Contractor dossier
13 projects on file, including joint ventures this contractor is part of.
Total projects
13
Total budget
₱67.7M
Average progress
89.4%
Completion rate
76.9%
Average risk score
27.9
Low risk on average, out of 100
Flagged as unusual
2
15.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XII | 11 | ₱59.8M | 29.1 | 2 | 87.4% |
| Region XIII | 2 | ₱7.9M | 21.2 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 8 | ₱34.3M | 13.6 | 0 | 100.0% |
| GAA 2025 SSP | 2 | ₱10.8M | 91.6 | 2 | 31.0% |
| Water Provision and Storage | 2 | ₱18.5M | 25.0 | 0 | 100.0% |
| Roads | 1 | ₱4.1M | 20.8 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25ME0106CONSTRUCTION OF TALUS MULTI-PUPOSE BUILDING, TALUS, MALUNGON, SARANGANI PROVINCE | Region XII | Sarangani DEO | On-Going | ₱5.9M | 33% | High risk93 | Flagged0.038 |
| 25ME0120COMPLETION OF SITIO DATAL BACA MULTI-PURPOSE BUILDING, DATAL BATONG, MALUNGON, SARANGANI PROVINCE | Region XII | Sarangani DEO | On-Going | ₱4.9M | 29% | High risk90 | Flagged0.033 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25ME0106CONSTRUCTION OF TALUS MULTI-PUPOSE BUILDING, TALUS, MALUNGON, SARANGANI PROVINCE | Region XII | Sarangani DEO | On-Going | ₱5.9M | 33% | High risk93 | Flagged0.038 |
| 25ME0120COMPLETION OF SITIO DATAL BACA MULTI-PURPOSE BUILDING, DATAL BATONG, MALUNGON, SARANGANI PROVINCE | Region XII | Sarangani DEO | On-Going | ₱4.9M | 29% | High risk90 | Flagged0.033 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25ME0106CONSTRUCTION OF TALUS MULTI-PUPOSE BUILDING, TALUS, MALUNGON, SARANGANI PROVINCE | Region XII | Sarangani DEO | On-Going | ₱5.9M | 33% | High risk93 | Flagged0.038 |
| 2 | 25ME0120COMPLETION OF SITIO DATAL BACA MULTI-PURPOSE BUILDING, DATAL BATONG, MALUNGON, SARANGANI PROVINCE | Region XII | Sarangani DEO | On-Going | ₱4.9M | 29% | High risk90 | Flagged0.033 |
| 3 | 24NC0076CONSTRUCTION OF SCHOOL BUILDING IN CAIGANGAN ELEMENTARY SCHOOL, BRGY. CAIGANGAN, VERUELA, AGUSAN DEL SUR | Region XIII | Agusan del Sur 2nd DEO | Completed | ₱5M | 100% | Medium risk31 | —-0.036 |
| 4 | 23ME0090CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY KAPATAN, GLAN, SARANGANI PROVINCE | Region XII | Sarangani DEO | Completed | ₱8.8M | 100% | Low risk25 | —-0.042 |
| 5 | 23ME0100CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY LUTAY, MALUNGON, SARANGANI PROVINCE | Region XII | Sarangani DEO | Completed | ₱9.7M | 100% | Low risk25 | —-0.049 |
| 6 | 24M00165INSTALLATION/APPLICATION/CONSTRUCTION OF SIGNAGE, PAVEMENT MARKINGS, AND PEDESTRIAN REFUGE ISLAND ALONG FILIPINO-AMERICAN FRIENDSHIP AVE. - K1665 + 500 - K1666 + 499, GENERAL SANTOS CITY, SOUTH COTABATO | Region XII | Region XII | On-Going | ₱4.1M | 100% | Low risk21 | —-0.052 |
| 7 | 23ME0097CONSTRUCTION OF LUMATIL MULTI-PURPOSE BUILDING (BARANGAY HALL), MAASIM, SARANGANI PROVINCE | Region XII | Sarangani DEO | Completed | ₱5.8M | 100% | Low risk16 | —-0.037 |
| 8 | 17ME0095CLUSTER 14: 1. CONST. OF (1) STOREY (2) CL BLDG. @ SAN ROQUE ES; 2. CONST. OF (1) STOREY (3) CL BLDG. @ SAN JUAN IS, ALL OF MALUNGON, SARANGANI PROVINCE | Region XII | Sarangani DEO | Completed | ₱6.3M | 100% | Low risk15 | —-0.015 |
| 9 | 17ME0131CONST. OF (1) STOREY, (4) CL BLDG. @ TONGA LIM SIAO IS, GLAN, SARANGANI PROVINCE | Region XII | Sarangani DEO | Completed | ₱4.7M | 100% | Low risk14 | —-0.005 |
| 10 | 24NC0042CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY DEL MONTE, VERUELA, AGISAM DE; SIR | Region XIII | Agusan del Sur 2nd DEO | Completed | ₱3M | 100% | Low risk12 | —-0.077 |
| 11 | 17ME0132CONST. OF (1) STOREY, (4) CL BLDG @ LAMLANGIL ES, MALUNGON, SARANGANI PROVINCE | Region XII | Sarangani DEO | Completed | ₱4.7M | 100% | Low risk11 | —-0.010 |
| 12 | 24MB0039CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY BUAYAN, GENERAL SANTOS CITY, SOUTH COTABATO | Region XII | South Cotabato 1st DEO | Completed | ₱3M | 100% | Low risk6 | —-0.078 |
| 13 | 18ME0010CONST./REHAB. OF BARANGAY HALL, KIBLAT, MALUNGON, SARANGANI PROVINCE | Region XII | Sarangani DEO | Completed | ₱1.8M | 100% | Low risk3 | —-0.083 |