Opening the dossier…
Opening the dossier…
Contractor dossier
256 projects on file, including joint ventures this contractor is part of.
Total projects
256
Total budget
₱6.2B
Average progress
95.2%
Completion rate
82.4%
Average risk score
43.7
Medium risk on average, out of 100
Flagged as unusual
10
3.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 252 | ₱6.2B | 44.1 | 10 | 95.1% |
| Region IV-B | 3 | ₱5.5M | 11.4 | 0 | 100.0% |
| National Capital Region | 1 | ₱4.9M | 47.4 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 95 | ₱1.2B | 32.6 | 2 | 97.5% |
| Roads | 89 | ₱2.6B | 48.2 | 1 | 93.1% |
| Flood Control and Drainage | 56 | ₱1.8B | 46.6 | 0 | 98.0% |
| OTHER | 7 | ₱460.9M | 81.1 | 5 | 81.8% |
| GAA 2025 OO-1 | 4 | ₱115.2M | 93.0 | 2 | 73.9% |
| Water Provision and Storage | 4 | ₱13.1M | 40.8 | 0 | 100.0% |
| GAA 2025 OO-2 | 1 | ₱62.7M | 92.3 | 0 | 74.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25IK0004NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS, BASEY - MARABUT - PINAMITINAN RD., K0910+000 - K0910+470, K0910+494 - K0911+000 | Region VIII | Samar 2nd DEO | On-Going | ₱52.5M | 92% | High risk94 | —-0.004 |
| 25I00097ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0699+071 - K0700+000, K0697+535 - K0697+663, K0698+032 - K0698+163 | Region VIII | Region VIII | On-Going | ₱33.8M | 50% | High risk93 | Flagged0.007 |
| 25I00095ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OD ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) K0698+541 - K0968+613 | Region VIII | Region VIII | On-Going | ₱14.5M | 61% | High risk92 | Flagged0.006 |
| 25I00114ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0692+684 - K0692+761 | Region VIII | Region VIII | On-Going | ₱14.5M | 92% | High risk92 | —-0.005 |
| 25IK0051CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OF FLOOD CONTROL STRUCTURE, ANTIAO BRIDGE IV (CATBALOGAN DIVERSION BRIDGE), STA. 0+926.31-STA. 1+040.00, BRGY, SAN ANDRES, CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱62.7M | 74% | High risk92 | —-0.008 |
| 23IK0073CONSTRUCTION OF CATBALOGAN DRAINAGE SYSTEM (ANTIAO CREEK AND OUTFALLS), CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱101.3M | 98% | High risk83 | Flagged0.017 |
| 23IK0104CONST. OF MULTI-PURPOSE BLDG.- CONST. OF DPWH SAMAR 2ND DEO NEW BLDG., CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱96.5M | 93% | High risk83 | Flagged0.020 |
| 24IK0099CONSTRUCTION OF MULTI-PURPOSE BUILDING- CONST. OF DPWH SAMAR 2ND DEO NEW BUILDING, CATBALOGAN CITY, | Region VIII | Samar 2nd DEO | On-Going | ₱77.2M | 69% | High risk81 | Flagged0.009 |
| 24IC0149ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - BAGAHUPI-BABATNGON-STA. CRUZ-BARUGO-CARIGARA ROAD, K0918+000 - K0920+000, BABATNGON, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱49M | 100% | High risk81 | —-0.036 |
| 23IK0078CONSTRUCTION OF MULTI-PURPOSE BUILDING, LAGUNDI, CATBALOGAN CITY, SAMAR (PHASE I) | Region VIII | Samar 2nd DEO | On-Going | ₱48.2M | 85% | High risk81 | Flagged0.013 |
| 24IJ0075CSSP: CONSTRUCTION OF MULTI-PURPOSE BUILDING (LEGISLATIVE BUILDING), GANDARA, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱49.2M | 28% | High risk81 | Flagged0.018 |
| 24IJ0067CSSP: CONSTRUCTION OF ROAD, BRGY. QUEZON - CANTAGUIC ROAD, SAN JORGE, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱39.5M | 100% | High risk78 | —-0.039 |
| 22I00107CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN ANDRES, CATBALOGAN CITY, SAMAR | Region VIII | Region VIII | On-Going | ₱123.3M | 93% | High risk67 | —-0.021 |
| 24IK0041CONSTRUCTION OF CATBALOGAN DRAINAGE SYSTEM, CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱95.4M | 77% | High risk64 | —-0.017 |
| 24IM0104CONCRETING OF BRGY. 103 PALANOG TO BRGY. 104 SALVACION FMR PHASE II, BRGY. 103 PALANOG AND BRGY. 104 SALVACION, TACLOBAN CITY, LEYTE | Region VIII | Tacloban City DEO | On-Going | ₱99.4M | 25% | High risk64 | Flagged0.031 |
