Contractor dossier
91 projects on file, including joint ventures this contractor is part of.
Total projects
91
Total budget
₱4B
Average progress
93.7%
Completion rate
76.9%
Average risk score
53.9
Medium risk on average, out of 100
Flagged as unusual
5
5.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 91 | ₱4B | 53.9 | 5 | 93.7% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 51 | ₱2.2B | 50.2 | 0 | 93.3% |
| Flood Control and Drainage | 21 | ₱1B | 47.6 | 0 | 99.3% |
| OTHER | 5 | ₱149M | 78.1 | 2 | 97.7% |
| Buildings and Facilities | 5 | ₱107.8M | 50.6 | 0 | 100.0% |
| GAA 2025 OO-1 | 3 | ₱262.2M | 93.7 | 2 | 69.4% |
| Water Provision and Storage | 3 | ₱41.1M | 48.4 | 0 | 100.0% |
| GAA 2025 OO-2 | 2 | ₱116.5M | 91.7 | 0 | 58.9% |
| GAA 2025 SSP | 1 | ₱29.4M | 95.6 | 1 | 66.3% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25IK0013SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), CONSTRUCTION OF ROAD, BARANGAY HINICA-AN TO BARANGAY MALOBAGO, MOTIONG, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱29.4M | 66% | High risk96 | Flagged0.017 |
| 25I00093NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0831+800 - K0832+920 | Region VIII | Region VIII | On-Going | ₱84.8M | 67% | High risk95 | Flagged0.010 |
| 25II0007ROAD WIDENING, SECONDARY ROADS, PANGPANG-PALAPAG-MAPANAS-GAMAY-LAPINIG RD., K0806+200-K0808+000; K0811+105-K0811+700, NORTHERN SAMAR 2ND DISTRICT | Region VIII | Northern Samar 2nd DEO | On-Going | ₱144.6M | 56% | High risk93 | Flagged0.023 |
| 25I00132ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0778+265 - K0778+360 | Region VIII | Region VIII | On-Going | ₱32.7M | 85% | High risk92 | —-0.004 |
| 25IJ0010OO2: CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY BARRUZ, PHASE II, MATUGUINAO, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱67.5M | 98% | High risk92 | —-0.013 |
| 25IK0036CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BICAL BRIDGE ALONG SAN JUANICO - BASEY - SOHOTON ROAD, ST. RITA, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱49M | 19% | High risk91 | —-0.001 |
| 19II0110REPAIR/REHABILITATION OF NATIONAL ROAD, ALONG CATARMAN - LAOANG ROAD, BANTAYAN - SAN ROQUE SECTION, SITIO NAPERES, SAN ROQUE, N. SAMAR K0768+694 - K0768+808, SAN ROQUE, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱30M | 100% | High risk86 | Flagged0.014 |
| 24IK0077CONST. OF ROAD, BARANGAY GUIMBANGA TO BARANGAY ANTOL, CALBIGA, SAMAR, STA. 0+000.00-STA. 1+965.00 | Region VIII | Samar 2nd DEO | On-Going | ₱48.2M | 88% | High risk82 | Flagged0.005 |
| 18II0014CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS, SECONDARY ROADS, PANGPANG-PALAPAG-MAPANAS-GAMAY-LAPINIG ROAD, K0826+100 - K0826+684, 2ND DISTRICT, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱18.3M | 100% | High risk75 | —-0.035 |
| 21II0072CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS (ARTECHE-JIPAPAD-LAS NAVAS-RAWIS) AT BARANGAY GIBUANGAN AND BARANGAY SAGUDSURON, CATUBIG, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱32.3M | 100% | High risk74 | —-0.036 |
| 17II0014CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG SAN ROQUE-CABABTOAN OLD ROAD, STA. K0775+000 - K0776+000, SAN ROQUE, NORTHERN SAMAR II | Region VIII | Northern Samar 2nd DEO | Completed | ₱20.2M | 100% | High risk73 | —-0.035 |
| 23IJ0103CSSP: CONSTRUCTION OF MULTI-PURPOSE BUILDING, CALBAYOG DISTRICT HOSPITAL, CALBAYOG CITY, SAMAR | Region VIII | Samar 1st DEO | On-Going | ₱59.1M | 100% | High risk61 | —-0.047 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25II0007ROAD WIDENING, SECONDARY ROADS, PANGPANG-PALAPAG-MAPANAS-GAMAY-LAPINIG RD., K0806+200-K0808+000; K0811+105-K0811+700, NORTHERN SAMAR 2ND DISTRICT | Region VIII | Northern Samar 2nd DEO | On-Going | ₱144.6M | 56% | High risk93 | Flagged0.023 |
| 25IK0013SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), CONSTRUCTION OF ROAD, BARANGAY HINICA-AN TO BARANGAY MALOBAGO, MOTIONG, SAMAR | Region VIII | Samar 2nd DEO | On-Going | ₱29.4M | 66% | High risk96 | Flagged0.017 |
