Contractor dossier
91 projects on file, including joint ventures this contractor is part of.
Total projects
91
Total budget
₱4B
Average progress
93.7%
Completion rate
76.9%
Average risk score
53.9
Medium risk on average, out of 100
Flagged as unusual
5
5.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 91 | ₱4B | 53.9 | 5 | 93.7% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 51 | ₱2.2B | 50.2 | 0 | 93.3% |
| Flood Control and Drainage | 21 | ₱1B | 47.6 | 0 | 99.3% |
| OTHER | 5 | ₱149M | 78.1 | 2 | 97.7% |
| Buildings and Facilities | 5 | ₱107.8M | 50.6 | 0 | 100.0% |
| GAA 2025 OO-1 | 3 | ₱262.2M | 93.7 | 2 | 69.4% |
| Water Provision and Storage | 3 | ₱41.1M | 48.4 | 0 | 100.0% |
| GAA 2025 OO-2 | 2 | ₱116.5M | 91.7 | 0 | 58.9% |
| GAA 2025 SSP | 1 | ₱29.4M | 95.6 | 1 | 66.3% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25IK0013SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), CONSTRUCTION OF ROAD, BARANGAY HINICA-AN TO BARANGAY MALOBAGO, MOTIONG, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱29.4M | 66% | High risk96 | Flagged0.017 |
| 25I00093NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0831+800 - K0832+920 | Region VIII | Region VIII | On-Going | ₱84.8M | 67% | High risk95 | Flagged0.010 |
| 25II0007ROAD WIDENING, SECONDARY ROADS, PANGPANG-PALAPAG-MAPANAS-GAMAY-LAPINIG RD., K0806+200-K0808+000; K0811+105-K0811+700, NORTHERN SAMAR 2ND DISTRICT | Region VIII | Northern Samar 2nd DEO | On-Going | ₱144.6M | 56% | High risk93 | Flagged0.023 |
| 25I00132ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0778+265 - K0778+360 | Region VIII | Region VIII | On-Going | ₱32.7M | 85% | High risk92 | —-0.004 |
| 25IJ0010OO2: CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY BARRUZ, PHASE II, MATUGUINAO, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱67.5M | 98% | High risk92 | —-0.013 |
| 25IK0036CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BICAL BRIDGE ALONG SAN JUANICO - BASEY - SOHOTON ROAD, ST. RITA, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱49M | 19% | High risk91 | —-0.001 |
| 19II0110REPAIR/REHABILITATION OF NATIONAL ROAD, ALONG CATARMAN - LAOANG ROAD, BANTAYAN - SAN ROQUE SECTION, SITIO NAPERES, SAN ROQUE, N. SAMAR K0768+694 - K0768+808, SAN ROQUE, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱30M | 100% | High risk86 | Flagged0.014 |
| 24IK0077CONST. OF ROAD, BARANGAY GUIMBANGA TO BARANGAY ANTOL, CALBIGA, SAMAR, STA. 0+000.00-STA. 1+965.00 | Region VIII | Samar 2nd DEO | On-Going | ₱48.2M | 88% | High risk82 | Flagged0.005 |
| 18II0014CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS, SECONDARY ROADS, PANGPANG-PALAPAG-MAPANAS-GAMAY-LAPINIG ROAD, K0826+100 - K0826+684, 2ND DISTRICT, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱18.3M | 100% | High risk75 | —-0.035 |
| 21II0072CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS (ARTECHE-JIPAPAD-LAS NAVAS-RAWIS) AT BARANGAY GIBUANGAN AND BARANGAY SAGUDSURON, CATUBIG, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱32.3M | 100% | High risk74 | —-0.036 |
| 17II0014CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG SAN ROQUE-CABABTOAN OLD ROAD, STA. K0775+000 - K0776+000, SAN ROQUE, NORTHERN SAMAR II | Region VIII | Northern Samar 2nd DEO | Completed | ₱20.2M | 100% | High risk73 | —-0.035 |
