65 projects on file, including joint ventures this contractor is part of.
Total projects
65
Total budget
₱1.6B
Average progress
99.8%
Completion rate
96.9%
Average risk score
37.3
Medium risk on average, out of 100
Flagged as unusual
1
1.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XIII | 60 | ₱1.4B | 36.7 | 1 | 99.8% |
| Region VIII | 4 | ₱127.4M | 43.9 | 0 | 100.0% |
| Region X | 1 | ₱9.7M | 44.5 | 0 | 95.5% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 27 | ₱667.5M | 37.9 | 0 | 99.8% |
| Buildings and Facilities | 20 | ₱227.2M | 26.6 | 0 | 100.0% |
| Bridges | 6 | ₱72.8M | 42.4 | 0 | 100.0% |
| Flood Control and Drainage | 5 | ₱344.4M | 50.1 | 0 | 100.0% |
| Water Provision and Storage | 5 | ₱44M | 39.8 | 0 | 100.0% |
| OTHER | 2 | ₱194.2M | 81.6 | 1 | 94.4% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24N00211CONSTRUCTION OF BUENAVISTA POBLACION SEAWALL PROTECTION, BUENAVISTA, AGUSAN DEL NORTE | Region XIII | Region XIII | On-Going | ₱149.6M | 89% | High risk89 | Flagged0.062 |
| 17NA0002ROAD WIDENING INCLUDING DRAINAGE, PAVING OF SHOULDER AND RROW ACQUISITION ALONG AGUSAN - MALAYBALAY ROAD K1271+(-756) - K1271+(-041), K1271+199 - K1271+484, AGUSAN DEL NORTE 2ND L.D. | Region XIII | Agusan del Norte DEO | Completed | ₱44.6M | 100% | High risk74 | —-0.030 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24N00211CONSTRUCTION OF BUENAVISTA POBLACION SEAWALL PROTECTION, BUENAVISTA, AGUSAN DEL NORTE | Region XIII | Region XIII | On-Going | ₱149.6M | 89% | High risk89 | Flagged0.062 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24N00211CONSTRUCTION OF BUENAVISTA POBLACION SEAWALL PROTECTION, BUENAVISTA, AGUSAN DEL NORTE | Region XIII | Region XIII | On-Going | ₱149.6M | 89% | High risk89 | Flagged0.062 |
| 2 | 17NA0002ROAD WIDENING INCLUDING DRAINAGE, PAVING OF SHOULDER AND RROW ACQUISITION ALONG AGUSAN - MALAYBALAY ROAD K1271+(-756) - K1271+(-041), K1271+199 - K1271+484, AGUSAN DEL NORTE 2ND L.D. | Region XIII | Agusan del Norte DEO | Completed | ₱44.6M | 100% | High risk74 | —-0.030 |
| 3 | 24N00212CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CASILAK RIVER (TALO-AO - MATABAO SECTION), BUENAVISTA, AGUSAN DEL NORTE | Region XIII | Region XIII | Completed | ₱96.5M | 100% | Medium risk59 | —-0.008 |
| 4 | 18IL0011OFF-CARRIAGEWAY IMPROVEMENT-SECONDARY ROADS/BDRY SOUTHERN LEYTE-MAASIN-MACROHON-SOGOD-JCT DAANG MAHARLIKA K1124+386-K1127+980, K1132+694-K1133+660, (SHOULDER PAVING/CONSTRUCTION), SOUTHERN LEYTE | Region VIII | Southern Leyte 1st DEO | Completed | ₱96.5M | 100% | Medium risk58 | —-0.084 |
| 5 | 17NA0021IMPROVEMENT/CONSTRUCTION OF RIVER DIKE ALONG CABADBARAN RIVER, CITY OF CABADBARAN, AGUSAN DEL NORTE 2ND L.D. | Region XIII | Agusan del Norte DEO | Completed | ₱41.2M | 100% | Medium risk55 | —-0.046 |
| 6 | 24NA0025REHABILITATION OF CABADBARAN RIVER BAY-ANG PANDANON SECTION, CABADBARAN CITY, AGUSAN DEL NORTE | Region XIII | Agusan del Norte DEO | Completed | ₱95.5M | 100% | Medium risk49 | —-0.061 |
| 7 | 17NG0033ROAD CONCRETING OF BRGY. ROAD, BRGY. MAHAYAHAY, DEL CARMEN, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱4.9M | 100% | Medium risk49 | —-0.048 |
| 8 | 24NA0023CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MATABAO CREEK, BUENAVISTA, AGUSAN DEL NORTE | Region XIII | Agusan del Norte DEO | Completed | ₱96.5M | 100% | Medium risk48 | —-0.062 |
| 9 | 17NA0030REHABILITATION/RECONST. OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-BUENAVISTA-BUNAGUIT ROAD K1272+200-K1272+300,K1272+460-K1272+600, K1272+680 - K1272+747 (S00396MN) | Region XIII | Agusan del Norte DEO | Completed | ₱40.5M | 100% | Medium risk48 | —-0.052 |
