129 projects on file, including joint ventures this contractor is part of.
Total projects
129
Total budget
₱4.9B
Average progress
96.6%
Completion rate
93.0%
Average risk score
39.9
Medium risk on average, out of 100
Flagged as unusual
4
3.1% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XIII | 124 | ₱4.6B | 39.9 | 4 | 96.5% |
| Cordillera Administrative Region | 2 | ₱168.7M | 55.8 | 0 | 100.0% |
| Region X | 2 | ₱66.6M | 20.4 | 0 | 100.0% |
| Region VII | 1 | ₱43.6M | 46.2 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 43 | ₱1.6B | 42.1 | 0 | 96.5% |
| Flood Control and Drainage | 37 | ₱1.9B | 41.7 | 0 | 96.4% |
| Buildings and Facilities | 31 | ₱393.1M | 25.4 | 0 | 100.0% |
| Bridges | 10 | ₱378.3M | 41.2 | 0 | 99.3% |
| OTHER | 6 | ₱352.4M | 72.1 | 2 | 81.9% |
| GAA 2025 SSP | 1 | ₱59.6M | 94.8 | 1 | 60.5% |
| Bridges, Roads | 1 | ₱212.3M | 61.9 | 1 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25NE0029IMPROVEMENT OF ROAD LEADING TO DPWH DINAGAT ISLANDS DISTRICT ENGINEERING OFFICE, BARANGAY WILSON, SAN JOSE, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱59.6M | 60% | High risk95 | Flagged0.016 |
| 17N00056OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, DINAGAT-LORETO RD, K0001+000-K0002+860, K0016+468 - K0019+328, K0019+350 - K0019+700, K0020+520 - K0021+700, K0023+259 - K0024+000, K0024+740 - K0025+103, K0025+128 - K0025+489, K0025+505 - K0026+000, K0028+ | Region XIII | Region XIII | Completed | ₱112.7M | 100% | High risk79 | —-0.021 |
| 24NE0079CONSTRUCTION OF DRAINAGE SYSTEM AT SAN JOSE, SAN JOSE, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱72.4M | 91% | High risk77 | Flagged0.005 |
| 19NH0051LIANGA COASTAL BYPASS ROAD (SDCR ALTERNATIVE ROUTE), LIANGA, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱50.8M | 100% | High risk77 | —-0.022 |
| 25NG0052CONSTRUCTION OF DPWH - SURIGAO DEL NORTE 2ND DEO BUILDING, SURIGAO CITY, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱48.9M | 0% | High risk77 | Flagged0.022 |
| 19NH0065PACKAGE 8 - COMPLETION OF COVERED COURT, BRGY. SAN PEDRO, CANTILAN, SURIGAO DEL SUR & CONSTRUCTION OF MULTI-PURPOSE BUILDING BRGY. ESPERANZA, CARMEN, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱4.9M | 100% | High risk74 | —-0.028 |
| 17N00166ROAD CONSTRUCTION FROM BRGY. MAHANUB - POYAWON ROAD WITH BRIDGE COMPONENT PHASE 3A, ALEGRIA - GIGAQUIT, SURIGAO DEL NORTE | Region XIII | Region XIII | Completed | ₱212.3M | 100% | High risk62 | Flagged0.027 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 17N00166ROAD CONSTRUCTION FROM BRGY. MAHANUB - POYAWON ROAD WITH BRIDGE COMPONENT PHASE 3A, ALEGRIA - GIGAQUIT, SURIGAO DEL NORTE | Region XIII | Region XIII | Completed | ₱212.3M | 100% | High risk62 | Flagged0.027 |
| 25NG0052CONSTRUCTION OF DPWH - SURIGAO DEL NORTE 2ND DEO BUILDING, SURIGAO CITY, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | On-Going | ₱48.9M | 0% | High risk77 | Flagged0.022 |
