Opening the dossier…
Opening the dossier…
Contractor dossier
243 projects on file, including joint ventures this contractor is part of.
Total projects
243
Total budget
₱3.9B
Average progress
98.3%
Completion rate
91.4%
Average risk score
44.2
Medium risk on average, out of 100
Flagged as unusual
15
6.2% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region I | 219 | ₱3.3B | 44.4 | 12 | 99.2% |
| Region III | 14 | ₱163.4M | 36.0 | 0 | 100.0% |
| National Capital Region | 8 | ₱436M | 51.1 | 3 | 87.5% |
| Negros Island Region | 2 | ₱63.1M | 53.0 | 0 | 30.9% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 129 | ₱2B | 42.4 | 5 | 97.3% |
| Roads | 66 | ₱954.8M | 43.2 | 7 | 99.3% |
| Flood Control and Drainage | 34 | ₱952.4M | 55.2 | 3 | 99.5% |
| Water Provision and Storage | 9 | ₱30.2M | 35.7 | 0 | 100.0% |
| Bridges | 5 | ₱51.5M | 42.9 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24AA0384BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES: CONSTRUCTION OF MULTI PURPOSE BUILDING, (COVERED COURT) BARANGAY 11 LAGANDIT, PIDDIG, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱4.8M | 96% | High risk77 | —-0.041 |
| 23AA0362CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING (COVERED COURT), BARANGAY NO. 31, TALINGAAN, LAOAG CITY, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱4.7M | 98% | High risk76 | —-0.032 |
| 24AA0392BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES: CONSTRUCTION OF MULTI PURPOSE BUILDING, BARANGAY 02 SAN AGUSTIN, SARRAT, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱4.9M | 55% | High risk76 | —-0.022 |
| 21AA0080CONSTRUCTION OF ILOCOS NORTE PROVINCIAL CAPITOL MULTI-PURPOSE EXPANSION BUILDING, LAOAG CITY, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱99M | 100% | High risk73 | —-0.058 |
| 23AA0491CONSTRUCTION OF FLOOD MITIGATING STRUCTURE, BRGY. CABAROAN, PIDDIG, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱8.8M | 100% | High risk72 | Flagged0.017 |
| 24A00255BASIC INFRASTRUCTURE PROGRAM, REHABILITATION OF MULTI-PURPOSE BUILDING (GYMNASIUM), ILOCOS NORTE NATIONAL HIGH SCHOOL, PHASE II, BARANGAY 3, HERNANDO ST., LAOAG CITY | Region I | Region I | On-Going | ₱29.7M | 79% | High risk72 | —-0.030 |
| 23A00228SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), REHABILITATION OF MULTI-PURPOSE BUILDING (GYMNASIUM), ILOCOS NORTE NATIONAL HIGH SCHOOL, BARANGAY 3, HERNANDO ST., LAOAG CITY | Region I | Region I | Completed | ₱43.4M | 100% | High risk72 | —-0.077 |
| 17AB0044IMPROVEMENT /CONCRETING OF SAND DUNES ACCESS ROAD, PAOAY, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱39.7M | 100% | High risk72 | —-0.048 |
| 20AB0093CONSTRUCTION/UPGRADING /REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-PRIMARY ROADS, MANILA NORTH ROAD - K0484+480 - K0484+897 | Region I | Ilocos Norte 2nd DEO | Completed | ₱19.6M | 100% | High risk71 | —-0.084 |
| 18AA0232CONST. OF NATBAOAN BR. DRAINAGE SYSTEM & F/C ALONG MNR BRGY. PRAGATA PASUQUIN, I.N. | Region I | Ilocos Norte 1st DEO | Completed | ₱19M | 100% | High risk71 | —-0.064 |
| 21AB0012CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - TERTIARY ROADS, ILOCOS NORTE-APAYAO RD - K0484+047 - K0484+383, SAN NICOLAS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱9.8M | 100% | High risk71 | —-0.084 |
