Contractor dossier
29 projects on file, including joint ventures this contractor is part of.
Total projects
29
Total budget
₱343.8M
Average progress
89.5%
Completion rate
79.3%
Average risk score
46.1
Medium risk on average, out of 100
Flagged as unusual
2
6.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 27 | ₱325.2M | 45.3 | 2 | 92.4% |
| Region IV-A | 2 | ₱18.6M | 56.2 | 0 | 50.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 12 | ₱140.2M | 47.0 | 0 | 90.3% |
| Roads | 12 | ₱94M | 37.5 | 0 | 91.7% |
| Flood Control and Drainage | 3 | ₱85.3M | 46.2 | 0 | 100.0% |
| GAA 2025 SSP | 2 | ₱24.3M | 91.3 | 2 | 56.2% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25OF0205CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAUYO (KABAHAGI), QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱19.4M | 86% | High risk93 | Flagged0.007 |
| 25OF0186REHABILITATION OF FLOOD CONTROL STRUCTURE AT BARANGAY SAN AGUSTIN, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱4.8M | 26% | High risk90 | Flagged0.021 |
| 24DN0181IMPROVEMENT OF INTERSECTION - MANILA EAST ROAD (S01744LZ) - K0022+192 AND TAYTAY DIVERSION ROAD (S01587LZ) RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱9.5M | 0% | High risk66 | —-0.018 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25OF0186REHABILITATION OF FLOOD CONTROL STRUCTURE AT BARANGAY SAN AGUSTIN, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱4.8M | 26% | High risk90 | Flagged0.021 |
| 25OF0205CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAUYO (KABAHAGI), QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱19.4M | 86% | High risk93 | Flagged0.007 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25OF0205CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAUYO (KABAHAGI), QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱19.4M | 86% | High risk93 | Flagged0.007 |
| 2 | 25OF0186REHABILITATION OF FLOOD CONTROL STRUCTURE AT BARANGAY SAN AGUSTIN, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱4.8M | 26% | High risk90 | Flagged0.021 |
| 3 | 24DN0181IMPROVEMENT OF INTERSECTION - MANILA EAST ROAD (S01744LZ) - K0022+192 AND TAYTAY DIVERSION ROAD (S01587LZ) RIZAL (FIRST DISTRICT) | Region IV-A | Rizal 1st DEO | On-Going | ₱9.5M | 0% | High risk66 | —-0.018 |
| 4 | 23OF0115CONSTRUCTION OF MULTI-PURPOSE BUILDING (DISASTER OPERATIONS CENTER) AT BARANGAY PASONG TAMO, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱29.4M | 100% | Medium risk52 | —-0.098 |
| 5 | 22OF0071CONSTRUCTION OF MULTI-PURPOSE BUILDING 1, BARANGAY CULIAT, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱29.4M | 100% | Medium risk52 | —-0.093 |
| 6 | 25OF0203CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PASONG TAMO, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱19.4M | 0% | Medium risk50 | —-0.031 |
| 7 | 25OF0097CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT NEW HAVEN, BARANGAY KALIGAYAHAN, QUEZON CITY | National Capital Region | Quezon City 1st DEO | On-Going | ₱14.6M | 84% | Medium risk49 | —-0.060 |
| 8 | 22OF0066CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY STA. LUCIA, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱9.8M | 100% | Medium risk49 | —-0.102 |
| 9 | 24OF0225CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY PASONG TAMO, QUEZON CITY PHASE I | National Capital Region | Quezon City 1st DEO | On-Going | ₱4.9M | 100% | Medium risk48 | —-0.062 |
| 10 | 21OF0139CONSTRUCTION OF MULTI-PURPOSE BUILDING AT JEM 7, BARANGAY TALIPAPA, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱6.6M | 100% | Medium risk48 | —-0.103 |
| 11 | 20OF0242REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. HOLY SPIRIT, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱5.8M | 100% | Medium risk48 | —-0.099 |
| 12 | 21OF0121REHABILITATION OF SCHOOL BUILDING AT BARANGAY SANGANDAAN, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱6.7M | 100% | Medium risk48 | —-0.100 |
| 13 | 21OE0051CONSTRUCTION / REHABILITATION OF MULTI - PURPOSE BUILDING (DAY-CARE CENTER) AT BARANGAY 176 ZONE 15, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.103 |
| 14 | 20OF0273CONSTRUCTION OF COVERED COURT AT PUROK PAG-ASA, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱4.8M | 100% | Medium risk47 | —-0.100 |
| 15 | 21OE0006BANK IMPROVEMENT (STEEL SHEET PILE) ESTERO DE SAN MIGUEL, BARANGAY 384 & BARANGAY 385, STA.2+140.00 TO STA.2+260.00, STA.1+930.40 TO STA.1+963.20, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱46.8M | 100% | Medium risk47 | —-0.088 |
| 16 | 25OH0024ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-TERTIARY ROADS-MARIA OROSA ST-(S02793LZ) CHAINAGE 000-CHAINAGE 389 | National Capital Region | South Manila DEO | Completed | ₱27.4M | 100% | Medium risk46 | —-0.095 |
| 17 | 21DN0126OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - CORAZON C. AQUINO AVE. - K0021+202 - K0021+250 TAYTAY, RIZAL | Region IV-A | Rizal 1st DEO | Completed | ₱9.1M | 100% | Medium risk46 | —-0.108 |
| 18 | 24OF0068CONSTRUCTION OF DRAINAGE SYSTEMS AT BRGY. PASONG TAMO, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱19.2M | 100% | Medium risk46 | —-0.088 |
| 19 | 21OE0064REHABILITATION OF FLOOD CONTROL STRUCTURES AND FACILITIES ALONG BLUMENTRITT, STA. 0+000.00 TO STA. 214.40, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱19.3M | 100% | Medium risk46 | —-0.089 |
| 20 | 25OE0034PREVENTIVE MAINTENANCE - TERTIARY ROADS - CORDILLERA ST - (S02537LZ) CHAINAGE 000 - CHAINAGE 224 | National Capital Region | North Manila DEO | Completed | ₱11.5M | 100% | Medium risk46 | —-0.099 |
| 21 | 21OF0025REHABILITATION OF DRAINAGE AND ROAD AT TANDANG SORA AVE., BRGY. TANDANG SORA, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱9.5M | 100% | Medium risk46 | —-0.099 |
| 22 | 21OF0146REHABILITATION AND DRAINAGE IMPROVEMENT OF ROADS BARANGAY BALON BATO, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱6.7M | 100% | Medium risk46 | —-0.099 |
| 23 | 22OF0115CONSTRUCTION OF ROAD INCLUDING DRAINAGE IMPROVEMENT AT BARANGAY CULIAT, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱8.8M | 100% | Medium risk46 | —-0.100 |
| 24 | 25OH0022ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-TERTIARY ROADS-MARIA OROSA ST-(S02794LZ) CHAINAGE 340-CHAINAGE 415 | National Capital Region | South Manila DEO | Completed | ₱4M | 100% | Low risk25 | —-0.094 |
| 25 | 22OF0105PREVENTIVE MAINTENANCE OF ROAD: CONCRETE REBLOCKING ALONG CLOVERLEAF (SO5131LZ) CHAINAGE 0 - CHAINAGE 234, QUEZON CITY | National Capital Region | Quezon City 1st DEO | Completed | ₱3.6M | 100% | Low risk25 | —-0.095 |