Contractor dossier
56 projects on file, including joint ventures this contractor is part of.
Total projects
56
Total budget
₱989.1M
Average progress
95.3%
Completion rate
75.0%
Average risk score
44.9
Medium risk on average, out of 100
Flagged as unusual
7
12.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Cordillera Administrative Region | 54 | ₱974.4M | 44.9 | 7 | 95.1% |
| National Capital Region | 1 | ₱9.8M | 48.9 | 0 | 100.0% |
| Region II | 1 | ₱4.9M | 45.6 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 29 | ₱628.3M | 44.9 | 2 | 98.2% |
| Flood Control and Drainage | 9 | ₱195.9M | 42.4 | 1 | 88.2% |
| Buildings and Facilities | 9 | ₱86.9M | 39.2 | 2 | 98.5% |
| Water Provision and Storage | 5 | ₱31.3M | 24.5 | 0 | 100.0% |
| GAA 2025 SSP | 2 | ₱9.7M | 88.2 | 2 | 69.1% |
| GAA 2025 OO-1 | 1 | ₱27.3M | 92.8 | 0 | 83.5% |
| GAA 2025 OO-2 | 1 | ₱9.6M | 87.8 | 0 | 85.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25PL0082CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI- PURPOSE BUILDING, BARANGAY CASIGAYAN, DAGUPAN CENTRO, MAGSAYSAY, TABUK CITY, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱7.9M | 79% | High risk96 | Flagged0.015 |
| 25PK0028ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - PAVING OF UNPAVED ROADS - SECONDARY ROADS - KALINGA-ABRA RD - K0466+308-K0466+344, K0468+153-K0468+170, K0468+640-K0468+696, K0473+190-K0473+405, K0473+ | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱27.3M | 83% | High risk93 | —-0.000 |
| 25PL0042ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE A | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱9.6M | 85% | High risk88 | —-0.003 |
| 25PL0104CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION (COMPLETION) OF ACCESS ROAD | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱1.8M | 59% | High risk81 | Flagged0.019 |
| 20PL0105CONSTRUCTION OF SLOPE PROTECTION ALONG MALALAO NATIONAL ROAD, TABUK CITY, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱9.8M | 100% | High risk65 | —-0.040 |
| 17P00044ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) JCT. TALUBIN - BARLIG - NATONIN - PARACELIS - CALACCAD ROAD, CHAINAGE 458 - CHAINAGE 2720, CHAINAGE 2940 | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱126.2M | 100% | High risk62 | —-0.030 |
| 17PL0023REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT MANAGEMENT-4 (HDM-4) - TERTIARY MALALAO NATIONAL ROAD (AGBANNAWAG-MALALAO-BULO SECTION) KO518+920 - KO519+17 | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱6.5M | 100% | High risk61 | —-0.046 |
| 17PM0029NETWORK DEVELOPMENT-PAVING OF UNPAVED ROADS, TERTIARY ROADS JCT. TALUBIN-BARLIG-NATONIN-PARACELIS-CALACCAD RD (S00534LZ) K0480+608 - K0480+917 | Cordillera Administrative Region | Mountain Province 2nd DEO | Completed | ₱11.6M | 100% | High risk60 | —-0.048 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25PL0104CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION (COMPLETION) OF ACCESS ROAD | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱1.8M | 59% | High risk81 | Flagged0.019 |
| 17PL0185PACKAGE 17: A) TOMIAGAN FLOOD CONTROL ALONG PASIL RIVER, B) DAO CREEK FLOOD CONTROL, C) NANENG FLOOD CONTROL ALONG CHICO RIVER, D) PINAGAN FLOOD CONTROL ALONG CHICO RIVER | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱78.8M | 100% | Medium risk58 | Flagged0.016 |
| 25PL0082CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI- PURPOSE BUILDING, BARANGAY CASIGAYAN, DAGUPAN CENTRO, MAGSAYSAY, TABUK CITY, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱7.9M | 79% | High risk96 | Flagged0.015 |