| 25NE0029IMPROVEMENT OF ROAD LEADING TO DPWH DINAGAT ISLANDS DISTRICT ENGINEERING OFFICE, BARANGAY WILSON, SAN JOSE, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱59.6M | 60% | High risk95 | Flagged0.016 |
| 24NE0079CONSTRUCTION OF DRAINAGE SYSTEM AT SAN JOSE, SAN JOSE, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | On-Going | ₱72.4M | 91% | High risk77 | Flagged0.005 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 101 | 21NE0089REPAIR/REHABILITATION OF DPWH BUILDING INCLUDING OTHER FACILITIES @ DPWH DINAGAT ISLANDS DISTRICT ENGINEERING OFFICE, BRGY. CUARINTA, SAN JOSE, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | Completed | ₱9.8M | 100% | Medium risk36 | —-0.082 |
| 102 | 21NG0061CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL) / GIGAQUIT, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱9.9M | 100% | Medium risk36 | —-0.079 |
| 103 | 21NG0062CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL) (PHASE 2) / GIGAQUIT, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱9.9M | 100% | Medium risk36 | —-0.080 |
| 104 | 21NG0067IMPROVEMENT OF MUNICIPAL LEGISLATIVE BUILDING GIGAQUIT, SURIGAO DEL NORTE/GIGAQUIT, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱5.1M | 100% | Medium risk35 | —-0.081 |
| 105 | 19NH0105CONCRETING OF BRGY. CABAS-AN SILOP SPRING FMR, BRGY. CABAS-AN, CANTILAN, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱10M | 100% | Medium risk34 | —-0.032 |
| 106 | 19NH0097CONCRETING OF BRGY. GAMUTON NATIONAL ROAD JUNCTION - ZONE 1 FMR, BRGY. GAMUTON, LANUZA, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱10M | 100% | Medium risk33 | —-0.027 |
| 107 | 18ND0117CONSTRUCTION OF FOUR-STOREY EIGHT CLASSROOMS SCHOOL BUILDING @ BUTUAN CITY SCHOOL OF ARTS & TRADES, BUTUAN CITY | Region XIII | Butuan City DEO | Completed | ₱21.7M | 100% | Medium risk33 | —-0.040 |
| 108 | 23NE0161REHABILITATION OF MULTI-PURPOSE BUILDING BARANGAY DON RUBEN, SAN JOSE, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | Completed | ₱4.8M | 100% | Medium risk32 | —-0.084 |
| 109 | 23NE0169REHABILITATION OF MULTI-PURPOSE BUILDING BARANGAY LUNA, SAN JOSE, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | Completed | ₱4.8M | 100% | Medium risk32 | —-0.084 |
| 110 | 23NE0173REHABILITATION OF MULTI-PURPOSE BUILDING BARANGAY SAN JUAN, SAN JOSE, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | Completed | ₱4.7M | 100% | Medium risk30 | —-0.079 |
| 111 | 17NG0014REPAIR/REHAB. OF MULTIPURPOSE BUILDING (MUNICIPAL GYM), BRGY. PILARING, PILAR, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 1st DEO | Completed | ₱2M | 100% | Low risk27 | —-0.051 |
| 112 | 17KH0025CONSTRUCTION OF CLASSROOMS: BULUA NHS, 4-STY, 20-CL, CDOC | Region X | Cagayan de Oro City 1st DEO | Completed | ₱31.6M | 100% | Low risk20 | —-0.020 |
| 113 | 17KH0093CONSTRUCTION OF CLASSROOMS: 4STY16CL BULUA NHS (3 - HE CL, 1 - LEC RM, 2 - SPEECH LAB, 4 - SCIENCE LAB), BRGY. BULUA, CAGAYAN DE ORO CITY | Region X | Cagayan de Oro City 1st DEO | Completed | ₱35M | 100% | Low risk20 | —-0.020 |
