Contractor dossier
206 projects on file, including joint ventures this contractor is part of.
Total projects
206
Total budget
₱1.5B
Average progress
99.9%
Completion rate
98.1%
Average risk score
14.1
Low risk on average, out of 100
Flagged as unusual
2
1.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XII | 206 | ₱1.5B | 14.1 | 2 | 99.9% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 148 | ₱372.3M | 7.7 | 0 | 100.0% |
| Roads | 29 | ₱723.6M | 27.1 | 0 | 100.0% |
| Bridges | 12 | ₱199.7M | 21.2 | 0 | 100.0% |
| Flood Control and Drainage | 8 | ₱57.9M | 24.6 | 0 | 100.0% |
| GAA 2025 OO-1 | 3 | ₱59.2M | 88.5 | 1 | 97.0% |
| OTHER | 2 | ₱48.7M | 72.3 | 1 | 93.9% |
| GAA 2025 SSP | 2 | ₱4.9M | 53.4 | 0 | 100.0% |
| Water Provision and Storage | 2 | ₱6.9M | 12.2 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25MH0006RECONSTRUCTION TO CONCRETE PAVEMENT - AWANG-UPI-LEBAK-KALAMANSIG-PALIMBANG-SARANGANI RD - K1913+960 - K1914+110 | Region XII | Sultan Kudarat 2nd DEO | On-Going | ₱18.5M | 91% | High risk91 | Flagged0.002 |
| 25MH0020WIDENING OF BRIDGE - PANGAWAN BR. 1 (B01263MN) ALONG AWANG-UPI-LEBAK-KALAMNSIG-PALIMBANG-SARANGANI RD | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱16.2M | 100% | High risk87 | —-0.032 |
| 25MH0018REHABILITATION/MAJOR REPAIR OF BRIDGE - UPPER LIMULAN BR. (B01782MN) ALONG SNA-LEBAK-KALAMANSIG RD | Region XII | Sultan Kudarat 2nd DEO | On-Going | ₱24.5M | 100% | High risk87 | —-0.004 |
| 25MH0033CONSTRUCTION OF CONCRETE ROAD - ROAD IN LIMULAN TO PUSOT AREA LEADING TO MARKET AND PROCESSING CENTER IN SUPPORT OF COFFEE, COCONUT, AND CORN INDUSTRIES, BRGY. LIMULAN, KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | On-Going | ₱24.4M | 88% | High risk73 | Flagged0.003 |
| 25MH0035CONSTRUCTION OF CONCRETE ROAD - BRGY. BASAK-VILLAMONTE-CAPILAN CONNECTING TO NEW CALINOG IN SUPPORT OF BAMBOO COFFEE PLANTATION, LEBAK, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱24.4M | 100% | High risk71 | —-0.032 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25MH0033CONSTRUCTION OF CONCRETE ROAD - ROAD IN LIMULAN TO PUSOT AREA LEADING TO MARKET AND PROCESSING CENTER IN SUPPORT OF COFFEE, COCONUT, AND CORN INDUSTRIES, BRGY. LIMULAN, KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | On-Going | ₱24.4M | 88% | High risk73 | Flagged0.003 |
| 25MH0006RECONSTRUCTION TO CONCRETE PAVEMENT - AWANG-UPI-LEBAK-KALAMANSIG-PALIMBANG-SARANGANI RD - K1913+960 - K1914+110 | Region XII | Sultan Kudarat 2nd DEO | On-Going | ₱18.5M | 91% | High risk91 | Flagged0.002 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 176 | 19MH0056CONSTRUCTION OF MULTI-PURPOSE BUILDING (SENIOR CITIZEN BUILDING) BRGY. LIMULAN, KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱994.8K | 100% | Low risk4 | —-0.085 |
| 177 | 19MH0144CONSTRUCTION OF MULTI-PURPOSE BUILDING BRGY. NALILIDAN,KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱995.1K | 100% | Low risk4 | —-0.087 |
| 178 | 19MH0109CONSTRUCTION OF MULTI-PURPOSE BUILDING (BRGY. HALL) BRGY. SANTA CLARA, KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱995K | 100% | Low risk4 | —-0.087 |
| 179 | 19MH0104CONSTRUCTION OF MULTI-PURPOSE BUILDING (BRGY. HALL) BRGY. LIMULAN, KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱995K | 100% | Low risk4 | —-0.087 |
| 180 | 19MH0139CONSTRUCTION OF MULTI-PURPOSE BUILDING BRGY. DUMANGAS NUEVO, KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱995.1K | 100% | Low risk4 | —-0.087 |
| 181 | 19MH0145CONSTRUCTION OF MULTI-PURPOSE BUILDING BRGY. TACUPIS, SEN. NINOY AQUINO, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱995.1K | 100% | Low risk3 | —-0.083 |
