Contractor dossier
47 projects on file, including joint ventures this contractor is part of.
Total projects
47
Total budget
₱243.4M
Average progress
99.4%
Completion rate
80.9%
Average risk score
33.9
Medium risk on average, out of 100
Flagged as unusual
1
2.1% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region II | 34 | ₱127.4M | 27.5 | 0 | 100.0% |
| Cordillera Administrative Region | 13 | ₱116.1M | 50.9 | 1 | 97.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 22 | ₱60.5M | 24.3 | 0 | 99.7% |
| Roads | 18 | ₱122.5M | 37.8 | 0 | 99.8% |
| OTHER | 4 | ₱26M | 58.3 | 0 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱27.8M | 92.7 | 1 | 80.6% |
| Flood Control and Drainage | 1 | ₱4.5M | 27.0 | 0 | 100.0% |
| Water Provision and Storage | 1 | ₱2.2M | 26.9 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25PC0055OO1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM - REHAB/ RECONSTRUCTION OF ROADS WITH SLIPS,SLOPE COLLAPSE, & LANDSLIDE-TERTIARY ROADS - APAYAO(CALANASAN)-ILOCOS NORTE RD-K0622+577-K0622+628, K0629+000 - K0629+045 | Cordillera Administrative Region | Apayao 2nd DEO | On-Going | ₱27.8M | 81% | High risk93 | Flagged0.002 |
| 22BC0066CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROLL-IT)-MANILA NORTH ROAD TO CALLUNGAN MASISIT ROAD LEADING TO COCONUT GROWERS, SANCHEZ MIRA, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱10.1M | 100% | High risk71 | —-0.023 |
| 21BC0018CSSP- CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROLL-IT) - JCT. MANILA NORTH ROAD LEADING TO COFFEE PLANTATION, LABLABIG, CLAVERIA, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱8.8M | 100% | High risk67 | —-0.023 |
| 21BC0117CSSP-CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM - TIKAS)-CONSTRUCTION OF BARRACKS, CLAVERIA MUNICIPAL POLICE, CLAVERIA, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱9.8M | 100% | High risk61 | —-0.046 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25PC0055OO1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM - REHAB/ RECONSTRUCTION OF ROADS WITH SLIPS,SLOPE COLLAPSE, & LANDSLIDE-TERTIARY ROADS - APAYAO(CALANASAN)-ILOCOS NORTE RD-K0622+577-K0622+628, K0629+000 - K0629+045 | Cordillera Administrative Region | Apayao 2nd DEO | On-Going | ₱27.8M | 81% | High risk93 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25PC0055OO1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM - REHAB/ RECONSTRUCTION OF ROADS WITH SLIPS,SLOPE COLLAPSE, & LANDSLIDE-TERTIARY ROADS - APAYAO(CALANASAN)-ILOCOS NORTE RD-K0622+577-K0622+628, K0629+000 - K0629+045 | Cordillera Administrative Region | Apayao 2nd DEO | On-Going | ₱27.8M | 81% | High risk93 | Flagged0.002 |
| 2 | 22BC0066CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROLL-IT)-MANILA NORTH ROAD TO CALLUNGAN MASISIT ROAD LEADING TO COCONUT GROWERS, SANCHEZ MIRA, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱10.1M | 100% | High risk71 | —-0.023 |
| 3 | 21BC0018CSSP- CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROLL-IT) - JCT. MANILA NORTH ROAD LEADING TO COFFEE PLANTATION, LABLABIG, CLAVERIA, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱8.8M | 100% | High risk67 | —-0.023 |
| 4 | 21BC0117CSSP-CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURES IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM - TIKAS)-CONSTRUCTION OF BARRACKS, CLAVERIA MUNICIPAL POLICE, CLAVERIA, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱9.8M | 100% | High risk61 | —-0.046 |
| 5 | 24PC0037OO1:ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - APAYAO-ILOCOS NORTE RD - K0657 + 900 - K0657 + 960 | Cordillera Administrative Region | Apayao 2nd DEO | On-Going | ₱7M | 100% | Medium risk58 | —-0.045 |
| 6 | 24PC0063ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - APAYAO-ILOCOS NORTE RD - K0658 + 820 - K0659 + 050 | Cordillera Administrative Region | Apayao 2nd DEO | On-Going | ₱6.1M | 100% | Medium risk58 | —-0.045 |
| 7 | 24PC0077CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS(SIPAG) -EVACUATION CENTERS/QUARANTINE FACILITIES/PUBLIC HEALTH FACILITES - CONSTRUCTION OF EVACUATION CENTER, BARANGAY MALUBIBIT, FLORA, APAYAO | Cordillera Administrative Region | Apayao 2nd DEO | On-Going | ₱9.8M | 93% | Medium risk56 | —-0.037 |
| 8 | 24PC0055CY 2024 BEFF - CONSTRUCTION OF CLASSROOMS, CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN LT. BALAG ELEMENTARY SCHOOL, BARANGAY LT. BALAG, PUDTOL, APAYAO | Cordillera Administrative Region | Apayao 2nd DEO | On-Going | ₱5.7M | 100% | Medium risk55 | —-0.005 |