| 19II0110REPAIR/REHABILITATION OF NATIONAL ROAD, ALONG CATARMAN - LAOANG ROAD, BANTAYAN - SAN ROQUE SECTION, SITIO NAPERES, SAN ROQUE, N. SAMAR K0768+694 - K0768+808, SAN ROQUE, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱30M | 100% | High risk86 | Flagged0.014 |
| 25I00093NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0831+800 - K0832+920 | Region VIII | Region VIII | On-Going | ₱84.8M | 67% | High risk95 | Flagged0.010 |
| 24IK0077CONST. OF ROAD, BARANGAY GUIMBANGA TO BARANGAY ANTOL, CALBIGA, SAMAR, STA. 0+000.00-STA. 1+965.00 | Region VIII | Samar 2nd DEO | On-Going | ₱48.2M | 88% | High risk82 | Flagged0.005 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 20II0026CONSTRUCTION OF CATUBIG FLOOD CONTROL STRUCTURE AND DRAINAGE SYSTEM, CATUBIG, RIVER BASIN, CATUBIG, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱37.2M | 100% | Medium risk46 | —-0.078 |
| 77 | 24II0071CONSTRUCTION OF ROAD IN BRGY. INAMLAN, LAOANG, N. SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱19.8M | 100% | Medium risk46 | —-0.092 |
| 78 | 22II0024CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY TINOBLAN, LAOANG, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱33.8M | 100% | Medium risk46 | —-0.078 |
| 79 | 21II0044ROAD CONCRETING, BARANGAY CABABTO-AN, PAMBUJAN, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱7M | 100% | Medium risk46 | —-0.092 |
| 80 | 20II0029CONSTRUCTION OF PALAPAG RIVER CONTROL, PALAPAG RIVER BASIN, PALAPAG, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱46.6M | 100% | Medium risk46 | —-0.079 |
| 81 | 18II0056CONSTRUCTION OF GAMAY RIVER CONTROL, GAMAY, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱45.6M | 100% | Medium risk46 | —-0.080 |
| 82 | 19IH0139CONSTRUCTION OF MULTI-PURPOSED BUILDING(COVERED COURT), BASILIO B. CHAN MEMORIAL AGRICULTURAL INDUSTRIAL SCHOOL, LAVEZARES, NORTHERN SAMAR | Region VIII | Northern Samar 1st DEO | Completed | ₱4.8M | 100% | Medium risk46 | —-0.097 |
| 83 | 18II0028CONSTRUCTION OF PAMBUJAN RIVER CONTROL, PAMBUJAN RIVER BASIN, PAMBUJAN, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱36.3M | 100% | Medium risk46 | —-0.080 |
| 84 | 23II0062CONCRETING OF BRGY. CATIGBIAN TO BRGY. PALMERA FMR, BRGY. CATIGBIAN AND BRGY. PALMERA, LAOANG, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱9.9M | 100% | Medium risk44 | —-0.042 |
| 85 | 18II0083CONCRETING OF BRGY. CABARIAN - BRGY. CANJUMADAL FMR, BRGY. CABARIAN - BRGY. CANJUMADAL, PAMBUJAN, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱5.8M | 100% | Medium risk44 | —-0.039 |
| 86 | 23II0059CONCRETING OF NBRGY. BANGON-BRGY. BONIFACIO TO BRGY. LONOY FMR, BRGY. BANGON-BRGY. BONIFACIO AND LONOY, GAMAY, N. SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱12.9M | 100% | Medium risk43 | —-0.040 |
| 87 | 23II0060CONCRETING OF BRGY. CADE-AN TO BRGY. GUIBUANGAN FMR, BRGY. CADE-AN AND BRGY. GUIBUANGAN, GAMAY, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱12.9M | 100% | Medium risk43 | —-0.040 |
| 88 | 25I00089NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0768+862 - K0768+998 | Region VIII | Region VIII | On-Going | ₱4.3M | 1% | Medium risk40 | —-0.002 |
| 89 | 25I00067SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROAD ALONG MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0714+906 - K0714+963 | Region VIII | Region VIII | On-Going | ₱2.1M | 100% | Medium risk39 | —-0.030 |
| 90 | 18II0005CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROAD, TERTIARY ROAD, ARTECHE - JIPAPAD - LAS NAVAS - RAWIS ROAD, K0811+096, LAS NAVAS, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱4.6M | 100% | Low risk24 | —-0.094 |
| 91 | 18II0012CONSTRUCTION OF RIVER CONTROL, BRGY. JOLEJOLE DISTRICT POBLACION, LAS NAVAS, NORTHERN SAMAR | Region VIII | Northern Samar 2nd DEO | Completed | ₱4.6M | 100% | Low risk23 | —-0.077 |