Contractor dossier
37 projects on file, including joint ventures this contractor is part of.
Total projects
37
Total budget
₱811.1M
Average progress
90.8%
Completion rate
81.1%
Average risk score
40.6
Medium risk on average, out of 100
Flagged as unusual
2
5.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region II | 34 | ₱807.4M | 42.7 | 2 | 90.0% |
| Cordillera Administrative Region | 2 | ₱1M | 19.9 | 0 | 100.0% |
| Region XII | 1 | ₱2.7M | 12.1 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 24 | ₱365.6M | 38.5 | 0 | 95.8% |
| Flood Control and Drainage | 5 | ₱387.2M | 57.1 | 1 | 71.9% |
| Buildings and Facilities | 4 | ₱16.3M | 36.4 | 0 | 100.0% |
| Bridges | 3 | ₱39.3M | 45.5 | 1 | 67.3% |
| Water Provision and Storage | 1 | ₱2.7M | 12.1 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23BH0264SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF BRGY. STO. DOMINGO FLOOD CONTROL STRUCTURE, SECTION 3, JONES, ISABELA | Region II | Isabela 4th DEO | On-Going | ₱96.5M | 0% | High risk71 | Flagged0.055 |
| 16BH0095ASSET PRESERVATION OF NATIONAL ROADS-PREVENTIVE MAINTENANCE BASED ON PAVEMENT MANAGEMENT SYSTEM/HDM4 | Region II | Isabela 4th DEO | Completed | ₱9.4M | 100% | High risk66 | —-0.052 |
| 25BF0018OO1 - ASSET PRESERVATION PROGRAM REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - SANTIAGO-TUGUEGARAO RD - K0417 + 335 - K0418 + 060, QUEZON, ISABELA | Region II | Isabela 2nd DEO | Completed | ₱21.2M | 100% | High risk64 | —-0.053 |
| 25BH0024ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF QUIMALABASA NORTE FLOOD CONTROL STRUCTURE SECTION 5, | Region II | Isabela 4th DEO | On-Going | ₱106.1M | 87% | High risk62 | —-0.026 |
| 24BH0105SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BRGY. STO. DOMINGO FLOOD CONTROL STRUCTURE, SECTION 4, JONES, ISABELA | Region II | Isabela 4th DEO | Completed | ₱96.5M | 100% | High risk61 | —-0.054 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23BH0264SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF BRGY. STO. DOMINGO FLOOD CONTROL STRUCTURE, SECTION 3, JONES, ISABELA | Region II | Isabela 4th DEO | On-Going | ₱96.5M | 0% | High risk71 | Flagged0.055 |
| 23BH0226BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF BRIDGE IN SANTIAGO CITY, ISABELA | Region II | Isabela 4th DEO | On-Going | ₱9.9M | 2% | Medium risk46 | Flagged0.017 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 23BH0264SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF BRGY. STO. DOMINGO FLOOD CONTROL STRUCTURE, SECTION 3, JONES, ISABELA | Region II | Isabela 4th DEO | On-Going | ₱96.5M | 0% | High risk71 | Flagged0.055 |
| 2 | 16BH0095ASSET PRESERVATION OF NATIONAL ROADS-PREVENTIVE MAINTENANCE BASED ON PAVEMENT MANAGEMENT SYSTEM/HDM4 | Region II | Isabela 4th DEO | Completed | ₱9.4M | 100% | High risk66 | —-0.052 |
| 3 | 25BF0018OO1 - ASSET PRESERVATION PROGRAM REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - SANTIAGO-TUGUEGARAO RD - K0417 + 335 - K0418 + 060, QUEZON, ISABELA | Region II | Isabela 2nd DEO | Completed | ₱21.2M | 100% | High risk64 | —-0.053 |
| 4 | 25BH0024ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF QUIMALABASA NORTE FLOOD CONTROL STRUCTURE SECTION 5, | Region II | Isabela 4th DEO | On-Going | ₱106.1M | 87% | High risk62 | —-0.026 |
| 5 | 24BH0105SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BRGY. STO. DOMINGO FLOOD CONTROL STRUCTURE, SECTION 4, JONES, ISABELA | Region II | Isabela 4th DEO | Completed | ₱96.5M | 100% | High risk61 | —-0.054 |
| 6 | 25B00067OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS - MAHARLIKA HIGHWAY - K0346+694 - K0347+282, K0347+430 -K0347+993, K0350+700 - K0351+561, K0352+0 | Region II | Region II | On-Going | ₱72.5M | 0% | Medium risk51 | —-0.020 |
| 7 | 24B00083CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER 11239 - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS ALONG DAANG MAHARLIKA (LZ) - K0344 +(-037.40) - K0345 + 000.00, K0346 + 278.40 | Region II | Region II | On-Going | ₱59.1M | 100% | Medium risk51 | —-0.050 |
| 8 | 20BH0091CONSTRUCTION OF MULTI-PURPOSE BUILDING, CABARUAN NATIONAL HIGH SCHOOL, BRGY. CABARUAN | Region II | Isabela 4th DEO | Completed | ₱5M | 100% | Medium risk47 | —-0.085 |
