Contractor dossier
115 projects on file, including joint ventures this contractor is part of.
Total projects
115
Total budget
₱4.9B
Average progress
86.9%
Completion rate
67.0%
Below 70%
Average risk score
52.9
Medium risk on average, out of 100
Flagged as unusual
15
13.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| National Capital Region | 61 | ₱1.5B | 47.4 | 0 | 92.5% |
| Region III | 18 | ₱1.3B | 58.3 | 5 | 80.8% |
| Region IV-A | 17 | ₱610.4M | 48.7 | 0 | 88.2% |
| Region V | 9 | ₱549.6M | 62.2 | 1 | 82.7% |
| Region VII | 6 | ₱568.2M | 81.7 | 5 | 48.9% |
| Region VI | 4 | ₱384.1M | 65.6 | 4 | 91.7% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 39 | ₱1.3B | 49.9 | 0 | 76.3% |
| Flood Control and Drainage | 34 | ₱2B | 54.4 | 7 | 86.1% |
| Buildings and Facilities | 31 | ₱528M | 47.2 | 0 | 100.0% |
| OTHER | 9 | ₱816.1M | 70.6 | 6 | 91.2% |
| GAA 2025 SSP | 2 | ₱198M | 95.2 | 2 | 87.9% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CJ0224IMPROVEMENT OF STA. CATALINA - BALETE DIVERSION ROAD (SEGMENT B), TARLAC CITY, TARLAC | Region III | Tarlac DEO | On-Going | ₱99M | 90% | High risk95 | Flagged0.009 |
| 25CJ0223IMPROVEMENT OF STA. CATALINA - BALETE DIVERSION ROAD (SEGMENT A), TARLAC CITY, TARLAC | Region III | Tarlac DEO | On-Going | ₱99M | 86% | High risk95 | Flagged0.010 |
| 24FN0092OO2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONST./REHAB. OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONST. OF FLOOD CONTROL STRUCT., BICOL RIVER REV'T WALL, BRGY. SAN RAMON SEC., BULA, CAMSUR | Region V | Camarines Sur 5th DEO | On-Going | ₱144.8M | 63% | High risk92 | Flagged0.064 |
| 23HO0286CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD DIKE AT SITIO GALUCAN, BRG | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 99% | High risk91 | Flagged0.059 |
| 23HO0254CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT SITIO POBLACION - SITIO NONOK, BRGY. MONTAÑE | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.084 |
| 23HO0269CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT SITIO POBLACION - SITIO MAINIT, BRGY. MONTAÑ | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.084 |
| 23HO0253- CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES,CONSTRUCTION OF REVETMENT WALL AT SITIO TUNGA, BRGY. MONTAÑEZA, MALABUYOC, C | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.084 |
| 24CC0021CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY SANTA MONICA, HAGONOY, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱77.2M | 86% | High risk76 | —-0.019 |
| 23HO0268CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) FLOOD MITIGATION STRUCTURES PROTECTING MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES, CONSTRUCTION OF REVETMENT WALL, SITIO GALUCAN, PACKAGE 2, BARANGA | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 94% | High risk75 | Flagged0.033 |
| 24CC0628REHABILITATION OF WATERWAYS ALONG BALAGTAS RIVER BRGY. PULONG GUBAT, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱48.2M | 0% | High risk75 | Flagged0.047 |
| 25DF0067CONVERGENCE & SPECIAL SUPPORT PROGSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)ACCESS RDS &/OR BRIDGES FROM THE NATIONAL RD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIESCONST OF SAN FRANCISCO BYPASS RD PHASE 1, GEN TRIAS | Region IV-A | Cavite 1st DEO | On-Going | ₱95.5M | 0% | High risk73 | —-0.013 |
| 23GB0057CONSTRUCTION OF SEAWALL AT BRGY. SANTA FE PANDAN, ANTIQUE | Region VI | Antique DEO | On-Going | ₱96M | 92% | High risk67 | Flagged0.004 |
| 24DF0020ORG. OUTCOME 1:ENSURE SAFE & RELIABLE NATIONAL RD SYSTEM ASSET PRESERVATION PROGCONST/UPGRADING/REHAB OF DRAINAGE ALONG NATIONAL RDS-PRIMARY RDS JUANITO R.REMULLA, SR.RD K0038+312-K0038+540, K0039+100 -K0039+740,K0039+770-K0040+330,K0040+400-K0040+450, | Region IV-A | Cavite 1st DEO | On-Going | ₱27.2M | 0% | High risk67 | —-0.006 |
