Contractor dossier
10 projects on file, including joint ventures this contractor is part of.
Total projects
10
Total budget
₱102.2M
Average progress
77.1%
Completion rate
30.0%
Below 70%
Average risk score
54.1
Medium risk on average, out of 100
Flagged as unusual
3
30.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Cordillera Administrative Region | 10 | ₱102.2M | 54.1 | 3 | 77.1% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 5 | ₱53.9M | 48.5 | 1 | 63.6% |
| Roads | 4 | ₱43.4M | 50.8 | 1 | 98.8% |
| GAA 2025 SSP | 1 | ₱4.9M | 94.8 | 1 | 57.8% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25PL0110CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF MABALBALANAY-AGBANNAWAG BOX CULVERT, TABUK CITY, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱4.9M | 58% | High risk95 | Flagged0.018 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25PL0110CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF MABALBALANAY-AGBANNAWAG BOX CULVERT, TABUK CITY, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱4.9M | 58% | High risk95 | Flagged0.018 |
| 24PL0076CONCRETING OF ALOY TO TAWANG, BRGY. GUILAYON FMR, GUILAYON, TABUK CITY, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱16.8M | 95% | Medium risk51 | Flagged0.009 |
| 23PL0112CONSTRUCTION OF 1STY5CL, TOPPAN INTEGRATED SCHOOL, TABUK, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱11.4M | 94% | Medium risk53 | Flagged0.005 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25PL0110CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF MABALBALANAY-AGBANNAWAG BOX CULVERT, TABUK CITY, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱4.9M | 58% | High risk95 | Flagged0.018 |
| 2 | 23PL0078CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY. SAN JUAN, TABUK CITY, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱9.9M | 100% | Medium risk54 | —-0.078 |
| 3 | 24PL0115CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP): BASIC INFRASTRUCTURE PROGRAM (BIP) - EVACUATION CENTERS/ QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION OF KALINGA GABRIELA MIJA KIM MEDICAL CENTER, TABUK CITY | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱14.8M | 14% | Medium risk53 | —-0.010 |
| 4 | 24PL0118CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - EVACUATION CENTERS/ QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION (COMPLETION) OF MION KIM MEDICAL CENTER, BARANGAY AGBANNAWAG, TABUK CITY, KALINGA PROV | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱14.8M | 11% | Medium risk53 | —-0.010 |
| 5 | 23PL0112CONSTRUCTION OF 1STY5CL, TOPPAN INTEGRATED SCHOOL, TABUK, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱11.4M | 94% | Medium risk53 | Flagged0.005 |
| 6 | 24PL0060CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES - CONSTRUCTION OF SAN FRANCISCO - FF CRUZ - CALLAGDAO - CS-BLOCK 3 - | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱5.6M | 100% | Medium risk51 | —-0.046 |
| 7 | 22PL0059BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES - CONSTRUCTION OF PUROK 4/TUGA/GREENHILLS ACCESS ROAD, BRGY. CALANAN/TUGA/BULANAO, TABUK CITY, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱4.8M | 100% | Medium risk51 | —-0.080 |
| 8 | 24PL0076CONCRETING OF ALOY TO TAWANG, BRGY. GUILAYON FMR, GUILAYON, TABUK CITY, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱16.8M | 95% | Medium risk51 | Flagged0.009 |
| 9 | 21PL0100ASSET PRESERVATION - REHABILITATION/ RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS-KALINGA-CAGAYAN RD (CALANAN-ENRILE SECTION) - K0510 + 438 - K0510 + 538, K0510 + 644 - K0510 + 768, K0512 + 000 - K0512 + 294, | Cordillera Administrative Region | Lower Kalinga DEO | Completed | ₱16.2M | 100% | Medium risk51 | —-0.078 |
| 10 | 24PL0075CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MALALAO, TABUK CITY, KALINGA | Cordillera Administrative Region | Lower Kalinga DEO | On-Going | ₱3M | 100% | Low risk29 | —-0.044 |