| 182 | 19MH0021CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL) BRGY. KALIBUHAN, PALIMBANG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱994.8K | 100% | Low risk3 | —-0.085 |
| 183 | 19MH0129CONSTRUCTION OF MULTI-PURPOSE BUILDING (SENIOR CITIZEN) BRGY. LANGGAL, SEN. NINOY AQUINO, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱995.1K | 100% | Low risk3 | —-0.086 |
| 184 | 19MH0125CONSTRUCTION OF MULTI-PURPOSE BUILDING (SENIOR CITIZEN) BRGY. BUKLOD, SEN. NINOY AQUINO, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱995.1K | 100% | Low risk3 | —-0.086 |
| 185 | 21MH0052CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY CHUA, BAGUMBAYAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱1.5M | 100% | Low risk3 | —-0.085 |
| 186 | 21MH0038CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (GYMNASIUM), BARANGAY BAI SARIPINANG, BAGUMBAYAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱996.5K | 100% | Low risk3 | —-0.084 |
| 187 | 19MH0127CONSTRUCTION OF MULTI-PURPOSE BUILDING (SENIOR CITIZEN) BRGY. KANULAY, BAGUMBAYAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱995.1K | 100% | Low risk3 | —-0.084 |
| 188 | 18MH0064CONSTRUCTION (COMPLETION) OF GYMNASIUM LIMULAN, KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱678.7K | 100% | Low risk3 | —-0.084 |
| 189 | 17MH0271CONSTRUCTION OF ONE (1) STOREY - THREE (3) CLASSROOMS SCHOOL BUILDING AT SANGAY NATIONAL HIGH SCHOOL KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱4.1M | 100% | Low risk3 | —-0.019 |
| 190 | 17MH0198CONSTRUCTION OF UNIQUE WORKSHOP BUILDING (7X22.5) AT E. ARCANO MEM. NATIONAL HIGH SCHOOL LEBAK, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱3.2M | 100% | Low risk3 | —-0.018 |
| 191 | 17MH0295CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING WITH TOILET AT DATU ITO ANDONG MEMORIAL ELEMENTARY SCHOOL KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱2.9M | 100% | Low risk3 | —-0.019 |
| 192 | 17MH0154CONSTRUCTION OF ONE (1) STOREY - THREE (3) CLASSROOMS SCHOOL BUILDING AT AMPAD-GUIABAR MEMORIAL ELEMENTARY SCHOOL LEBAK, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱3.7M | 100% | Low risk3 | —-0.019 |
| 193 | 17MH0196CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING WITH TOILET AT CAPILAN ELEMENTARY SCHOOL - (B) LEBAK, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱2.8M | 100% | Low risk3 | —-0.020 |
| 194 | 17MH0156CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING AT PAKIL ELEMENTARY SCHOOL LEBAK, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱2.6M | 100% | Low risk3 | —-0.020 |
| 195 | 17MH0230CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING WITH TOILET AT GESTOSANI MEMORIAL ELEMENTARY SCHOOL LEBAK, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱2.8M | 100% | Low risk2 | —-0.020 |
| 196 | 17MH0194CONSTRUCTION OF UNIQUE WORKSHOP BUILDING (7X22.5) AT STA. CLARA NATIONAL HIGH SCHOOL KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱3.2M | 100% | Low risk2 | —-0.019 |
| 197 | 17MH0252CONSTRUCTION OF UNIQUE WORKSHOP (7X22.5) BUILDING AT STA. CLARA NATIONAL HIGH SCHOOL KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱3.1M | 100% | Low risk2 | —-0.019 |
| 198 | 17MH0193CONSTRUCTION OF UNIQUE WORKSHOP BUILDING (7X22.5) AT SANGAY NATIONAL HIGH SCHOOL KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱3.3M | 100% | Low risk2 | —-0.019 |
| 199 | 17MH0272CONSTRUCTION OF UNIQUE WORKSHOP (7X22.5) BUILDING AT SANGAY NATIONAL HIGH SCHOOL KALAMANSIG, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱3.3M | 100% | Low risk2 | —-0.020 |
| 200 | 17MH0299CONSTRUCTION OF ONE (1) STOREY - TWO (2) CLASSROOMS SCHOOL BUILDING WITH TOILET AT TIBONG-TIBONG ELEMENTARY SCHOOL LEBAK, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱2.9M | 100% | Low risk2 | —-0.020 |