| 23PL0119CONCRETING OF SITIO TOPAP TO SITIO DALUWAY, BRGY. BALLAYANGON FMR, BRGY. BALLAYANGON, PINUKPUK, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱11.9M | 87% | Medium risk47 | Flagged0.013 |
| 23PL0124CONCRETING OF BARANGAY LOWER TALOCTOC FMR, BARANGAY LOWER TALOCTOC, TANUDAN, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱11.9M | 95% | Medium risk44 | Flagged0.011 |
| 23PL0113CONSTRUCTION OF 1STY5CL, BULO NATIONAL HIGH SCHOOL, TABUK, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱11.6M | 90% | Medium risk50 | Flagged0.007 |
| 23PL0114CONSTRUCTION OF 1STY7CL, GUILAYON INTEGRATED SCHOOL, TABUK, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱17.9M | 96% | Medium risk53 | Flagged0.006 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25PL0082CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI- PURPOSE BUILDING, BARANGAY CASIGAYAN, DAGUPAN CENTRO, MAGSAYSAY, TABUK CITY, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱7.9M | 79% | High risk96 | Flagged0.015 |
| 2 | 25PK0028ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - PAVING OF UNPAVED ROADS - SECONDARY ROADS - KALINGA-ABRA RD - K0466+308-K0466+344, K0468+153-K0468+170, K0468+640-K0468+696, K0473+190-K0473+405, K0473+ | Cordillera Administrative Region | Upper Kalinga DEO | On-Going | ₱27.3M | 83% | High risk93 | —-0.000 |
| 3 | 25PL0042ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE A | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱9.6M | 85% | High risk88 | —-0.003 |
| 4 | 25PL0104CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION (COMPLETION) OF ACCESS ROAD | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱1.8M | 59% | High risk81 | Flagged0.019 |
| 5 | 20PL0105CONSTRUCTION OF SLOPE PROTECTION ALONG MALALAO NATIONAL ROAD, TABUK CITY, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱9.8M | 100% | High risk65 | —-0.040 |
| 6 | 17P00044ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) JCT. TALUBIN - BARLIG - NATONIN - PARACELIS - CALACCAD ROAD, CHAINAGE 458 - CHAINAGE 2720, CHAINAGE 2940 | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱126.2M | 100% | High risk62 | —-0.030 |
| 7 | 17PL0023REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT MANAGEMENT-4 (HDM-4) - TERTIARY MALALAO NATIONAL ROAD (AGBANNAWAG-MALALAO-BULO SECTION) KO518+920 - KO519+17 | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱6.5M | 100% | High risk61 | —-0.046 |
| 8 | 17PM0029NETWORK DEVELOPMENT-PAVING OF UNPAVED ROADS, TERTIARY ROADS JCT. TALUBIN-BARLIG-NATONIN-PARACELIS-CALACCAD RD (S00534LZ) K0480+608 - K0480+917 | Cordillera Administrative Region | Mountain Province 2nd DEO | Completed | ₱11.6M | 100% | High risk60 | —-0.048 |
| 9 | 18P00036ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT- PAVING OF UNPAVED ROADS-TERTIARY ROADS MT. PROVINCE - ISABELA RD CHAINAGE 21883-CHAINAGE 24699, CHAINAGE 24699-CHAINAGE 25863 | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱131M | 100% | Medium risk58 | —-0.062 |
| 10 | 17PL0185PACKAGE 17: A) TOMIAGAN FLOOD CONTROL ALONG PASIL RIVER, B) DAO CREEK FLOOD CONTROL, C) NANENG FLOOD CONTROL ALONG CHICO RIVER, D) PINAGAN FLOOD CONTROL ALONG CHICO RIVER | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱78.8M | 100% | Medium risk58 | Flagged0.016 |