| 23IJ0103CSSP: CONSTRUCTION OF MULTI-PURPOSE BUILDING, CALBAYOG DISTRICT HOSPITAL, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱59.1M | 100% | High risk61 | —-0.047 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25II0007ROAD WIDENING, SECONDARY ROADS, PANGPANG-PALAPAG-MAPANAS-GAMAY-LAPINIG RD., K0806+200-K0808+000; K0811+105-K0811+700, NORTHERN SAMAR 2ND DISTRICT | Region VIII | Northern Samar 2nd DEO | On-Going | ₱144.6M | 56% | High risk93 | Flagged0.023 |
| 25IK0013SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), CONSTRUCTION OF ROAD, BARANGAY HINICA-AN TO BARANGAY MALOBAGO, MOTIONG, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱29.4M | 66% | High risk96 | Flagged0.017 |
| 19II0110REPAIR/REHABILITATION OF NATIONAL ROAD, ALONG CATARMAN - LAOANG ROAD, BANTAYAN - SAN ROQUE SECTION, SITIO NAPERES, SAN ROQUE, N. SAMAR K0768+694 - K0768+808, SAN ROQUE, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱30M | 100% | High risk86 | Flagged0.014 |
| 25I00093NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0831+800 - K0832+920 | Region VIII | Region VIII | On-Going | ₱84.8M | 67% | High risk95 | Flagged0.010 |
| 24IK0077CONST. OF ROAD, BARANGAY GUIMBANGA TO BARANGAY ANTOL, CALBIGA, SAMAR, STA. 0+000.00-STA. 1+965.00 | Region VIII | Samar 2nd DEO | On-Going | ₱48.2M | 88% | High risk82 | Flagged0.005 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25IK0013SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), CONSTRUCTION OF ROAD, BARANGAY HINICA-AN TO BARANGAY MALOBAGO, MOTIONG, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱29.4M | 66% | High risk96 | Flagged0.017 |
| 2 | 25I00093NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0831+800 - K0832+920 | Region VIII | Region VIII | On-Going | ₱84.8M | 67% | High risk95 | Flagged0.010 |
| 3 | 25II0007ROAD WIDENING, SECONDARY ROADS, PANGPANG-PALAPAG-MAPANAS-GAMAY-LAPINIG RD., K0806+200-K0808+000; K0811+105-K0811+700, NORTHERN SAMAR 2ND DISTRICT | Region VIII | Northern Samar 2nd DEO | On-Going | ₱144.6M | 56% | High risk93 | Flagged0.023 |
| 4 | 25I00132ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0778+265 - K0778+360 | Region VIII | Region VIII | On-Going | ₱32.7M | 85% | High risk92 | —-0.004 |
| 5 | 25IJ0010OO2: CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY BARRUZ, PHASE II, MATUGUINAO, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱67.5M | 98% | High risk92 | —-0.013 |
| 6 | 25IK0036CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BICAL BRIDGE ALONG SAN JUANICO - BASEY - SOHOTON ROAD, ST. RITA, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱49M | 19% | High risk91 | —-0.001 |
| 7 | 19II0110REPAIR/REHABILITATION OF NATIONAL ROAD, ALONG CATARMAN - LAOANG ROAD, BANTAYAN - SAN ROQUE SECTION, SITIO NAPERES, SAN ROQUE, N. SAMAR K0768+694 - K0768+808, SAN ROQUE, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱30M | 100% | High risk86 | Flagged0.014 |
| 8 | 24IK0077CONST. OF ROAD, BARANGAY GUIMBANGA TO BARANGAY ANTOL, CALBIGA, SAMAR, STA. 0+000.00-STA. 1+965.00 | Region VIII | Samar 2nd DEO | On-Going | ₱48.2M | 88% | High risk82 | Flagged0.005 |
| 9 | 18II0014CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS, SECONDARY ROADS, PANGPANG-PALAPAG-MAPANAS-GAMAY-LAPINIG ROAD, K0826+100 - K0826+684, 2ND DISTRICT, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱18.3M | 100% | High risk75 | —-0.035 |
| 10 | 21II0072CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS (ARTECHE-JIPAPAD-LAS NAVAS-RAWIS) AT BARANGAY GIBUANGAN AND BARANGAY SAGUDSURON, CATUBIG, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱32.3M | 100% | High risk74 | —-0.036 |
