25 projects on file, including joint ventures this contractor is part of.
Total projects
25
Total budget
₱311.6M
Average progress
90.4%
Completion rate
72.0%
Average risk score
54.1
Medium risk on average, out of 100
Flagged as unusual
1
4.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region V | 25 | ₱311.6M | 54.1 | 1 | 90.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 11 | ₱101M | 46.1 | 0 | 99.9% |
| Roads | 10 | ₱113.1M | 55.2 | 0 | 86.2% |
| Flood Control and Drainage | 2 | ₱48M | 53.0 | 0 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱35.1M | 93.9 | 0 | 77.8% |
| GAA 2025 SSP | 1 | ₱14.4M | 93.7 | 1 | 20.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25FI0023ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - LAGTA - CROSSING - MALINTA RD (S00017MT) - K0107+902 - K0108+440, CITY OF MASBATE, MASBATE | Region V | Masbate 2nd DEO | On-Going | ₱35.1M | 78% | High risk94 | —-0.003 |
| 25FM0055CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BATUAN CENTRAL SCHOOL, BATUAN, MASBATE. | Region V | Masbate 1st DEO | On-Going | ₱14.4M | 20% | High risk94 | Flagged0.020 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25FI0023ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - LAGTA - CROSSING - MALINTA RD (S00017MT) - K0107+902 - K0108+440, CITY OF MASBATE, MASBATE | Region V | Masbate 2nd DEO | On-Going | ₱35.1M | 78% | High risk94 | —-0.003 |
| 2 | 25FM0055CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BATUAN CENTRAL SCHOOL, BATUAN, MASBATE. | Region V | Masbate 1st DEO | On-Going | ₱14.4M | 20% | High risk94 | Flagged0.020 |
| 3 | 23FI0010CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM - ACCESS ROADS AND /OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES-CONSTRUCTION AND ROAD-JUNCTION NATIONAL ROAD TO BARANGAY CALUMPANG, MILAG | Region V | Masbate 2nd DEO | Completed | ₱29.7M | 100% | Medium risk58 | —-0.097 |
| 4 | 24FJ0032CSSP- BIP- ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/ S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF ROAD, SIMAWA- BONIFACIO ROAD, USON, MASBATE | Region V | Masbate 3rd DEO | On-Going | ₱9.7M | 100% | Medium risk58 | —-0.065 |
| 5 | 24FJ0033CSSP- BIP- ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/ S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF ROAD, MARCELLA- CENTRO ROAD, USON, MASBATE | Region V | Masbate 3rd DEO | Completed | ₱9.8M | 100% | Medium risk58 | —-0.098 |
| 6 | 24FJ0040CSSP- BIP- ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/ S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF CONCRETE ROAD, BRGY. LIBERTAD, MUNICIPALITY OF USON, MASBATE PROVINCE | Region V | Masbate 3rd DEO | Completed | ₱4.8M | 100% | Medium risk58 | —-0.097 |
| 7 | 25FJ0016CSSP- BIP- ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF ROAD, BARANGAY POBLACION, USON, MASBATE | Region V | Masbate 3rd DEO | On-Going | ₱4.8M | 0% | Medium risk57 | —-0.041 |
| 8 | 24FJ0037CSSP- BIP- ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/ S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF CONCRETE ROAD, BRGY. NABUHAY, MUNICIPALITY OF USON, MASBATE PROVINCE | Region V | Masbate 3rd DEO | Completed | ₱4.9M | 100% | Medium risk57 | —-0.099 |
| 9 | 24FJ0019CSSP- BIP- ACESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF ROAD, CAGBATANG- MAHAYAHAY ROAD, CATAINGAN, MASBATE | Region V | Masbate 3rd DEO | Completed | ₱9.9M | 100% | Medium risk57 | —-0.096 |