| 21AB0134CONCRETING/IMPROVEMENT OF DRAINAGE STRUCTURE FACILITIES, BRGY. 6, SAN NICOLAS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱12.4M | 100% | High risk71 | —-0.068 |
| 21AA0036REHABILITATION/IMPROVEMENT OF SORONG ROAD, PASUQUIN, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱11.8M | 100% | High risk71 | —-0.083 |
| 18AA0291CONCRETING OF NAMBARAN-ABKIR ROAD, BRGY. NAMBARAN, BACARRA, ILOCOS NORTE AND BRGY. ABKIR, VINTAR, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱20.8M | 100% | High risk71 | —-0.083 |
| 23AA0004ROAD WIDENING - SECONDARY ROADS - LAOAG-BALACCAD RD K0480+(-266) - K0480+000, K0480+(-301) - K0480+(-266), K0480+000 - K0481+522 | Region I | Region I | On-Going | ₱94.1M | 65% | High risk70 | —-0.015 |
| 24AA0313IMPROVEMENT OF MULTI-PURPOSE BUILDING, ILOCOS NORTE NATIONAL HIGH SCHOOL (INNHS), LAOAG CITY, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱4.9M | 100% | High risk70 | —-0.080 |
| 24AA0312IMPROVEMENT OF MULTI - PURPOSE BUILDING, ILOCOS NORTE COLLEGE OF ARTS AND TRADES (INCAT), LAOAG CITY, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱4.9M | 100% | High risk70 | —-0.080 |
| 23AA0499CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BURAYOC RIVER, PAGUDPUD, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱9.2M | 100% | High risk70 | Flagged0.018 |
| 17CN0135CONSTRUCTION OF SERIES OF GROUNDSILL ALONG DIDUAN (MANGLAD) RIVER, BRGY. DINADIAWAN, DIPACULAO, AURORA | Region III | Aurora DEO | Completed | ₱49M | 100% | High risk70 | —-0.056 |
| 23AA0259SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES -CONSTRUCTION OF SEAWALL, BARANGAY POBLACION 2, BURAYOC, PAGUDPUD, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱29.4M | 100% | High risk70 | —-0.064 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 22O00097RECONSTRUCTION/REHABILITATION OF OLD ENGINEERING OFFICE (EO) TO INTERNAL HOUSE AFFAIRS (IHAO) STAFF HOUSE BUILDING | National Capital Region | National Capital Region | On-Going | ₱34.6M | 0% | Medium risk39 | Flagged0.049 |
| 23AA0499CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BURAYOC RIVER, PAGUDPUD, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱9.2M | 100% | High risk70 | Flagged0.018 |
| 23AA0491CONSTRUCTION OF FLOOD MITIGATING STRUCTURE, BRGY. CABAROAN, PIDDIG, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱8.8M | 100% | High risk72 | Flagged0.017 |
| 17AB0235REPAIR/MAINTENANCE OF DAMAGED BANK PROTECTION ALONG BONGO RIVER, BRGY. ALBANO, DINGRAS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱45.8M | 100% | High risk62 | Flagged0.016 |
| 23O00088PROPOSED CONSTRUCTION OF NEB MULTI-LEVEL PARKING | National Capital Region | National Capital Region | On-Going | ₱96.5M | 100% | High risk63 | Flagged0.007 |
| 23O00087PROPOSED CONSTRUCTION OF ENGINEERING MULTI-LEVEL PARKING | National Capital Region | National Capital Region | On-Going | ₱91.6M | 100% | Medium risk58 | Flagged0.006 |
| 23AA0478CONSTRUCTION OF 1STY2CL, MMSU LABORATORY ELEMENTARY SCHOOL, LAOAG CITY, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱4.8M | 100% | High risk66 | Flagged0.004 |
| 24AA0468CONSTRUCTION OF 4-STOREY 8-CLASSROOM SCHOOL BUILDING IN SHAMROCK ELEMENTARY SCHOOL, BARANGAY 7-B, LAOAG CITY, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱24.9M | 93% | High risk67 | Flagged0.004 |