| 11 | 23PL0001ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM -CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-PRIMARY ROADS - KALINGA-CAGAYAN ROAD (CALANAN-ENRILE SECTION) - K0500+474 - K0501+753 | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱62.2M | 100% | Medium risk55 | —-0.035 |
| 12 | 18PL0153CONSTRUCTION OF FOUR(4) STOREY EIGHT(8) CLASSROOM WORKSHOP SCHOOL BUILDING 2, TABUK CITY NATIONAL HIGH SCHOOL, TABUK CITY, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱37.7M | 100% | Medium risk54 | —-0.024 |
| 13 | 23PL0114CONSTRUCTION OF 1STY7CL, GUILAYON INTEGRATED SCHOOL, TABUK, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱17.9M | 96% | Medium risk53 | Flagged0.006 |
| 14 | 24PL0034CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - MACUTAY-GREENHILLS-SAN PEDRO AND SAN VICENTE ACCESS ROAD LEADING TO ELEPHANT HILL, | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱9.8M | 97% | Medium risk51 | —-0.043 |
| 15 | 18PL0042REHABILITATION/RECONSTRUCTION OF NAT'L RD WITH ROAD SLIPS, SLOPE COLLAPSE & LANDSLIDES ALONG KALINGA - CAGAYAN RD (CALANAN-ENRILE SECT), K0496+884 - K0517+269 I.S., TABUK CITY, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱31M | 100% | Medium risk51 | —-0.079 |
| 16 | 21PL0007CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES, BANGAAN-BAKIR ACCESS ROAD CONNECTING LIWAN WEST NATIONAL ROAD AND BANGAAN-BAKIR ACCESS ROAD IN SUPPORT TO VEGGIE NOODLES P | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱4.9M | 100% | Medium risk51 | —-0.079 |
| 17 | 19PL0104ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDES ALONG KALINGA - CAGAYAN RD. (CALANAN - ENRILE SECTION)K0499+933 - K0500+000, K0513+403-K0513+468, K0516+912- K0516+967, K0517+420-K0517+436 | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱15.1M | 100% | Medium risk51 | —-0.077 |
| 18 | 25PL0068ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - MT PROVINCE BDRY-CALANAN-PINUKPUK-ABBUT RD (PINUK | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱21.8M | 68% | Medium risk51 | —-0.043 |
| 19 | 23PL0063ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - BALBALAN-PINUKPUK RD - K0499+3298 - K0499+3458, K0518+972 - K0519+085 | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱9.8M | 100% | Medium risk51 | —-0.082 |
| 20 | 19PL0136CONSTRUCTION OF BULANAO - SAN JUAN - APPAS - SOCBOT ROAD, TABUK CITY, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱19.4M | 100% | Medium risk51 | —-0.081 |
| 21 | 23PL0053CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION (CONCRETING) OF BOYDON ROAD, BRGY. LIWAN EAST, RIZAL, KALING | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱4.9M | 100% | Medium risk51 | —-0.075 |
| 22 | 23PL0113CONSTRUCTION OF 1STY5CL, BULO NATIONAL HIGH SCHOOL, TABUK, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱11.6M | 90% | Medium risk50 | Flagged0.007 |
| 23 | 24PL0043ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF NAMBUCAYAN HIGHSCHOOL FLOOD CONTROL ALONG MANANIG RIVER | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱35.1M | 94% | Medium risk50 | —-0.026 |
| 24 | 24PL0120ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF DRAINAGE CANAL ALONG MT. PROVINCE BDRY. - CALANAN - PINUKPUK - ABBUT ROAD, CALANA | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱34.3M | 0% | Medium risk50 | —-0.003 |
| 25 | 20PL0077CONTINUATION OF TULYAO FLOOD CONTROL ALONG TULYAO CREEK, CALANAN, TABUK CITY, KALINGA, STA. 0+000 - STA. 0+250 & STA. 0+000 - STA. 0+047.5, TABUK CITY, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱24.2M | 100% | Medium risk49 | —-0.063 |