| 10 | 21FJ0002CONSTRUCTION OF MULTI-PURPOSE BUILDING-CONSTRUCTION OF PLACER MUNICIPAL HOSPITAL (PHASE 1), PLACER, MASBATE | Region V | Masbate 3rd DEO | Completed | ₱9.9M | 100% | Medium risk56 | —-0.096 |
| 11 | 22FI0005BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION OF ROAD, JUNCTION NATIONAL ROAD TO BARANGAY BURI, STA.0+500 - STA.1+336, MANDAON, MASBATE | Region V | Masbate 2nd DEO | Completed | ₱24.7M | 100% | Medium risk55 | —-0.097 |
| 12 | 22FI0037FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SEAWALL, STA.0+000 - STA.0+058 (CONSTRUCTION), POBLACION, AROROY, MASBATE | Region V | Masbate 2nd DEO | Completed | ₱24.5M | 100% | Medium risk53 | —-0.085 |
| 13 | 23FJ0014OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF DIVISORIA FLOOD CONTROL, STA. 0+110.00- STA. 0+290.00, UPSTREAM RIGHT SIDE, CAWAYAN, MASBATE | Region V | Masbate 3rd DEO | Completed | ₱23.5M | 100% | Medium risk53 | —-0.085 |
| 14 | 21FI0043CONCRETING OF BRGY. UMABAY INTERIOR TO BRGY. BAANG TO BRGY. SAWMILL FMR, STA. 3+960 - STA. 4+180, NET LENGTH = 0.440 LANE KM (0.220 KM), MOBO, MASBATE | Region V | Masbate 2nd DEO | Completed | ₱9.9M | 100% | Medium risk52 | —-0.047 |
| 15 | 20FJ0020CONSTRUCTION OF ONE(1) UNIT TWO(2) STOREY SIX(6) CLASSROOM SCHOOL BUILDING AT DALIPE ELEMENTARY SCHOOL, CAWAYAN, MASBATE | Region V | Masbate 3rd DEO | Completed | ₱18.2M | 100% | Medium risk51 | —-0.053 |
| 16 | 22FM0038CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING, BUENAVISTA INTEGRATED SCHOOL. | Region V | Masbate 1st DEO | Completed | ₱4.8M | 100% | Medium risk48 | —-0.052 |
| 17 | 24FJ0070CONSTRUCTION OF 1- STOREY 2- CLASSROOM SCHOOL BUILDING IN AURORA ELEMENTARY SCHOOL, BARANGAY AURORA, MUNICIPALITY OF USON, MASBATE PROVINCE | Region V | Masbate 3rd DEO | On-Going | ₱7.4M | 99% | Medium risk47 | —-0.017 |
| 18 | 24FJ0072CONSTRUCTION OF 1- STOREY 2- CLASSROOM SCHOOL BUILDING IN EULOGIO C. ADOPTANTE ELEMENTARY SCHOOL, BARANGAY SAN RAFAEL, MUNICIPALITY OF CATAINGAN, MASBATE PROVINCE | Region V | Masbate 3rd DEO | On-Going | ₱7.4M | 100% | Medium risk47 | —-0.016 |
| 19 | 18FJ0120CONSTRUCTION OF RURAL HEALTH UNIT, USON, MASBATE | Region V | Masbate 3rd DEO | Completed | ₱14.9M | 100% | Medium risk47 | —-0.047 |
| 20 | 18FJ0122CONSTRUCTION OF RURAL HEALTH UNIT, ESPERANZA, MASBATE | Region V | Masbate 3rd DEO | Completed | ₱14.9M | 100% | Medium risk47 | —-0.053 |
| 21 | 22FM0037CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING, BATUAN CENTRAL SCHOOL. | Region V | Masbate 1st DEO | Completed | ₱4.8M | 100% | Medium risk46 | —-0.050 |
| 22 | 23FM0045CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING, BATUAN CENTRAL SCHOOL. | Region V | Masbate 1st DEO | Completed | ₱5.4M | 100% | Medium risk46 | —-0.050 |
| 23 | 20FJ0034CONSTRUCTION OF ONE(1) UNIT ONE(1) STOREY FOUR(4) CLASSROOM SCHOOL BUILDING AT VILLA ELEMENTARY SCHOOL, ESPERANZA, MASBATE | Region V | Masbate 3rd DEO | Completed | ₱10M | 100% | Medium risk46 | —-0.056 |
| 24 | 25FJ0043OO1: NETWORK DEVELOPMENT PROGRAM- ROAD WIDENING- SECONDARY ROADS- BUENAVISTA- KAWAYAN RD- K0068+571- K0068+671 | Region V | Masbate 3rd DEO | On-Going | ₱4.7M | 62% | Medium risk42 | —-0.057 |
| 25 | 20FJ0029CONSTRUCTION OF ONE(1) UNIT ONE(1) STOREY ONE(1) CLASSROOM SCHOOL BUILDING AT BAGUMBAYAN ES, CATAINGAN, MASBATE | Region V | Masbate 3rd DEO | Completed | ₱3.2M | 100% | Low risk26 | —-0.051 |