Opening the dossier…
Opening the dossier…
Contractor dossier
4 projects on file, including joint ventures this contractor is part of.
Total projects
4
Total budget
₱44.7M
Average progress
100.0%
Completion rate
100.0%
Average risk score
28.9
Low risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Cordillera Administrative Region | 4 | ₱44.7M | 28.9 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 3 | ₱40.8M | 30.6 | 0 | 100.0% |
| Water Provision and Storage | 1 | ₱3.9M | 24.0 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Nothing to report.
No high-risk projects here.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 23PF0032REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE: BAGUIO- BONTOC ROAD - K0317+820 - K0317+837, K0318+012- K0318+049, K0318+052 - K0318+070, K0318+320 - K0318+396, K0320+345 - K0320+410, BUGUIAS, BENGUET | Cordillera Administrative Region | Benguet 2nd DEO | Completed | ₱34.3M | 100% | Medium risk45 | —-0.086 |
| 2 | 21PF0034REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS TERTIARY ROAD: GOV. BADO DANGWA NATIONAL ROAD, K0338+500 K0338+600 | Cordillera Administrative Region | Benguet 2nd DEO | Completed | ₱4.5M | 100% | Low risk26 | —-0.080 |
| 3 | 22PF0108CONSTRUCTION (COMPLETION) OF POBLACION WATER SUPPLY AT BARANGAY POBLACION, BAKUN, BENGUET | Cordillera Administrative Region | Benguet 2nd DEO | Completed | ₱3.9M | 100% | Low risk24 | —-0.046 |
| 4 | 19PE0038LOCAL INFRASTRUCTURE PROGRAM, LOCAL ROADS: CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF LOWER BATO ROAD, LONGLONG PUGUIS, LA TRINIDAD, BENGUET | Cordillera Administrative Region | Benguet 1st DEO | Completed | ₱2M | 100% | Low risk21 | —-0.077 |