| 9 | 20BH0053CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO TRADES INDUSTRIES AND ECONOMIC ZONES - BRGY. BACULOD TO DISSIMURAY ROAD CAUAYAN CITY, ISABELA | Region II | Isabela 4th DEO | Completed | ₱49M | 100% | Medium risk47 | —-0.080 |
| 10 | 21BH0109CONSTRUCTION/REHABILITATION/IMPROVEMENT OF MULTI-PURPOSE BUILDING, BARANGAY MABBAYAD | Region II | Isabela 4th DEO | Completed | ₱5M | 100% | Medium risk47 | —-0.084 |
| 11 | 23BH0180ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS- FLOOD MANAGEMENT PROGRAM- CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONSTRUCTION OF BARANGAY 1 FLOOD CONTROL STRUCTURE, STA.0+000- STA.0+350, | Region II | Isabela 4th DEO | On-Going | ₱49M | 73% | Medium risk47 | —-0.017 |
| 12 | 24BH0313SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES- CONSTRUCTION OF SINILI BRIDGE, SANTIAGO CITY, ISABELA (PHASE II) | Region II | Isabela 4th DEO | Completed | ₱24.5M | 100% | Medium risk46 | —-0.049 |
| 13 | 23BH0226BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF BRIDGE IN SANTIAGO CITY, ISABELA | Region II | Isabela 4th DEO | On-Going | ₱9.9M | 2% | Medium risk46 | Flagged0.017 |
| 14 | 23BH0225BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF SINILI BRIDGE, SANTIAGO CITY, ISABELA | Region II | Isabela 4th DEO | Completed | ₱4.9M | 100% | Medium risk45 | —-0.049 |
| 15 | 20BE0012ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS: ASPHALT OVERLAY ALONG DAANG MAHARLIKA (LZ) CITY OF ILAGAN, ISABELA, K0397+098 - K0397+282, K0397+417 - K0399+008, K0400+637 - K0401+579 | Region II | Isabela 1st DEO | Completed | ₱34.5M | 100% | Medium risk45 | —-0.080 |
| 16 | 18BE0028PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY ALONG DAANG MAHARLIKA (LZ) KO394+(-827)-KO394+000, KO411+138-KO411+190, KO415+520-KO415+900, KO416+433-KO417+144, KO419+152-KO419+305 CITY OF ILAGAN, ISABELA | Region II | Isabela 1st DEO | Completed | ₱24.6M | 100% | Medium risk44 | —-0.079 |
| 17 | 20BE0021ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - DAANG MAHARLIKA (LZ) TUMAUINI, SAN PABLO, ISABELA KO433+973-KO434+292, KO434+311-KO434+715, KO459+801-KO459+905 | Region II | Isabela 1st DEO | Completed | ₱11.1M | 100% | Medium risk44 | —-0.081 |
| 18 | 24BH0027ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF BARANGAY FUGU FLOOD CONTROL STRUCTURE, SECTION 1, JONES | Region II | Isabela 4th DEO | On-Going | ₱39.2M | 100% | Medium risk44 | —-0.033 |
| 19 | 18BE0027PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY ALONG CALAMAGUI-ILAGAN RD. KO399+479-KO399+600, KO399+600-KO399+637.14, KO399+637.14-KO399+781, KO400+573-KO402+000 CITY OF ILAGAN, ISABELA | Region II | Isabela 1st DEO | Completed | ₱18.7M | 100% | Medium risk44 | —-0.079 |
| 20 | 20BG0048001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - DAANG MAHARLIKA (LZ) - K0387+170 - K0387+824, GAMU, ISABELA | Region II | Isabela 3rd DEO | Completed | ₱10.3M | 100% | Medium risk44 | —-0.083 |
| 21 | 21BF0065INSTALLATION/APPLICATION/CONSTRUCTION OF ROAD SAFETY DEVICES IN IDENTIFIED BLACKSPOTS ALONG SANTIAGO-TUGUEGARAO ROAD K0365+(-1140) - K0418+457 (INTERMITTENT SECTIONS), AURORA, SAN MANUEL, ROXAS, MALLIG AND QUEZON, ISABELA | Region II | Isabela 2nd DEO | Completed | ₱11.4M | 100% | Medium risk43 | —-0.083 |
| 22 | 21BF0064INSTALLATION/APPLICATION/CONSTRUCTION OF ROAD SAFETY DEVICES ALONG GAMU-ROXAS ROAD K0399+000 - K0418+1180 (INTERMITTENT SECTIONS), BURGOS & ROXAS, ISABELA | Region II | Isabela 2nd DEO | Completed | ₱8M | 100% | Medium risk43 | —-0.083 |
| 23 | 22BH0027BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF LOCAL ROAD, BARANGAY PAPAN WESTE, JONES, ISABELA | Region II | Isabela 4th DEO | Completed | ₱6.9M | 100% | Medium risk43 | —-0.086 |
| 24 | 22BH0022BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF LOCAL ROAD, BARANGAY DIPANGIT, JONES, ISABELA | Region II | Isabela 4th DEO | Completed | ₱6.4M | 100% | Medium risk43 | —-0.087 |
| 25 | 21BH0041CONSTRUCTION OF LOCAL ROADS, BARANGAY CABUGAO | Region II | Isabela 4th DEO | Completed | ₱5M | 100% | Medium risk43 | —-0.084 |