| 10 | 18IL0013CONSTRUCTION OF NEW PERMANENT BRIDGES / MANHILO BRIDGE II ALONG BDRY. SOUTHERN LEYTE-MAASIN-MACROHON-SOGOD-JCT DAANG MAHARLIKA (CONSTRUCTION OF CONCRETE BRIDGE), MAASIN CITY, SOUTHERN LEYTE | Region VIII | Southern Leyte 1st DEO | Completed | ₱14.7M | 100% | Medium risk48 | —-0.057 |
| 11 | 19IL0005ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS/BDRY. SO. LEYTE-MAASIN-MACROHON-SOGOD-JCT. DAANG MAHARLIKA-K1124±444-K1124±453, K1142+252-K1142+287, K1142+287-K1142+555, K1152+313-K1152+344.50, K1153+170-K | Region VIII | Southern Leyte 1st DEO | Completed | ₱12.8M | 100% | Medium risk47 | —-0.093 |
| 12 | 23NA0002READ - CONCRETING OF ROAD ALONG ABILAN PROVINCIAL ROAD, BRGY. ABILAN, BUENAVISTA, AGUSAN DEL NORTE | Region XIII | Agusan del Norte DEO | Completed | ₱76.2M | 100% | Medium risk45 | —-0.085 |
| 13 | 24NA0018CONCRETING OF ROAD ALONG ABILAN PROVINCIAL ROAD, PHASE II, ABILAN, BUENAVISTA, AGUSAN DEL NORTE | Region XIII | Agusan del Norte DEO | Completed | ₱64.3M | 100% | Medium risk45 | —-0.086 |
| 14 | 25KD0020CONSTRUCTION OF ROADS/PATHWAY WITH DRAINAGE, BARANGAY BALUBAL, CAGAYAN DE ORO CITY | Region X | Cagayan de Oro City 2nd DEO | On-Going | ₱9.7M | 96% | Medium risk45 | —-0.060 |
| 15 | 24NA0017RETROFITTING OF GUINABSAN BRIDGE, BARANGAY GUINABSAN, BUENAVISTA, AGUSAN DEL NORTE | Region XIII | Agusan del Norte DEO | Completed | ₱16.7M | 100% | Medium risk43 | —-0.048 |
| 16 | 23NA0024WIDENING OF PERMANENT BRIDGES KINABJANGAN PARALLEL BRIDGE ALONG BUTUAN CITY CAGAYAN DE ORO CITY - ILIGAN CITY ROAD (AGUSAN-MISAMIS OR. RD) | Region XIII | Agusan del Norte DEO | Completed | ₱9.8M | 100% | Medium risk42 | —-0.050 |
| 17 | 21NA0050CONSTRUCTION/REHABILITATION/COMPLETION OF SANTIAGO PUBLIC TERMINAL , SANTIAGO, AGUSAN DEL NORTE | Region XIII | Agusan del Norte DEO | Completed | ₱49.5M | 100% | Medium risk41 | —-0.076 |
| 18 | 23NA0012RETROFITTING OF MALAPONG BRIDGE, BRGY. MALAPONG BUENAVISTA, AGUSAN DEL NORTE | Region XIII | Agusan del Norte DEO | Completed | ₱7.9M | 100% | Medium risk41 | —-0.045 |
| 19 | 19NA0019WIDENING OF PERMANENT BRIDGES-MAMKAS BRIDGE (B00825MN) ALONG DAANG MAHARLIKA (SURIGAO-AGUSAN SECTION) (PHASE II), KITCHARAO, AGUSAN DEL NORTE | Region XIII | Agusan del Norte DEO | Completed | ₱14.7M | 100% | Medium risk41 | —-0.049 |
| 20 | 18NA0009REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS(TERTIARY ROADS), BUENAVISTA BUNAGUIT RD, CHAINAGE 120 - CHAINAGE 1713, BUENAVISTA, AGUSAN DEL NORTE | Region XIII | Agusan del Norte DEO | Completed | ₱43.1M | 100% | Medium risk41 | —-0.088 |
| 21 | 20NA0007REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-TERTIARY ROADS, AGUSAN - BUKIDNON ROAD (S00395MN), K1260+587.60 - K1260+673.50, AGUSAN DEL NORTE | Region XIII | Agusan del Norte DEO | Completed | ₱19.6M | 100% | Medium risk41 | —-0.089 |
| 22 | 20NA0014REHAB./RECONST./UPGRADING OF DAMAGED PAVED ROADS-TERTIARY ROADS, BUENAVISTA-BUNAGUIT RD (S00390MN), CHAINAGE 1925.68-CHAINAGE 2865 BUENAVISTA, AGUSAN DEL NORTE | Region XIII | Agusan del Norte DEO | Completed | ₱37.2M | 100% | Medium risk41 | —-0.088 |
| 23 | 18NA0003PAVING OF UNPAVED ROADS TERTIARY ROADS BUENAVISTA-BUNAGUIT ROAD (S00396MN) K1271+178 - K1271+919, (S00475MN) K1273+463 - K1273+675, S00390MN) CHAINAGE 0 - CHAINAGE 120, BUENAVISTA, AGUSAN DEL NORTE | Region XIII | Agusan del Norte DEO | Completed | ₱32.3M | 100% | Medium risk41 | —-0.088 |
| 24 | 20NA0009REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS, NASIPIT PORT ROAD (S00392MN), K1264+558 - K1265+000, NASIPIT, AGUSAN DEL NORTE | Region XIII | Agusan del Norte DEO | Completed | ₱16.8M | 100% | Medium risk40 | —-0.088 |
| 25 | 21NA0029CONCRETING OF TAGCATONG - BALATAKAN ROAD (PHASE II), CARMEN, AGUSAN DEL NORTE | Region XIII | Agusan del Norte DEO | Completed | ₱19.6M | 100% | Medium risk40 | —-0.089 |