| 9 | 24PC0041OO1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - APAYAO (CALANASAN)-ILOCOS NORTE RD - K0617 + 740 - K0617 + 810 | Cordillera Administrative Region | Apayao 2nd DEO | On-Going | ₱19.4M | 100% | Medium risk53 | —-0.044 |
| 10 | 24PC0056CY 2024 BEFF - CONSTRUCTION OF CLASSROOMS, CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN STA. FILOMENA ELEMENTARY SCHOOL, BARANGAY STA. FILOMENA, CALANASAN, APAYAO | Cordillera Administrative Region | Apayao 2nd DEO | On-Going | ₱5.6M | 100% | Medium risk53 | —-0.005 |
| 11 | 23BC0043CSSP-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROLL-IT)-CENTRO 2-NAGBARANGANAN-CAGAYAN STATE UNIVERSITY ROAD CONNECTING TO CACAO PLANTATION AREA IN SUPPORT OF CACAO INDUSTRY, CENTRO 2, SANCHEZ MIRA, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱3.7M | 100% | Medium risk53 | —-0.025 |
| 12 | 24PC0018ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - APAYAO-ILOCOS NORTE RD - K0660 + 065 - K0660 + 115 | Cordillera Administrative Region | Apayao 2nd DEO | On-Going | ₱10M | 100% | Medium risk52 | —-0.044 |
| 13 | 24PC0039OO1:ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - APAYAO-ILOCOS NORTE RD - K0668 + 100 - K0668 + 130 | Cordillera Administrative Region | Apayao 2nd DEO | On-Going | ₱7.9M | 98% | Medium risk52 | —-0.042 |
| 14 | 19PC0057PACKAGE III-A.) ROAD REHABILITATION ALONG CLAVERIA-CALANASAN-KABUGAO ROAD, K0638+700-K0642+000 W/ EXCEPTIONS, MARAGMIN SECTION, B.) ROAD REHABILITATION ALONG CLAVERIA-CALANASAN-KABUGAO ROAD K0643+100-K0649+200 W/ EXCEPTIONS, SALAGUNTING SECTION, CALANASAN | Cordillera Administrative Region | Apayao 2nd DEO | Completed | ₱9.9M | 100% | Medium risk44 | —-0.032 |
| 15 | 18PC0032PACKAGE III: 1) IMPROVEMENT OF TANGLAGAN NATIONAL HIGH SCHOOL, TANGLAGAN, CALANASAN, APAYAO, 2.) CONSTRUCTION OF DRAINAGE FACILITIES PEDRO BUNOT CENTRAL SCHOOL POBLACION, CALANASAN, APAYAO | Cordillera Administrative Region | Apayao 2nd DEO | Completed | ₱3.4M | 100% | Medium risk43 | —-0.046 |
| 16 | 21BC0153CONCRETING OF BRGY. STO. NIÑO FMR, BRGY. STO. NIÑO, CLAVERIA, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱14.8M | 100% | Medium risk42 | —-0.024 |
| 17 | 21BC0183CONSTRUCTION/COMPLETION OF 2 STOREY 4 LABORATORY AT STA. PRAXEDES HIGH SCHOOL, STA.PRAXEDES, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱5M | 100% | Medium risk42 | —-0.038 |
| 18 | 24BC0017CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION / IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURIST ROAD INFRASTRUCTURE PROGRAM - TRIP) - ACCESS ROAD LEADING TO GARAW-GARAW FALLS, KITTAG, SANCHEZ MIRA, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱9.7M | 100% | Medium risk42 | —-0.077 |
| 19 | 23BC0051CSSP-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROLL-IT)-PAGAY BARANGAY ROAD TO MANILA NORTH ROAD CONNECTING TO PINEAPPLE, COCONUT, BANANA, & CORN PLANTATION & PROCESSING, ABBANGKERUAN, PAMPLONA, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱6.2M | 100% | Medium risk40 | —-0.077 |
| 20 | 22BC0141CSSP-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROLL-IT)-CATARAOAN BARANGAY ROAD SECTION CONNECTING TO MANILA NORTH ROAD TO COFFEE PLANTATION AND CITRUS PLANTATION AND PROCESSING, CATARAOAN, CLAVERIA, CAGAYA | Region II | Cagayan 2nd DEO | Completed | ₱7.8M | 100% | Medium risk39 | —-0.077 |
| 21 | 22BC0060CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROLL-IT)-JCT. MANILA NORTH ROAD LEADING TO COFFEE PLANTATION, LABLABIG, CLAVERIA, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱4.9M | 100% | Medium risk39 | —-0.076 |
| 22 | 23BC0032CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-CLAVERIA BAY VIEW BOULEVARD INCLUDING ACCESS ROAD, CLAVERIA, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱5.2M | 100% | Medium risk38 | —-0.073 |
| 23 | 21BC0039LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY VILLA REY AND BARANGAY CATARAUAN, PIAT, CAGAYAN, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CENTRO SUR AND BARANGAY CENTRO NORTE, STO. NIÑO, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱3M | 100% | Medium risk30 | —-0.083 |
| 24 | 21BC0096LOCAL INFRASTRUCTURE PROGRAM-FLOOD CONTROL AND DRAINAGE-FLOOD CONTROL STRUCTURES/FACILITIES-CONSTRUCTION OF SLOPE PROTECTION ALONG NANGASANGAN CREEK, BARANGAY CENTRO 4, CLAVERIA, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱4.5M | 100% | Low risk27 | —-0.063 |
| 25 | 21BC0045WATER MANAGEMENT FACILITIES: CONSTRUCTION OF WATER SYSTEM AT BARANGAY BALANNI, STO. NIÑO, CAGAYAN | Region II | Cagayan 2nd DEO | Completed | ₱2.2M | 100% | Low risk27 | —-0.048 |