Contractor dossier
23 projects on file, including joint ventures this contractor is part of.
Total projects
23
Total budget
₱458.8M
Average progress
89.4%
Completion rate
60.9%
Below 70%
Average risk score
49.5
Medium risk on average, out of 100
Flagged as unusual
1
4.3% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VII | 21 | ₱402.7M | 46.7 | 0 | 96.2% |
| Region V | 2 | ₱56.1M | 79.0 | 1 | 18.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 18 | ₱379.8M | 48.6 | 0 | 90.6% |
| Flood Control and Drainage | 2 | ₱32M | 46.9 | 0 | 100.0% |
| Buildings and Facilities | 2 | ₱9.4M | 38.0 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱37.7M | 93.9 | 1 | 26.2% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25FI0040CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES - CONSTRUCTION OF AROROY COASTAL ROAD, AROROY, MASBATE | Region V | Masbate 2nd DEO | On-Going | ₱37.7M | 26% | High risk94 | Flagged0.018 |
| 25FJ0055OO1: NETWORK DEVELOPMENT PROGRAM- ROAD WIDENING- SECONDARY ROADS- MASBATE- CATAINGAN- PLACER RD- K0020+200- K0020+321, K0020+885- K0021+142 | Region V | Masbate 3rd DEO | On-Going | ₱18.5M | 10% | High risk64 | —-0.014 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25FI0040CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES - CONSTRUCTION OF AROROY COASTAL ROAD, AROROY, MASBATE | Region V | Masbate 2nd DEO | On-Going | ₱37.7M | 26% | High risk94 | Flagged0.018 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25FI0040CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES - CONSTRUCTION OF AROROY COASTAL ROAD, AROROY, MASBATE | Region V | Masbate 2nd DEO | On-Going | ₱37.7M | 26% | High risk94 | Flagged0.018 |
| 2 | 25FJ0055OO1: NETWORK DEVELOPMENT PROGRAM- ROAD WIDENING- SECONDARY ROADS- MASBATE- CATAINGAN- PLACER RD- K0020+200- K0020+321, K0020+885- K0021+142 | Region V | Masbate 3rd DEO | On-Going | ₱18.5M | 10% | High risk64 | —-0.014 |
| 3 | 25HF0038CONVERGENCE AND SPECIAL SUPPORT PROGRAM SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONSTRUCTION OF ROAD, BARANGAY KAMANS | Region VII | Cebu 3rd DEO | On-Going | ₱48.8M | 97% | Medium risk54 | —-0.062 |
| 4 | 25HF0042CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY JAGBUAYA | Region VII | Cebu 3rd DEO | On-Going | ₱48.7M | 89% | Medium risk51 | —-0.060 |
| 5 | 25HF0077CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY MANGGA | Region VII | Cebu 3rd DEO | On-Going | ₱48.8M | 93% | Medium risk51 | —-0.060 |
| 6 | 25HF0078CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BRGY. MACU | Region VII | Cebu 3rd DEO | On-Going | ₱48.8M | 65% | Medium risk51 | —-0.053 |
| 7 | 25HF0076CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY SAN JUA | Region VII | Cebu 3rd DEO | On-Going | ₱48.8M | 85% | Medium risk51 | —-0.057 |
| 8 | 25HF0036CONVERGENCE AND SPECIAL SUPPORT PROGRAM BASIC INFRASTRUCTURE PROGRAM (BIP)BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONSTRUCTION OF ROAD, BARANGAY KAMANSI, TUBURAN, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.096 |
| 9 | 22HF0058CONSTRUCTION OF DRAINAGE SYSTEM AT BRGY. PUTAT, K0102+755 - K0103+052, TUBURAN, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱7.6M | 100% | Medium risk47 | —-0.077 |
| 10 | 24HF0011CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ALEGRIA-BANGKITO ROAD LEADING TO KABANGKALAN COFFEE PLANTATION, BRGY. ALEGRIA-BANGKITO, TUBURAN, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱29.3M | 100% | Medium risk47 | —-0.096 |
| 11 | 22HF0048CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT LANGOYON RIVER, BARANGAY POBLACION 8, UPSTREAM L/S, STA. 2+320 - STA. 2+519, TUBURAN, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱24.4M | 100% | Medium risk47 | —-0.078 |
| 12 | 25HF0056CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT )-ALEGRIA-BANGKITO ROAD LEADING TO KABA | Region VII | Cebu 3rd DEO | On-Going | ₱19.5M | 94% | Medium risk47 | —-0.062 |
| 13 | 25HF0017CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY COLONIA | Region VII | Cebu 3rd DEO | On-Going | ₱24.4M | 97% | Medium risk46 | —-0.062 |
| 14 | 22HF0069CONSTRUCTION OF ROAD, BARANGAY COLONIA TO BARANGAY MAGHAN-AY, TUBURAN, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱4.8M | 100% | Medium risk46 | —-0.094 |
| 15 | 24HF0052CONSTRUCTION OF ROAD IN BARANGAY COLONIA TO BARANGAY KAGBAO, TUBURAN, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.096 |
| 16 | 25HF0037CONVERGENCE AND SPECIAL SUPPORT PROGRAM BASIC INFRASTRUCTURE PROGRAM (BIP)BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONSTRUCTION OF ROAD, BARANGAY MONTEALEGRE, TUBURAN, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.096 |
| 17 | 24HF0088IMPROVEMENT OF SITIO MATNOG ROAD, BARANGAY YUTAT - BARANGAY KAMPOOT, TUBURAN, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.097 |
| 18 | 24HF0054CONSTRUCTION OF ROAD IN BARANGAY KALANGAHAN TO BARANGAY AMATUGAN, TUBURAN, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.096 |
| 19 | 24HF0053CONSTRUCTION OF ROAD IN BARANGAY TOMINJAO TO BARANGAY SIOTES, TUBURAN, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.096 |
| 20 | 23HF0048CONSTRUCTION OF ROAD, BARANGAY ALEGRIA-GIMAMA, TUBURAN, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.097 |
| 21 | 25HF0035: CONVERGENCE AND SPECIAL SUPPORT PROGRAM BASIC INFRASTRUCTURE PROGRAM (BIP) BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY MAG-ALWA, TUBURAN, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱4.9M | 100% | Medium risk45 | —-0.095 |
| 22 | 23HF0087CONSTRUCTION OF 1STY2CL, LUSONG NATIONAL HIGH SCHOOL, TUBURAN, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱4.7M | 100% | Medium risk39 | —-0.053 |
| 23 | 23HF0086CONSTRUCTION OF 1STY2CL, PATUPAT NHS, BARILI, CEBU | Region VII | Cebu 3rd DEO | Completed | ₱4.7M | 100% | Medium risk37 | —-0.052 |