7 projects on file, including joint ventures this contractor is part of.
Total projects
7
Total budget
₱234.5M
Average progress
100.0%
Completion rate
100.0%
Average risk score
44.5
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region II | 6 | ₱230.5M | 48.2 | 0 | 100.0% |
| Cordillera Administrative Region | 1 | ₱4.1M | 22.2 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 3 | ₱30.3M | 39.4 | 0 | 100.0% |
| Flood Control and Drainage | 1 | ₱95.1M | 62.6 | 0 | 100.0% |
| Bridges | 1 | ₱95.3M | 60.7 | 0 | 100.0% |
| Buildings and Facilities | 1 | ₱9.8M | 48.1 | 0 | 100.0% |
| Water Provision and Storage | 1 | ₱4.1M | 22.2 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 21BG0128LOCAL PROGRAM - FLOOD CONTROL STRUCTURES/FACILITIES -CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CAGAYAN RIVER BANK - BARANGAY CANANGAN, ANGADANAN, ISA | Region II | Isabela 3rd DEO | Completed | ₱95.1M | 100% | High risk63 | —-0.053 |
| 21B00005ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - BATU BRIDGE (B01227LZ) ALONG DAANG MAHARLIKA (LZ) | Region II | Region II | Completed | ₱95.3M | 100% | High risk61 | —-0.034 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 21BG0128LOCAL PROGRAM - FLOOD CONTROL STRUCTURES/FACILITIES -CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CAGAYAN RIVER BANK - BARANGAY CANANGAN, ANGADANAN, ISA | Region II | Isabela 3rd DEO | Completed | ₱95.1M | 100% | High risk63 | —-0.053 |
| 2 | 21B00005ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - BATU BRIDGE (B01227LZ) ALONG DAANG MAHARLIKA (LZ) | Region II | Region II | Completed | ₱95.3M | 100% | High risk61 | —-0.034 |
| 3 | 21BI0058LOCAL PROGRAM-CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-BUILDING AND OTHER STRUCTURES-MULTIPURPOSE /FACILITIES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, SOLANO, NUEVA VIZCAYA | Region II | Nueva Vizcaya DEO | Completed | ₱9.8M | 100% | Medium risk48 | —-0.089 |
| 4 | 20BI0075CONCRETING OF BRGY. BAKIR TO BRGY. STA. LUCIA FMR, BRGY. BAKIR & BRGY. STA. LUCIA, BAGABAG, NUEVA VIZCAYA | Region II | Nueva Vizcaya DEO | Completed | ₱9.5M | 100% | Medium risk40 | —-0.033 |
| 5 | 20BI0078CONCRETING OF BRGY. VILLARINA TO BRGY. STA. LUCIA FMR, BRGY. VILLARINA AND BRGY. STA. LUCIA, BAGABAG, NUEVA VIZCAYA | Region II | Nueva Vizcaya DEO | Completed | ₱8.8M | 100% | Medium risk39 | —-0.033 |
| 6 | 21BI0068CONCRETING OF BRGY. IPIL-CUNEG FMR BRGY. IPIL-CUNEG, BAYOMBONG, NUEVA VIZCAYA | Region II | Nueva Vizcaya DEO | Completed | ₱11.9M | 100% | Medium risk39 | —-0.033 |
| 7 | 20P00040CONSTRUCTION / REHABILITATION OF WATER SUPPLY / SEPTAGE AND SEWERAGE / RAIN WATER COLLECTOR SYSTEMS - RAIN WATER COLLECTORS IN PUBLIC FACILITIES - CAR | Cordillera Administrative Region | Cordillera Administrative Region | Completed | ₱4.1M | 100% | Low risk22 | —-0.047 |