Opening the dossier…
Opening the dossier…
Contractor dossier
4 projects on file, including joint ventures this contractor is part of.
Total projects
4
Total budget
₱19.2M
Average progress
67.0%
Completion rate
0.0%
Below 70%
Average risk score
54.1
Medium risk on average, out of 100
Flagged as unusual
1
25.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-A | 4 | ₱19.2M | 54.1 | 1 | 67.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Water Provision and Storage | 4 | ₱19.2M | 54.1 | 1 | 67.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DB0205CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION OF PUBLIC WATER SYSTEM, BRGY. SABANG, TUY, BATANGAS | Region IV-A | Batangas 1st DEO | On-Going | ₱4.8M | 33% | High risk70 | Flagged0.002 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25DB0205CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION OF PUBLIC WATER SYSTEM, BRGY. SABANG, TUY, BATANGAS | Region IV-A | Batangas 1st DEO | On-Going | ₱4.8M | 33% | High risk70 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25DB0205CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION OF PUBLIC WATER SYSTEM, BRGY. SABANG, TUY, BATANGAS | Region IV-A | Batangas 1st DEO | On-Going | ₱4.8M | 33% | High risk70 | Flagged0.002 |
| 2 | 25DB0210CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION OF WATER SYSTEM, PAYAPA IBABA, LEMERY, BATANGAS | Region IV-A | Batangas 1st DEO | On-Going | ₱4.8M | 41% | Medium risk49 | —-0.024 |
| 3 | 25DB0211CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION OF WATER SYSTEM, PAYAPA ILAYA, LEMERY, BATANGAS | Region IV-A | Batangas 1st DEO | On-Going | ₱4.8M | 100% | Medium risk49 | —-0.044 |
| 4 | 25DB0203CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION OF PUBLIC WATER SYSTEM, BRGY. TAKLANG ANAK, CITY OF CALACA, BATANGAS | Region IV-A | Batangas 1st DEO | On-Going | ₱4.8M | 94% | Medium risk49 | —-0.040 |