| 11 | 17II0014CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG SAN ROQUE-CABABTOAN OLD ROAD, STA. K0775+000 - K0776+000, SAN ROQUE, NORTHERN SAMAR II | Region VIII | Northern Samar 2nd DEO | Completed | ₱20.2M | 100% | High risk73 | —-0.035 |
| 12 | 23IJ0103CSSP: CONSTRUCTION OF MULTI-PURPOSE BUILDING, CALBAYOG DISTRICT HOSPITAL, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱59.1M | 100% | High risk61 | —-0.047 |
| 13 | 22II0011ROAD WIDENING, SECONDARY ROAD, SN POLICARPO-ARTECHE-LAPINIG RD, K0857+000-K0860+000 | Region VIII | Northern Samar 2nd DEO | Completed | ₱96.5M | 100% | Medium risk60 | —-0.082 |
| 14 | 22II0059REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, SECONDARY ROADS, RAWIS - CATUBIG RD., K0789+762.60 - K0791+000, K0793+950 - K0794+396, 2ND DISTRICT, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱93.7M | 100% | Medium risk60 | —-0.081 |
| 15 | 21I00022NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS - ARTECHE, BRGY. CATUMSAN - JIPAPAD - LAS NAVAS - CATUBIG - RAWIS ROAD, NORTHERN SAMAR 2ND DISTRICT | Region VIII | Region VIII | Completed | ₱100M | 100% | Medium risk60 | —-0.067 |
| 16 | 22IK0030CONSTRUCTION OF CONCEPCION-TAPUL-NAWI-PAGSANGHAN-ANAGASE-ST. NIÑO-MAYLOBE-SARAO CANVAIS-CARANAS ROAD, 0+000-0+977, PARANAS-MOTIONG, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱86.8M | 61% | Medium risk57 | —-0.015 |
| 17 | 25I00130ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0783+089 - K0783+120 | Region VIII | Region VIII | On-Going | ₱11.2M | 38% | Medium risk57 | —-0.010 |
| 18 | 18II0060REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, SECONDARY ROADS, PANGPANG-PALAPAG-MAPANAS-GAMAY-LAPINIG ROAD, K0809+600-K0809+983, SECOND DISTRICT, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱91.7M | 100% | Medium risk57 | —-0.084 |
| 19 | 25II0027CONSTRUCTION OF ROAD, GANDARA - MATUGUINAO - LAS NAVAS ROAD (NORTHERN SAMAR SIDE) | Region VIII | Northern Samar 2nd DEO | On-Going | ₱78.1M | 1% | Medium risk56 | —-0.024 |
| 20 | 19II0009ROAD WIDENING, SECONDARY ROADS, SAN POLICARPO - ARTECHE - LAPINIG ROAD, K0865+929 - K0867+772, 2ND DISTRICT, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱64.4M | 100% | Medium risk55 | —-0.089 |
| 21 | 17II0023OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE LAOANG-CALOMOTAN ROAD, K0792+000 - K0794+315, LAOANG, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱39.4M | 100% | Medium risk55 | —-0.058 |
| 22 | 23IK0040PREVENTIVE MAINT. - SECONDARY ROADS (BASEY-MARABUT-PINAMITINAN RD), K0942+643-K0946+400, K0949+000-K0951+169, BASEY, SAMAR | Region VIII | Samar 2nd DEO | Completed | ₱68.2M | 100% | Medium risk55 | —-0.091 |
| 23 | 23II0044CONSTRUCTION OF ROAD, NAGOOCAN-OSANG-HINAGONOYAN-STA FE ROAD, CATUBIG, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱67.2M | 100% | Medium risk55 | —-0.089 |
| 24 | 24IJ0007(RE-ADVERTISED) OO1: REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - CALBAYOG - CATARMAN RD. K0803+042 - K0803+238, K0803+280 - K0803+314 | Region VIII | Samar 1st DEO | Completed | ₱60.2M | 100% | Medium risk55 | —-0.091 |
| 25 | 24IJ0027OO1: REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS, CALBAYOG - CATARMAN RD. K0794+470 - K0794+562, K0794+948 - K0795+000 | Region VIII | Samar 1st DEO | Completed | ₱57.3M | 100% | Medium risk55 | —-0.090 |