47 projects on file, including joint ventures this contractor is part of.
Total projects
47
Total budget
₱822.1M
Average progress
97.9%
Completion rate
91.5%
Average risk score
39.5
Medium risk on average, out of 100
Flagged as unusual
2
4.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IX | 47 | ₱822.1M | 39.5 | 2 | 97.9% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Water Provision and Storage | 31 | ₱676.4M | 36.0 | 0 | 99.2% |
| Roads | 9 | ₱96.7M | 41.6 | 0 | 100.0% |
| Buildings and Facilities | 5 | ₱19.6M | 37.3 | 0 | 100.0% |
| OTHER | 2 | ₱29.4M | 88.6 | 2 | 64.2% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25JF0055CONCRETING OF BRGY. BALANSAG FMR, BRGY. BALANSAG, ROSELLER T. LIM, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | On-Going | ₱14.9M | 72% | High risk89 | Flagged0.054 |
| 25JD0078CONCRETING OF BRGY. LUX TO BRGY. SAS FMR, BRGY. LUX AND BRGY. SAS, GUTALAC, ZAMBOANGA DEL NORTE - MODIFIED TO: CONCRETING OF BRGY. LUX, GUTALAC, ZAMBOANGA DEL NORTE | Region IX | Zamboanga del Norte 3rd DEO | On-Going | ₱14.5M | 57% | High risk88 | Flagged0.057 |
| 17JF0016CONSTRUCTION OF VARIOUS WATER SUPPLY PROJECTS IN ZAMBOANGA SIBGUAY, IPIL ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱76.4M | 100% | High risk66 | —-0.001 |
| 17JF0021CONSTRUCTION OF VARIOUS WATER SUPPLY PROJECTS IN TITAY, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱69.6M | 100% | High risk66 | —-0.002 |
| 16JF0053CONST./ COMPLETION/ REHAB OF BUILDING AND OTHER STRUCTURES (CLUSTERED) A.) CONST. MPB (BRGY. HALL) BRGY. COLORAN, SIAY, Z.S B.) CONST. OF MPB (BRGY. HALL) BRGY. MAGSAYSAY, SIAY Z.S C.) CONST. OF MPB BRGY. KIMUS, SIAY, Z.S 2ND LD | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱5.9M | 100% | High risk60 | —-0.056 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25JD0078CONCRETING OF BRGY. LUX TO BRGY. SAS FMR, BRGY. LUX AND BRGY. SAS, GUTALAC, ZAMBOANGA DEL NORTE - MODIFIED TO: CONCRETING OF BRGY. LUX, GUTALAC, ZAMBOANGA DEL NORTE | Region IX | Zamboanga del Norte 3rd DEO | On-Going | ₱14.5M | 57% | High risk88 | Flagged0.057 |
| 25JF0055CONCRETING OF BRGY. BALANSAG FMR, BRGY. BALANSAG, ROSELLER T. LIM, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | On-Going | ₱14.9M | 72% | High risk89 | Flagged0.054 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25JF0055CONCRETING OF BRGY. BALANSAG FMR, BRGY. BALANSAG, ROSELLER T. LIM, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | On-Going | ₱14.9M | 72% | High risk89 | Flagged0.054 |
| 2 | 25JD0078CONCRETING OF BRGY. LUX TO BRGY. SAS FMR, BRGY. LUX AND BRGY. SAS, GUTALAC, ZAMBOANGA DEL NORTE - MODIFIED TO: CONCRETING OF BRGY. LUX, GUTALAC, ZAMBOANGA DEL NORTE | Region IX | Zamboanga del Norte 3rd DEO | On-Going | ₱14.5M | 57% | High risk88 | Flagged0.057 |
| 3 | 17JF0016CONSTRUCTION OF VARIOUS WATER SUPPLY PROJECTS IN ZAMBOANGA SIBGUAY, IPIL ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱76.4M | 100% | High risk66 | —-0.001 |
| 4 | 17JF0021CONSTRUCTION OF VARIOUS WATER SUPPLY PROJECTS IN TITAY, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱69.6M | 100% | High risk66 | —-0.002 |
| 5 | 16JF0053CONST./ COMPLETION/ REHAB OF BUILDING AND OTHER STRUCTURES (CLUSTERED) A.) CONST. MPB (BRGY. HALL) BRGY. COLORAN, SIAY, Z.S B.) CONST. OF MPB (BRGY. HALL) BRGY. MAGSAYSAY, SIAY Z.S C.) CONST. OF MPB BRGY. KIMUS, SIAY, Z.S 2ND LD | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱5.9M | 100% | High risk60 | —-0.056 |
