Opening the dossier…
Opening the dossier…
Contractor dossier
40 projects on file, including joint ventures this contractor is part of.
Total projects
40
Total budget
₱243.6M
Average progress
98.8%
Completion rate
80.0%
Average risk score
41.3
Medium risk on average, out of 100
Flagged as unusual
1
2.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 40 | ₱243.6M | 41.3 | 1 | 98.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 21 | ₱99.3M | 38.0 | 0 | 100.0% |
| Roads | 17 | ₱133.6M | 43.4 | 0 | 97.7% |
| GAA 2025 SSP | 1 | ₱9.7M | 95.3 | 1 | 91.8% |
| Water Provision and Storage | 1 | ₱989.8K | 22.4 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25ID0023CONSTRUCTION OF CONCRETE ROAD,BARANGAY TUYO, MAC ARTHUR,LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱9.7M | 92% | High risk95 | Flagged0.009 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25ID0023CONSTRUCTION OF CONCRETE ROAD,BARANGAY TUYO, MAC ARTHUR,LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱9.7M | 92% | High risk95 | Flagged0.009 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25ID0023CONSTRUCTION OF CONCRETE ROAD,BARANGAY TUYO, MAC ARTHUR,LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱9.7M | 92% | High risk95 | Flagged0.009 |
| 2 | 22IG0051CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BARANGAY BUNGA, ABUYOG, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱9.7M | 100% | Medium risk50 | —-0.095 |
| 3 | 22IG0045CONSTRUCTION OF MULTI-PURPOSE BUILDING, ABUYOG, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱5.8M | 100% | Medium risk50 | —-0.095 |
| 4 | 24IG0101CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CAN-APORONG, ABUYOG, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱6.4M | 100% | Medium risk50 | —-0.096 |
| 5 | 22IG0040CONSTRUCTION OF MULTI-PURPOSE BUILDING, JAVIER, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱4.9M | 100% | Medium risk50 | —-0.096 |
| 6 | 25ID0016CONSTRUCTION OF ROAD,BARANGAY CANLAMPAY,CARIGARA,LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱27.2M | 88% | Medium risk49 | —-0.057 |
| 7 | 25ID0005CONSTRUCTION OF CONCRETE ROAD,BARANGAY TOLOSAHAY-BARANGAY ALEGRIA,JULITA,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱9.7M | 100% | Medium risk48 | —-0.092 |
| 8 | 23IG0127CONSTRUCTION OF MULTI-PURPOSE BUILDING, HINDANG, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.098 |
| 9 | 25ID0002ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-TERTIARY ROADS-BURAUEN-MAHAGNAO RD.-K0986+000-K0988+225.00,BURAUEN,LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱19.4M | 89% | Medium risk48 | —-0.056 |
| 10 | 24ID0037CONSTRUCTION OF ROAD, BARANGAY SAN ANTONIO-BOLONGTOHAN,DULAG,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱5.9M | 100% | Medium risk48 | —-0.090 |
| 11 | 23IG0143CONSTRUCTION OF 2STY4CL CANMARATING SENIOR HIGH SCHOOL, ABUYOG, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱9.9M | 100% | Medium risk48 | —-0.054 |
| 12 | 22IG0015CONSTRUCTION OF ROAD, BARANGAY BALOCAWEHAY, ABUYOG, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.089 |
| 13 | 22IG0008CONSTRUCTION OF ROAD, BARANGAY MAG-ATUBANG, ABUYOG, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.089 |
| 14 | 24IG0048CONSTRUCTION OF ROAD, BARANGAY TABIGUE, ABUYOG, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱4.9M | 100% | Medium risk48 | —-0.092 |
| 15 | 25ID0024CONSTRUCTION OF CONCRETE ROAD,BARANGAY GIMIRANAT WEST-BRGY. GIMIRANAT EAST ROAD, LA PAZ,LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱14.6M | 93% | Medium risk48 | —-0.058 |
| 16 | 23IG0017CONSTRUCTION OF ROAD, BARANGAY CANMARATING, ABUYOG, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.091 |
| 17 | 23ID0108CONSTRUCTION OF 1-UNIT 1 STY4CL SCHOOL BUILDING PALALE NATIONAL HIGHSCHOOL, MAC ARTHUR,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱10.4M | 100% | Medium risk47 | —-0.054 |
| 18 | 25ID0015REHABILITATION OF ROAD,BARANGAY COGON-GIMIRANAT WEST ROAD,LA PAZ,LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱9.7M | 90% | Medium risk47 | —-0.056 |
| 19 | 22ID0070CONSTRUCTION OF 1STY2CL, MAC ARTHUR CENTRAL SCHOOL,MAC ARTHUR,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱4.9M | 100% | Medium risk47 | —-0.053 |
| 20 | 25IG0064CONSTRUCTION OF ROAD, BARANGAY SANTA CRUZ, CITY OF BAYBAY, LEYTE | Region VIII | Leyte 5th DEO | On-Going | ₱4.9M | 100% | Medium risk47 | —-0.063 |
| 21 | 23IG0121CONSTRUCTION OF 1-UNIT 2CL SCHOOL BUILDING, STA. CRUZ ELEMENTARY SCHOOL, JAVIER, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.054 |
| 22 | 23IG0123CONSTRUCTION OF 1-UNIT 2CL SCHOOL BUILDING, MAHAPLAG CENTRAL SCHOOL, MAHAPLAG, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱4.9M | 100% | Medium risk45 | —-0.054 |
| 23 | 24IG0047CONSTRUCTION OF ROAD, BARANGAY BAYABAS, ABUYOG, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱4.8M | 100% | Medium risk45 | —-0.092 |
| 24 | 24IG0008CONSTRUCTION OF ROAD, BARANGAY ALTAVISTA, CITY OF BAYBAY, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱4.8M | 100% | Medium risk44 | —-0.092 |
| 25 | 24IG0003CONSTRUCTION OF ROAD, BARANGAY ZACARITO, CITY OF BAYBAY, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱4.8M | 100% | Medium risk44 | —-0.092 |