ALONG BALAGTAS RIVER (PHASE II), BARANGAY SAN JUAN, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | Medium risk55 | —-0.080 |
| 40 | 23CC0075CONSTRUCTION OF RIVERWALL ALONG BALAGTAS RIVER, PANGINAY (TRIBUTARY SECTION) STA. 15+270 TO STA. 15+475, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | Medium risk55 | —-0.081 |
| 41 | 23CC0092CONSTRUCTION OF RIVER CONTROL PROJECT ALONG BALAGTAS RIVER, PANGINAY (LS), STA. 13+090 - STA. 13+295, BALAGTAS, BUALCAN | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | Medium risk55 | —-0.081 |
| 42 | 23CC0093CONSTRUCTION OF RIVERWALL ALONG BALAGTAS RIVER, PANGINAY (RS), STA. 16+520 TO STA. 16+725, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | Medium risk55 | —-0.081 |
| 43 | 23CC0098CONSTRUCTION OF RIVER CONTROL PROJECT ALONG BALAGTAS RIVER, SAN JUAN SECTION, STA. 09+810 - STA. 10+015, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱96.5M | 100% | Medium risk55 | —-0.081 |
| 44 | 24CD0284REHABILITATION OF LONGOS PUMPING STATION, MEYCAUAYAN CITY, BULACAN, PHASE I | Region III | Bulacan 2nd DEO | On-Going | ₱23.4M | 100% | Medium risk53 | Flagged0.000 |
| 45 | 24CD0309REHABILITATION OF DISASTER RELATED INFRASTRUCTURE AND OTHER FACILITIESREHABILITATION OF TAWIRAN WAWANG PULO DIKE (PHASE III), MEYCAUAYAN RIVER, OBANDO, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱18.2M | 100% | Medium risk50 | —-0.001 |
| 46 | 24CD0310REHABILITATION OF DISASTER RELATED INFRASTRUCTURE AND OTHER FACILITIESREHABILITATION OF TAWIRAN WAWANG PULO DIKE (PHASE IV), MEYCAUAYAN RIVER, OBANDO, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱18.2M | 100% | Medium risk50 | —-0.001 |
| 47 | 24CD0292CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MEYCAUAYAN RIVER AND ITS TRIBUTARIES, BARANGAY SALUYSOY, MEYCAUAYAN, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱39.6M | 100% | Medium risk50 | Flagged0.002 |
| 48 | 24CD0314REHABILITATION OF DISASTER RELATED INFRASTRUCTURE AND OTHER FACILITIES REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG TUMANA SAN GABRIEL, STA. MARIA, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱18.7M | 100% | Medium risk43 | —-0.032 |
| 49 | 25CD0087CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MEYCAUAYAN RIVER AND ITS TRIBUTARIES (DECA HOMES SECTION), BARANGAY SALUYSOY, MEYCAUAYAN CITY, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱49M | 100% | Medium risk41 | —-0.061 |
| 50 | 24CD0086CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT OBANDO TRIBUTARIES, STA. 00+231 STA. 00+462, BARANGAY CATANGHALAN PAG-ASA, OBANDO, BULACAN | Region III | Bulacan 2nd DEO | Completed | ₱67.5M | 100% | Medium risk41 | —-0.090 |