| 6 | 22JI0036CONSTRUCTION OF LEVEL III WATER SUPPLY SYSTEM, OLUTANGA, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱56.9M | 100% | Medium risk55 | —-0.031 |
| 7 | 18JI0069CONSTRUCTION OF WATER SUPPLY PROJECT, PAYAO, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱67.5M | 100% | Medium risk55 | —-0.041 |
| 8 | 18JF0073CONSTRUCTION OF WATER SUPPLY PROJECT, TUNGAWAN, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱67M | 100% | Medium risk54 | —-0.026 |
| 9 | 18JF0074CONSTRUCTION OF WATER SUPPLY PROJECT, NAGA, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱58.4M | 100% | Medium risk54 | —-0.027 |
| 10 | 24JI0016CONSTRUCTION OF WATER SUPPLY SYSTEM (LEVEL III), BUUG, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | On-Going | ₱49M | 74% | Medium risk53 | —-0.010 |
| 11 | 21JI0028CONSTRUCTION OF LEVEL III WATER SUPPLY SYSTEM, DIPLAHAN, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱52.3M | 100% | Medium risk53 | —-0.040 |
| 12 | 21JC0011REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS LILOY-IPIL RD - K1971 + 450 - K1971 + 498, ZN. | Region IX | Zamboanga del Norte 3rd DEO | Completed | ₱28.7M | 100% | Medium risk52 | —-0.080 |
| 13 | 24JF0060CONCRETING OF BRGY. MARSOLO TO BRGY. SULO FMR, NAGA, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱21.2M | 100% | Medium risk51 | —-0.031 |
| 14 | 22JI0037CONSTRUCTION OF LEVEL III WATER SUPPLY SYSTEM, TALUSAN, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱49M | 100% | Medium risk51 | —-0.032 |
| 15 | 20JC0046CONSTRUCTION OF LEVEL III WATER SUPPLY SYSTEM, TAMPILISAN, ZAMBOANGA DEL NORTE | Region IX | Zamboanga del Norte 3rd DEO | Completed | ₱49M | 100% | Medium risk50 | —-0.039 |
| 16 | 22JF0020CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADE, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT), BRGY. TAMBANAN ROAD CONNECTING BRGY. TAMBANAN AND JUNCTION NATIONAL HIGHWAY IN SU | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱9.7M | 100% | Medium risk50 | —-0.086 |
| 17 | 22JF0040CONSTRUCTION OF LOCAL ROAD, BARANGAY KITABOG TO BARANGAY CAMANGA, TITAY, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱7.9M | 100% | Medium risk50 | —-0.085 |
| 18 | 23JF0025CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - BRGY. ROAD CONNECTING IMAVEMCO TO JUNCTION NATIONAL HIGHWAY IN SUPPORT OF NOOD | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱11.3M | 100% | Medium risk49 | —-0.086 |
| 19 | 20JI0061CONSTRUCTION OF LEVEL III WATER SUPPLY SYSTEM, IMELDA, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱39.2M | 100% | Medium risk49 | —-0.043 |
| 20 | 20JC0027CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, KALAWIT, ZAMBOANGA DEL NORTE | Region IX | Zamboanga del Norte 3rd DEO | Completed | ₱5M | 100% | Medium risk48 | —-0.078 |
| 21 | 23JI0035CONSTRUCTION OF WATER SYSTEM, BARANGAY GANDAAN, OLUTANGA, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.045 |
| 22 | 23JI0040CONSTRUCTION OF WATER SYSTEM, BARANGAY NOQUE, OLUTANGA, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.045 |
| 23 | 23JI0033CONSTRUCTION OF WATER SYSTEM, BARANGAY BATERIA, OLUTANGA, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.045 |
| 24 | 23JI0046CONSTRUCTION OF WATER SYSTEM, BARANGAY TANDU COMOT MABUHAY, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.045 |
| 25 | 25JD0023CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY POBLACION, GUTALAC, ZAMBOANGA DEL NORTE | Region IX | Zamboanga del Norte 3rd DEO | Completed | ₱11.8M | 100% | Medium risk47 | —-0.044 |