| 17AB0057CONCRETING OF BRGY. SINAMAR FMR, BRGY. SINAMAR, BANNA, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱1.9M | 100% | Low risk16 | Flagged0.003 |
| 17AB0056CONCRETING OF BRGY. CRISPINA FMR, BRGY. CRISPINA, BANNA, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱1.9M | 100% | Low risk16 | Flagged0.002 |
| 17AB0069CONCRETING OF BRGY. NAGUILIAN FMR, BRGY. NAGUILIAN, NUEVA ERA, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱2M | 100% | Low risk17 | Flagged0.002 |
| 17AB0055CONCRETING OF BRGY. BARBARANGAY FMR, BRGY. BARBARANGAY, BANNA, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱1.9M | 100% | Low risk16 | Flagged0.002 |
| 17AB0058CONCRETING OF BAOA WEST FMR, BRGY. BAOA WEST, BATAC, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱1.9M | 100% | Low risk16 | Flagged0.002 |
| 17AB0068CONCRETING OF BRGY. GUIDIGID FMR, BRGY. GUIDIGID, NUEVA ERA, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱1.9M | 100% | Low risk17 | Flagged0.001 |
| 17AB0067CONCRETING OF BRGY. GARNADEN FMR, BRGY. GARNADEN, NUEVA ERA, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱1.9M | 100% | Low risk17 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24AA0384BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES: CONSTRUCTION OF MULTI PURPOSE BUILDING, (COVERED COURT) BARANGAY 11 LAGANDIT, PIDDIG, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱4.8M | 96% | High risk77 | —-0.041 |
| 2 | 23AA0362CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING (COVERED COURT), BARANGAY NO. 31, TALINGAAN, LAOAG CITY, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱4.7M | 98% | High risk76 | —-0.032 |
| 3 | 24AA0392BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES: CONSTRUCTION OF MULTI PURPOSE BUILDING, BARANGAY 02 SAN AGUSTIN, SARRAT, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱4.9M | 55% | High risk76 | —-0.022 |
| 4 | 21AA0080CONSTRUCTION OF ILOCOS NORTE PROVINCIAL CAPITOL MULTI-PURPOSE EXPANSION BUILDING, LAOAG CITY, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱99M | 100% | High risk73 | —-0.058 |
| 5 | 23AA0491CONSTRUCTION OF FLOOD MITIGATING STRUCTURE, BRGY. CABAROAN, PIDDIG, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱8.8M | 100% | High risk72 | Flagged0.017 |
| 6 | 24A00255BASIC INFRASTRUCTURE PROGRAM, REHABILITATION OF MULTI-PURPOSE BUILDING (GYMNASIUM), ILOCOS NORTE NATIONAL HIGH SCHOOL, PHASE II, BARANGAY 3, HERNANDO ST., LAOAG CITY | Region I | Region I | On-Going | ₱29.7M | 79% | High risk72 | —-0.030 |
| 7 | 23A00228SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), REHABILITATION OF MULTI-PURPOSE BUILDING (GYMNASIUM), ILOCOS NORTE NATIONAL HIGH SCHOOL, BARANGAY 3, HERNANDO ST., LAOAG CITY | Region I | Region I | Completed | ₱43.4M | 100% | High risk72 | —-0.077 |
| 8 | 17AB0044IMPROVEMENT /CONCRETING OF SAND DUNES ACCESS ROAD, PAOAY, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱39.7M | 100% | High risk72 | —-0.048 |
| 9 | 20AB0093CONSTRUCTION/UPGRADING /REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-PRIMARY ROADS, MANILA NORTH ROAD - K0484+480 - K0484+897 | Region I | Ilocos Norte 2nd DEO | Completed | ₱19.6M | 100% | High risk71 | —-0.084 |