| 23GB0058CONSTRUCTION OF SEAWALL AT BRGY. POBLACION - BRGY. MALABOR TIBIAO, ANTIQUE | Region VI | Antique DEO | On-Going | ₱96M | 89% | High risk66 | Flagged0.003 |
| 25FD0015CONSTRUCTION OF SHORE PROTECTION STRUCTURE, BARANGAY LOHONG, RAGAY, CAMARINES SUR | Region V | Camarines Sur 1st DEO | On-Going | ₱94.4M | 87% | High risk66 | —-0.046 |
| 24OA0094REPAIR/REHABILITATION OF RIVERWALL ALONG MALABON-TULLAHAN RIVER, MALABON CITY (PHASE 2) | National Capital Region | Malabon-Navotas DEO | On-Going | ₱86.9M | 96% | High risk66 | —-0.009 |
| 21DH0053CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, CONSTRUCTION OF RIVER CONTROL ALONG PAGSANJAN RIVER, LUMBAN SECTION, LUMBAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱93.6M | 100% | High risk65 | —-0.071 |
| 23GB0052CONSTRUCTION OF SEAWALL AT BRGY. POBLACION 1- BRGY. LAPAZ HAMTIC, ANTIQUE | Region VI | Antique DEO | On-Going | ₱96M | 89% | High risk65 | Flagged0.005 |
| 23HO0236REPAIR/REHABILITATION/RECONSTRUCTION OF MONTAÑEZA RIVER FLOOD CONTROL SYSTEM (UPSTREAM-SECTION 2), MALABUYOC, CEBU | Region VII | Cebu 7th DEO | Completed | ₱95.4M | 100% | High risk65 | —-0.065 |
| 24FD0041CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG BIGAAN RIVER, MALUBAGO SECTION, SIPOCOT, CAMARINES SUR | Region V | Camarines Sur 1st DEO | Completed | ₱99M | 100% | High risk65 | —-0.075 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23HO0254CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT SITIO POBLACION - SITIO NONOK, BRGY. MONTAÑE | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.084 |
| 23HO0269CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT SITIO POBLACION - SITIO MAINIT, BRGY. MONTAÑ | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.084 |
| 23HO0253- CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES,CONSTRUCTION OF REVETMENT WALL AT SITIO TUNGA, BRGY. MONTAÑEZA, MALABUYOC, C | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.084 |
| 24FN0092OO2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONST./REHAB. OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONST. OF FLOOD CONTROL STRUCT., BICOL RIVER REV'T WALL, BRGY. SAN RAMON SEC., BULA, CAMSUR | Region V | Camarines Sur 5th DEO | On-Going | ₱144.8M | 63% | High risk92 | Flagged0.064 |
| 23HO0286CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD DIKE AT SITIO GALUCAN, BRG | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 99% | High risk91 | Flagged0.059 |
| 24CC0628REHABILITATION OF WATERWAYS ALONG BALAGTAS RIVER BRGY. PULONG GUBAT, BALAGTAS, BULACAN | Region III | Bulacan 1st DEO | On-Going | ₱48.2M | 0% | High risk75 | Flagged0.047 |
| 23HO0268CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) FLOOD MITIGATION STRUCTURES PROTECTING MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES, CONSTRUCTION OF REVETMENT WALL, SITIO GALUCAN, PACKAGE 2, BARANGA | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 94% | High risk75 | Flagged0.033 |
| 25CJ0223IMPROVEMENT OF STA. CATALINA - BALETE DIVERSION ROAD (SEGMENT A), TARLAC CITY, TARLAC | Region III | Tarlac DEO | On-Going | ₱99M | 86% | High risk95 | Flagged0.010 |
| 25CJ0224IMPROVEMENT OF STA. CATALINA - BALETE DIVERSION ROAD (SEGMENT B), TARLAC CITY, TARLAC | Region III | Tarlac DEO | On-Going | ₱99M | 90% | High risk95 | Flagged0.009 |
| 23GB0052CONSTRUCTION OF SEAWALL AT BRGY. POBLACION 1- BRGY. LAPAZ HAMTIC, ANTIQUE | Region VI | Antique DEO | On-Going | ₱96M | 89% | High risk65 | Flagged0.005 |
| 23GB0057CONSTRUCTION OF SEAWALL AT BRGY. SANTA FE PANDAN, ANTIQUE | Region VI | Antique DEO | On-Going | ₱96M | 92% | High risk67 | Flagged0.004 |