| 24IK0033CONST. OF FLOOD CONTROL BUCALAN BRIDGE, BARANGAY CANDUYOCAN, SAN SEBASTIAN, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱96.4M | 99% | High risk64 | —-0.025 |
| 22IJ0082OO2: CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PULID RIVER, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱93.9M | 100% | High risk63 | —-0.056 |
| 23IK0077CONSTRUCTION OF MULTI-PURPOSE BUILDING AT EASTERN VISAYAS REGIONAL SCIENCE HIGH SCHOOL BUILDING, GUINDAPUNAN, CATBALOGAN CITY | Region VIII | Samar 2nd DEO | Completed | ₱77.5M | 100% | High risk62 | —-0.082 |
| 24IK0089CONST. OF MULTI-PURPOSE BUILDING, CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱58.8M | 1% | High risk62 | —-0.016 |
| 24IK0095CONSTRUCTION OF PHASE III OF THE NEW PROVINCIAL HOSPITAL PROJECT, CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱66.8M | 48% | High risk62 | —-0.031 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24IM0104CONCRETING OF BRGY. 103 PALANOG TO BRGY. 104 SALVACION FMR PHASE II, BRGY. 103 PALANOG AND BRGY. 104 SALVACION, TACLOBAN CITY, LEYTE | Region VIII | Tacloban City DEO | On-Going | ₱99.4M | 25% | High risk64 | Flagged0.031 |
| 23IK0104CONST. OF MULTI-PURPOSE BLDG.- CONST. OF DPWH SAMAR 2ND DEO NEW BLDG., CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱96.5M | 93% | High risk83 | Flagged0.020 |
| 24IJ0075CSSP: CONSTRUCTION OF MULTI-PURPOSE BUILDING (LEGISLATIVE BUILDING), GANDARA, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱49.2M | 28% | High risk81 | Flagged0.018 |
| 23IK0073CONSTRUCTION OF CATBALOGAN DRAINAGE SYSTEM (ANTIAO CREEK AND OUTFALLS), CATBALOGAN CITY, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱101.3M | 98% | High risk83 | Flagged0.017 |
| 23IM0121CONSTRUCTION OF 4STY20CL, ST. FRANCIS INTEGRATED SCHOOL, TACLOBAN CITY, LEYTE | Region VIII | Tacloban City DEO | On-Going | ₱60M | 67% | High risk61 | Flagged0.015 |
| 23IK0078CONSTRUCTION OF MULTI-PURPOSE BUILDING, LAGUNDI, CATBALOGAN CITY, SAMAR (PHASE I) | Region VIII | Samar 2nd DEO | On-Going | ₱48.2M | 85% | High risk81 | Flagged0.013 |
| 24IK0099CONSTRUCTION OF MULTI-PURPOSE BUILDING- CONST. OF DPWH SAMAR 2ND DEO NEW BUILDING, CATBALOGAN CITY, | Region VIII | Samar 2nd DEO | On-Going | ₱77.2M | 69% | High risk81 | Flagged0.009 |
| 25I00097ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0699+071 - K0700+000, K0697+535 - K0697+663, K0698+032 - K0698+163 | Region VIII | Region VIII | On-Going | ₱33.8M | 50% | High risk93 | Flagged0.007 |
| 23IM0119CONSTRUCTION OF 4STY20CL, ANIBONG DREAMVILLE ELEMENTARY SCHOOL, TACLOBAN CITY, LEYTE | Region VIII | Tacloban City DEO | On-Going | ₱60M | 83% | High risk61 | Flagged0.007 |
| 25I00095ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OD ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) K0698+541 - K0968+613 | Region VIII | Region VIII | On-Going | ₱14.5M | 61% | High risk92 | Flagged0.006 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 176 | 21IK0058CONCRETING OF BRGY. PABANOG TO BRGY. TIGBAWON FMR PHASE 1, PARANAS, SAMAR, STA. 1+300 - STA. 1+920 | Region VIII | Samar 2nd DEO | Completed | ₱11.8M | 100% | Medium risk46 | —-0.044 |
| 177 | 19IJ0215(RE-ADVERTISED) CONCRETING OF BRGY.MACATINGOG - BRGY. DAWO FMR (PHASE II), BRGY.MACATINGOG AND BRGY. DAWO, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱9.1M | 100% | Medium risk45 | —-0.041 |
| 178 | 22IJ0093CONCRETING OF BRGY. PANLAYAHAN TO BRGY. CAYBAGO FMR PHASE II, BRGY. PANLAYAHAN AND BRGY. CAYBAGO, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱11.8M | 100% | Medium risk45 | —-0.043 |
| 179 | 18IJ0150CONCRETING OF BRGY. LAPAZ - BRGY. OSMEÑA FMR, BRGY. LAPAZ AND BRGY. OSMEÑA, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱8.2M | 100% | Medium risk45 | —-0.039 |
| 180 | 22IJ0097CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOM SCHOOL BUILDING, CALANYUGAN ELEMENTARY SCHOOL, PAGSANGHAN, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱5.2M | 100% | Medium risk43 | —-0.054 |