| 10 | 18AA0232CONST. OF NATBAOAN BR. DRAINAGE SYSTEM & F/C ALONG MNR BRGY. PRAGATA PASUQUIN, I.N. | Region I | Ilocos Norte 1st DEO | Completed | ₱19M | 100% | High risk71 | —-0.064 |
| 11 | 21AB0012CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - TERTIARY ROADS, ILOCOS NORTE-APAYAO RD - K0484+047 - K0484+383, SAN NICOLAS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱9.8M | 100% | High risk71 | —-0.084 |
| 12 | 21AB0134CONCRETING/IMPROVEMENT OF DRAINAGE STRUCTURE FACILITIES, BRGY. 6, SAN NICOLAS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱12.4M | 100% | High risk71 | —-0.068 |
| 13 | 21AA0036REHABILITATION/IMPROVEMENT OF SORONG ROAD, PASUQUIN, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱11.8M | 100% | High risk71 | —-0.083 |
| 14 | 18AA0291CONCRETING OF NAMBARAN-ABKIR ROAD, BRGY. NAMBARAN, BACARRA, ILOCOS NORTE AND BRGY. ABKIR, VINTAR, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱20.8M | 100% | High risk71 | —-0.083 |
| 15 | 23AA0004ROAD WIDENING - SECONDARY ROADS - LAOAG-BALACCAD RD K0480+(-266) - K0480+000, K0480+(-301) - K0480+(-266), K0480+000 - K0481+522 | Region I | Region I | On-Going | ₱94.1M | 65% | High risk70 | —-0.015 |
| 16 | 24AA0313IMPROVEMENT OF MULTI-PURPOSE BUILDING, ILOCOS NORTE NATIONAL HIGH SCHOOL (INNHS), LAOAG CITY, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱4.9M | 100% | High risk70 | —-0.080 |
| 17 | 24AA0312IMPROVEMENT OF MULTI - PURPOSE BUILDING, ILOCOS NORTE COLLEGE OF ARTS AND TRADES (INCAT), LAOAG CITY, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱4.9M | 100% | High risk70 | —-0.080 |
| 18 | 23AA0499CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BURAYOC RIVER, PAGUDPUD, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | On-Going | ₱9.2M | 100% | High risk70 | Flagged0.018 |
| 19 | 17CN0135CONSTRUCTION OF SERIES OF GROUNDSILL ALONG DIDUAN (MANGLAD) RIVER, BRGY. DINADIAWAN, DIPACULAO, AURORA | Region III | Aurora DEO | Completed | ₱49M | 100% | High risk70 | —-0.056 |
| 20 | 23AA0259SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES -CONSTRUCTION OF SEAWALL, BARANGAY POBLACION 2, BURAYOC, PAGUDPUD, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱29.4M | 100% | High risk70 | —-0.064 |
| 21 | 22AB0147CONCRETING OF BRGY. SAN AGUSTIN FMR, BRGY. SAN AGUSTIN, SAN NICOLAS, ILOCOS NORTE | Region I | Ilocos Norte 2nd DEO | Completed | ₱10M | 100% | High risk70 | —-0.032 |
| 22 | 23A00173CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - MARUAYA-DUPITAC-CALAMBEG-ESTANCIA ROAD LEADING TO LOWLAND COFFEE CONVERGENCE INITIATIVE PROJECT, BRGY. MARUAYA, PIDDIG, ILOCO | Region I | Region I | Completed | ₱57.9M | 100% | High risk70 | —-0.077 |
| 23 | 22A00231SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - CONSTRUCTION OF WATERWAY STRUCTURE ALONG BARUYEN RIVER, BRGY. BARUYEN, BANGUI, ILOCOS NORTE (PHASE I) | Region I | Region I | Completed | ₱48.2M | 100% | High risk70 | —-0.064 |
| 24 | 21AA0097CONSTRUCTION OF RIVER CONTROL SYSTEM, (PHASE 3 AND PHASE 4), BARANGAY TAGUIPORO, BANGUI, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱8.8M | 100% | High risk70 | —-0.067 |
| 25 | 21AA0098CONSTRUCTION/IMPROVEMENT OF RIVER CONTROL SYSTEM (PHASE II), BARANGAY TAGUIPORO, BANGUI, ILOCOS NORTE | Region I | Ilocos Norte 1st DEO | Completed | ₱9.8M | 100% | High risk69 | —-0.063 |