| 114 | 20NG0028ASSET PRESERVATION - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS SURIGAO WHARF ROAD/ SURIGAO CITY, SURIGAO DEL NORTE, K1126+455 - K1126+515 | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱4.4M | 100% | Low risk19 | —-0.083 |
| 115 | 17NH0061CONSTRUCTION OF SMALL MULTI-PURPOSE BUILDING, MAGASANG, CANTILAN, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱1.9M | 100% | Low risk19 | —-0.052 |
| 116 | 16NE0097REHABILITATION/REPAIR OF TAGBABOY BR. (B00082DG) ALONG DINAGAT - LORETO ROAD, BRGY. NAVARRO, TUBAJON, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | Completed | ₱921.2K | 100% | Low risk18 | —-0.024 |
| 117 | 19NG0042NETWORK DEVELOPMENT - ROAD WIDENING - TERTIARY ROADS ALONG DAANG MAHARLIKA (LIPATA-SURIGAO SECTION, Y LENGTH)/BRGY. LUNA, SURIGAO CITY, SURIGAO DEL NORTE, CHAINAGE 0 - CHAINAGE 35 | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱1.2M | 100% | Low risk18 | —-0.085 |
| 118 | 18NH0169PACKAGE 10-CONSTRUCTION/COMPLETION OF BHS FOR THE FF. LOCATION: A) CONSTRUCTION OF TWO (2) STOREY RHU BUILDING (PHASE 1), CANTILAN, SURIGAO DEL SUR B) COMPLETION OF BRGY. HEALTH STATION, BRGY. MATHO, CORTES, SURIGAO DEL SUR, CANTILAN & CORTES, SURIGAO DEL | Region XIII | Surigao del Sur 1st DEO | Completed | ₱2.4M | 100% | Low risk13 | —-0.031 |
| 119 | 23NE0101CONSTRUCTION OF 1STY2CL, SAN JOSE ELEMENTARY SCHOOL, CAGDIANAO, DINAGAT ISLANDS | Region XIII | Dinagat Islands DEO | Completed | ₱4.6M | 100% | Low risk13 | —-0.042 |
| 120 | 19NH0055PACKAGE 3-COMPLETION OF COVERED COURT, BRGY. CABAS-AN & CONST. OF MULTI-PURPOSE BLDG,.BRGY. CONSUELO,CANTILAN,SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱3.9M | 100% | Low risk12 | —-0.078 |
| 121 | 20NH0034CONSTRUCTION OF 1STY 2CL, SAN ANTONIO ELEMENTARY SCHOOL, TANDAG CITY, SURIGAO DEL SUR (132975) | Region XIII | Surigao del Sur 1st DEO | Completed | ₱4.1M | 100% | Low risk12 | —-0.036 |
| 122 | 18NH0163PACKAGE 6 - COMPLETION OF BARANGAY HEALTH STATION (BHS) FOR THE FOLLOWING LOCATION:A.) BRGY SAN ANTONIO,B.) BRGY. UNION,C.) BRGY. SAN ROQUE, D.)BRGY. PATONG-PATONG & E.)BRGY. SAN VICENTE, MADRID, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱3.2M | 100% | Low risk12 | —-0.035 |
| 123 | 18NH0164PACKAGE 7 - COMPLETION/CONSTRUCTION OF BARANGAY HEALTH STATION FOR THE FOLLOWING LOCATION:A.)BRGY. CONSUELO, CANTILAN B.)BRGY. CALAGDAAN, CANTILAN & C.) BRGY. PANAYUGON, MADRID, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱2.9M | 100% | Low risk12 | —-0.037 |
| 124 | 20NH0033CONSTRUCTION OF 1STY 2CL, BIOTO ELEMENTARY SCHOOL, TANDAG CITY, SURIGAO DEL SUR (132959) | Region XIII | Surigao del Sur 1st DEO | Completed | ₱4.1M | 100% | Low risk12 | —-0.036 |
| 125 | 21NG0064CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL) / GIGAQUIT, SURIGAO DEL NORTE | Region XIII | Surigao del Norte 2nd DEO | Completed | ₱1.2M | 100% | Low risk9 | —-0.074 |