| 24CD0311REHABILITATION OF DISASTER RELATED INFRASTRUCTURE AND OTHER FACILITIESREPAIR AND REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG MEYCAUAYAN RIVER, STA. 05+590 STA. 05+620 (LONGOS ZAMORA SECTION), MEYCAUAYAN, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱18.9M | 87% | Medium risk53 | Flagged0.004 |
| 23GB0058CONSTRUCTION OF SEAWALL AT BRGY. POBLACION - BRGY. MALABOR TIBIAO, ANTIQUE | Region VI | Antique DEO | On-Going | ₱96M | 89% | High risk66 | Flagged0.003 |
| 23GB0056CONSTRUCTION OF SEAWALL AT BRGY. BAYBAY, PANDAN, ANTIQUE | Region VI | Antique DEO | On-Going | ₱96M | 96% | High risk64 | Flagged0.001 |
| 24CD0312REHABILITATION OF DISASTER RELATED INFRASTRUCTURE AND OTHER FACILITIESREPAIR AND REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG MEYCAUAYAN RIVER, STA. 06+445 STA. 06+475 (LONGOS ZAMORA SECTION), MEYCAUAYAN, BULACAN | Region III | Bulacan 2nd DEO | On-Going | ₱18.9M | 97% | Medium risk53 | Flagged0.001 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 101 | 18OA0059REHABILITATION OF LOCAL ROAD, PUREZA ST., BRGY. TUGATOG, MALABON CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱9.9M | 100% | Medium risk46 | —-0.100 |
| 102 | 22OA0114CONSTRUCTION OF FOUR (4) STOREY, TWELVE (12) CLASSROOM SCHOOL BUILDING, TANGOS 1 ELEMENTARY SCHOOL, NAVOTAS CIT | National Capital Region | Malabon-Navotas DEO | Completed | ₱30.4M | 100% | Medium risk45 | —-0.047 |
| 103 | 22OD0078CONSTRUCTION OF ROAD INCLUDING DRAINAGE ALONG BRGY. 8 PHASE 1, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱9.6M | 100% | Medium risk45 | —-0.100 |
| 104 | 22OD0079CONSTRUCTION OF ROAD INCLUDING DRAINAGE BRGY. 12 PHASE 1, CALOOCAN CITY | National Capital Region | Metro Manila 3rd DEO | Completed | ₱9.6M | 100% | Medium risk45 | —-0.100 |
| 105 | 18OA0047REHABILITATION OF ROADS, LANGARAY ST., BRGY. LONGOS, MALABON CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱6.9M | 100% | Medium risk45 | —-0.100 |
| 106 | 18OA0020REHABILITATION OF ROAD, PAEZVILLE ST., DAMPALIT, MALABON CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱8.4M | 100% | Medium risk45 | —-0.099 |
| 107 | 23OA0093CONSTRUCTION OF FOUR (4) STOREY, TWELVE (12) CLASSROOM SCHOOL BUILDING, TANGOS I ELEMENTARY SCHOOL, NAVOTAS CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱13M | 100% | Medium risk43 | —-0.053 |
| 108 | 24CC0019CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE AT BARANGAY SAN MIGUEL, HAGONOY, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱77.2M | 100% | Medium risk35 | —-0.086 |
| 109 | 23CC0057CONSTRUCTION OF CONCRETE SLOPE PROTECTION AT BARANGAY SULIVAN, K003+350 - K003+550, BALIUAG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱38.6M | 100% | Low risk29 | —-0.094 |
| 110 | 23CC0058CONSTRUCTION OF CONCRETE SLOPE PROTECTION AT BARANGAY HINUKAY, K004+100 - K004+300, BALIUAG, BULACAN | Region III | Bulacan 1st DEO | Completed | ₱38.6M | 100% | Low risk29 | —-0.093 |
| 111 | 18DH0077CONSTRUCTION OF DRAINAGE SYSTEM, SITIO 4, LAMBAC, PAGSANJAN, LAGUNA | Region IV-A | Laguna 1st DEO | Completed | ₱2.9M | 100% | Low risk25 | —-0.086 |
| 112 | 19OA0094IMPROVEMENT OF PANGHULO ELEMENTARY SCHOOL, MALABON CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱2.9M | 100% | Low risk25 | —-0.102 |
| 113 | 19OA0093IMPROVEMENT OF PANGHULO ELEMENTARY SCHOOL-1, MALABON CITY | National Capital Region | Malabon-Navotas DEO | Completed | ₱2M | 100% | Low risk23 | —-0.093 |
| 114 | 21OE0066REHABILITATION OF FLOOD CONTROL STRUCTURES AND FACILITIES ALONG WASHINGTON PIY MARGAL DRAINAGE MAIN, STA. 0+000.00 TO STA. 0+209.44, MANILA CITY | National Capital Region | North Manila DEO | Completed | ₱1.3M | 100% | Low risk20 | —-0.088 |
| 115 | 24DH0091REPAIR/REHABILITATION/IMPROVEMENT OF RIVER CONTROL ALONG SANTA CRUZ RIVER, BRGY. STO. ANGEL SUR, SANTA CRUZ, LAGUNA | Region IV-A | Laguna 1st DEO | On-Going | ₱1.9M | 100% | Low risk19 | —-0.052 |