| 181 | 18IJ0112CONSTRUCTION OF MULTIPURPOSE BUILDING (LEGISLATIVE BUILDING) BARANGAY POBLACION C, TARANGNAN, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱4.7M | 100% | Medium risk42 | —-0.098 |
| 182 | 17IJ0227RE-ESTABLISHMENT OF STORAGE FACILITY SAN JORGE, SAN JORGE, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱9M | 100% | Medium risk41 | —-0.029 |
| 183 | 17IJ0202CONSTRUCTION OF TWO (2) STOREY - SIX (6) CLASSROOM SCHOOL BUILDING, TABAWAN INTEGRATED SCHOOL, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱11.9M | 100% | Medium risk40 | —-0.028 |
| 184 | 17IJ0205CONSTRUCTION OF TWO (2) STOREY - SIX (6) CLASSROOM SCHOOL BUILDING, MAG-UBAY NATIONAL HIGH SCHOOL, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱11.9M | 100% | Medium risk40 | —-0.028 |
| 185 | 17IJ0161CONSTRUCTION OF THREE (3) STOREY - SIX (6) CLASSROOM SCHOOL BUILDING, TINAMBACAN CENTRAL SCHOOL, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱13.9M | 100% | Medium risk40 | —-0.028 |
| 186 | 17IJ0111CLUSTER A: CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS) | Region VIII | Samar 1st DEO | Completed | ₱1.1M | 100% | Medium risk38 | —-0.038 |
| 187 | 17IJ0113CLUSTER C: CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS) | Region VIII | Samar 1st DEO | Completed | ₱938.3K | 100% | Medium risk38 | —-0.036 |
| 188 | 17IJ0112CLUSTER B: CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS) | Region VIII | Samar 1st DEO | Completed | ₱1.1M | 100% | Medium risk38 | —-0.038 |
| 189 | 19IJ0016CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE II) BRGY. CAPOOCAN, CALBAYOG, CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱2M | 100% | Low risk26 | —-0.097 |
| 190 | 21IJ0006CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE II),BRGY. SALJAG, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱2M | 100% | Low risk26 | —-0.097 |
| 191 | 19IJ0177LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM-BUILDINGS AND OTHER STRUCTURES-MULTI-PURPOSE/FACILITIES,CONSTRUCTION OF MULTI-PURPOSE BUILDING,BRGY.VILLAHERMOSA,STO.NIÑO,SAMAR | Region VIII | Samar 1st DEO | Completed | ₱4.7M | 100% | Low risk26 | —-0.098 |
| 192 | 20IJ0027LOCAL PROGRAM: CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. KERIKITE,ALMAGRO,SAMAR | Region VIII | Samar 1st DEO | Completed | ₱4.7M | 100% | Low risk26 | —-0.098 |
| 193 | 21IJ0080CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. TIGDARANAO, TARANGNAN,SAMAR | Region VIII | Samar 1st DEO | Completed | ₱2M | 100% | Low risk26 | —-0.096 |
| 194 | 19IJ0193LOCAL PROGRAM: CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TAMBONGAN, GANARA SAMAR | Region VIII | Samar 1st DEO | Completed | ₱4.7M | 100% | Low risk26 | —-0.097 |
| 195 | 20IJ0045LOCAL PROGRAM: CONSTRUCTION OF MULTI-PURPOSE BUILDING,BRGY. GUIN-ON, CALBAYOG CITY,SAMAR | Region VIII | Samar 1st DEO | Completed | ₱4.7M | 100% | Low risk26 | —-0.097 |
| 196 | 19IJ0170LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM - BUILDING AND OTHER STRUCTURES - MULTI-PURPOSE/FACILITIES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, LEGISLATIVE BUILDING-PHASE II), BRGY.POBLACION C, TARANGNAN,SAMAR | Region VIII | Samar 1st DEO | Completed | ₱4.7M | 100% | Low risk26 | —-0.098 |
| 197 | 20IJ0073CONSTRUCTION OF MULTIPURPOSE BUILDING, BRGY. MATOBATO, CALBAYOG CITY, WESTERN SAMAR | Region VIII | Samar 1st DEO | Completed | ₱4.7M | 100% | Low risk25 | —-0.097 |
| 198 | 20IJ0035LOCAL PROGRAM: CONSTRUCTION OF MULTI-PURPOSE BUILDING,BRGY. SUGOD, TARANGNAN, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱2.8M | 100% | Low risk25 | —-0.097 |
| 199 | 19IJ0179LOCAL PROGRAM: CONSTRUCTION OF MULTI-PURPOSE BUILDING,BARANGAY CABUNGAAN,STO.NIÑO,SAMAR | Region VIII | Samar 1st DEO | Completed | ₱2.8M | 100% | Low risk25 | —-0.097 |
| 200 | 20IJ0037LOCAL PROGRAM: CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. CARAYMAN, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | Completed | ₱2.3M | 100% | Low risk25 | —-0.097 |