Contractor dossier
101 projects on file, including joint ventures this contractor is part of.
Total projects
101
Total budget
₱765.9M
Average progress
95.6%
Completion rate
85.1%
Average risk score
42.0
Medium risk on average, out of 100
Flagged as unusual
7
6.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 101 | ₱765.9M | 42.0 | 7 | 95.6% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 42 | ₱332.1M | 42.9 | 3 | 92.2% |
| Buildings and Facilities | 38 | ₱199.2M | 38.1 | 1 | 99.0% |
| Flood Control and Drainage | 8 | ₱163.2M | 44.0 | 1 | 97.9% |
| Water Provision and Storage | 7 | ₱24.7M | 27.3 | 0 | 100.0% |
| GAA 2025 SSP | 3 | ₱12.8M | 91.2 | 2 | 80.2% |
| OTHER | 2 | ₱28.4M | 61.9 | 0 | 100.0% |
| Bridges | 1 | ₱5.5M | 47.7 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25IC0118CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY GUINCIAMAN, SAN MIGUEL, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱4.9M | 59% | High risk95 | Flagged0.019 |
| 25IG0063CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY KALANGGAMAN, BATO, LEYTE | Region VIII | Leyte 5th DEO | On-Going | ₱4.9M | 82% | High risk94 | Flagged0.013 |
| 25IG0027CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BALIW, HILONGOS, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱3M | 100% | High risk84 | —-0.025 |
| 25IG0085RAINWATER COLLECTOR SYSTEM | Region VIII | Leyte 5th DEO | On-Going | ₱2.6M | 100% | High risk66 | —-0.008 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24IC0182CONCRETING OF BRGY. SAN ROQUE FMR, BRGY. SAN ROQUE, STA. FE, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱11.9M | 0% | Medium risk45 | Flagged0.025 |
| 25IC0118CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY GUINCIAMAN, SAN MIGUEL, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱4.9M | 59% | High risk95 | Flagged0.019 |
| 23IG0163CONSTRUCTION OF RETAINING WALL AT THE RECLAMATION AREA OF STO. ROSARIO ST. BRGY. POBLACION, INOPACAN, LEYTE | Region VIII | Leyte 5th DEO | On-Going | ₱22.7M | 83% | Medium risk51 | Flagged0.018 |
| 25IG0063CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY KALANGGAMAN, BATO, LEYTE | Region VIII | Leyte 5th DEO | On-Going | ₱4.9M | 82% | High risk94 | Flagged0.013 |
| 23IC0195CONSTRUCTION OF MULTI-PURPOSE BUILDING, PDEA REGIONAL OFFICE 8, GOV'T CENTER, BRGY. CANDAHUG, PALO, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱24.1M | 62% | Medium risk51 | Flagged0.007 |
| 25IG0071CONCRETING OF BRGY. CALUMPANG TO BRGY. SAN VICENTE TO BRGY. ESPERANZA FMR, BRGYS. CALUMPANG, SAN VICENTE AND ESPERANZA, MATALOM, LEYTE | Region VIII | Leyte 5th DEO | On-Going | ₱14.9M | 55% | Medium risk50 | Flagged0.005 |
| 25IE0074CONCRETING OF SITIO RIMAS TO BRGY. PARARAO FMR, LEYTE, LEYTEBRGY. PARARAO, LEYTE, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱14.9M | 61% | Medium risk52 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 101 | 21IG0112CLUSTER III - CONSTRUCTION/COMPLETION OF 2STY2 ICT LAB, BATO NATIONAL HIGH SCHOOL, BATO, LEYTE, CONSTRUCTION/COMPLETION OF 2STY2CL SCI LAB, HILONGOS NATIONAL VOCATIONAL SCHOOL, HILONGOS, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱1.3M | 100% | Low risk12 | —-0.049 |