38 projects on file, including joint ventures this contractor is part of.
Total projects
38
Total budget
₱373.2M
Average progress
100.0%
Completion rate
100.0%
Average risk score
32.9
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VII | 38 | ₱373.2M | 32.9 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Bridges | 11 | ₱214.1M | 38.0 | 0 | 100.0% |
| Buildings and Facilities | 10 | ₱34.2M | 28.4 | 0 | 100.0% |
| Roads | 9 | ₱25.3M | 25.0 | 0 | 100.0% |
| Flood Control and Drainage | 5 | ₱85.8M | 43.6 | 0 | 100.0% |
| Water Provision and Storage | 2 | ₱5.5M | 23.7 | 0 | 100.0% |
| OTHER | 1 | ₱8.3M | 59.7 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 21H00002ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM, REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, CANSAGA BAY BR. (B00613CB) ALONG CANSAGA BAY BRIDGE | Region VII | Region VII | Completed | ₱144.7M | 100% | High risk65 | —-0.035 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 21HB0086001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- BRIDGE PROGRAM-RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES- TUBOD MONTE BRIDGE (BO0104BH) ALONG JCT (TER)-JAGNA-SIERRA BULLONES ROAD KO 066+090 | Region VII | Bohol 3rd DEO | Completed | ₱1.6M | 100% | Low risk19 | —-0.054 |
| 27 | 20HB0021RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES CAMAYAON BRIDGE (B00082BH) ALONG LOAY INTERIOR ROAD CARMEN, BOHOL KO 166 + 680 | Region VII | Bohol 3rd DEO | Completed | ₱1.4M | 100% | Low risk19 | —-0.056 |
| 28 | 20HB0004RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES TINOGDAN BRIDGE (B00042BH) ALONG TAGBILARAN EAST ROAD (TAGBILARAN-JAGNA) KO 232+285 | Region VII | Bohol 3rd DEO | Completed | ₱1.4M | 100% | Low risk19 | —-0.056 |
| 29 | 21HA0027REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - ANTEQUERA - SAN ISIDRO - LIBERTAD (TUBIGON) RD - K0039+824 - K0039+887 | Region VII | Bohol 1st DEO | Completed | ₱1M | 100% | Low risk18 | —-0.092 |
| 30 | 21HA0177CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY MAYACABAC, DAUIS, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱2M | 100% | Low risk18 | —-0.094 |
| 31 | 21HA0070CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT/EVACUATION CENTER @ CAMP FRANCISCO DAGOHOY), BARANGAY POBLACION III, TAGBILARAN CITY, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱4.2M | 100% | Low risk18 | —-0.094 |
| 32 | 20HA0089ROAD CONCRETING, BRGY. TABALONG, DAUIS, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱998K | 100% | Low risk18 | —-0.091 |
| 33 | 19HA0170CONCRETING OF BARANGAY ROAD, CALAYUGAN NORTE, LOON, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱495K | 100% | Low risk18 | —-0.092 |
| 34 | 20HA0057ROAD CONCRETING, BRGY. CANLAAS, ANTEQUERA, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱995K | 100% | Low risk18 | —-0.092 |
| 35 | 21HA0075REHABILITATION OF ROAD IN BARANGAY DOROL, BALILIHAN, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱980K | 100% | Low risk18 | —-0.092 |
| 36 | 21HA0186CONSTRUCTION OF MULTI-PURPOSE BUILDINGS (EVACUATION CENTER), BARANGAYS DATAG NORTE, DEL CARMEN ESTE AND SAN ROQUE, BALILIHAN, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱2.9M | 100% | Low risk18 | —-0.095 |
| 37 | 19HA0194CONSTRUCTION OF MULTI-PURPOSE BUILDING, MARIVELES, DAUIS, BOHOL | Region VII | Bohol 1st DEO | Completed | ₱2M | 100% | Low risk18 | —-0.092 |