29 projects on file, including joint ventures this contractor is part of.
Total projects
29
Total budget
₱400.3M
Average progress
99.1%
Completion rate
89.7%
Average risk score
44.3
Medium risk on average, out of 100
Flagged as unusual
0
0.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region V | 29 | ₱400.3M | 44.3 | 0 | 99.1% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 10 | ₱157M | 44.4 | 0 | 100.0% |
| Buildings and Facilities | 9 | ₱125.6M | 41.5 | 0 | 97.9% |
| Bridges | 5 | ₱82.2M | 47.2 | 0 | 100.0% |
| Flood Control and Drainage | 3 | ₱16M | 46.9 | 0 | 97.7% |
| Water Provision and Storage | 2 | ₱19.6M | 45.6 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Nothing to report.
No high-risk projects here.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
Nothing to report.
No flagged projects here.
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 18FH0175CONSTRUCTION OF FOUR(4) STOREY EIGHT (8) CLASSROOM-TWO(2) UNITS (7 X 18) SCIENCE LABORATORY, TWO(2) UNITS (7 X 18) ICT LABORATORY & FOUR(4) UNITS (7 X 18) REGULAR WORKSHOP SB, SAN MIGUEL RURAL DEVELOPMENT HS, SAN MIGUEL, CATANDUANES | Region V | Catanduanes DEO | Completed | ₱37.5M | 100% | Medium risk53 | —-0.033 |
| 2 | 19FH0135CLUSTER 5-CONSTRUCTION OF MULTI-PURPOSE BUILDING IN THE MUNICIPALITY OF VIRAC, CATANDUANES | Region V | Catanduanes DEO | Completed | ₱17.3M | 100% | Medium risk52 | —-0.093 |
| 3 | 19FH0130CLUSTER 4 - CONSTRUCTION/COMPLETION/REHABILITATION OF MULTI-PURPOSE BUILDING IN THE MUNICIPALITY OF VIRAC AND VARIOUS LOCATIONS IN CATANDUANES | Region V | Catanduanes DEO | Completed | ₱17.3M | 100% | Medium risk52 | —-0.093 |
| 4 | 23F00269LOCAL PROGRAM-NATIONAL BUILDING PROGRAM-BUILDINGS AND OTHER STRUCTURES-MULTIPURPOSE/FACILITIES-CONSTRUCTION OF EVACUATION CENTER, BARANGAY TUBAON, VIRAC, CATANDUANES, BARANGAY TUBAON, VIRAC, CATANDUANES (LONE DISTRICT) | Region V | Region V | On-Going | ₱9.6M | 81% | Medium risk52 | —-0.047 |
| 5 | 19FH0127CLUSTER 1-CONSTRUCTION OF MULTI-PURPOSE BUILDING IN THE MUNICIPALITY OF SAN ANDRES, CATANDUANES | Region V | Catanduanes DEO | Completed | ₱12.8M | 100% | Medium risk51 | —-0.094 |
| 6 | 17FH0001OFF-CARRIAGEWAY, IMPROVEMENT INCLUDING DRAINAGE BARAS-GIGMOTO-VIGA ROAD, K0025+698-K0026+000, BARAS, CATANDUANES | Region V | Catanduanes DEO | Completed | ₱34.3M | 100% | Medium risk51 | —-0.061 |
| 7 | 19FH0012CONSTRUCTION OF CONCRETE BRIDGE, BAGUMBAYAN BRIDGE ALONG JCT. BATO-BARAS ROAD, BAGUMBAYAN, BATO, CATANDUANES | Region V | Catanduanes DEO | Completed | ₱14.7M | 100% | Medium risk51 | —-0.062 |
| 8 | 25FH0054BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC,INFRASTRUCTURE/FACILITIES - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY MAYSURAM,CARAMORAN, CATANDUANES | Region V | Catanduanes DEO | On-Going | ₱4.8M | 100% | Medium risk50 | —-0.056 |
| 9 | 20FH0037WIDENING OF PERMANENT BRIDGES, LABANDERA BRIDGE (B0007CN) ALONG CATANDUANES CIRCUMFERENTIAL ROAD, BATO, CATANDUANES | Region V | Catanduanes DEO | Completed | ₱4.8M | 100% | Medium risk50 | —-0.062 |
| 10 | 18FH0173CONST. OF TWO(2) STOREY FOUR (4) CLASSROOM-TWO(2) UNITS (7 X 18) SCIENCE LABORATORY & TWO(2) UNITS (7 X 18) ICT LABORATORY SB, BUGAO NATIONAL HIGH SCHOOL, BAGAMANOC, CATANDUANES | Region V | Catanduanes DEO | Completed | ₱20.4M | 100% | Medium risk48 | —-0.033 |
| 11 | 17FH0070CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, REPLACEMENT OF PERMANENT WEAK BRIDGE, DORORIAN BRIDGE (B00058CN) ALONG BARAS-GIGMOTO-VIGA ROAD, GIGMOTO, CATANDUANES | Region V | Catanduanes DEO | Completed | ₱39.2M | 100% | Medium risk48 | —-0.028 |
| 12 | 21FH0016ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS-RECONSTRUCTION TO CONCRETE PAVEMENT-CATANDUANES CIRCUMFERENTIAL ROAD-K0199+000 - K0199+778 | Region V | Catanduanes DEO | Completed | ₱19.4M | 100% | Medium risk48 | —-0.099 |
| 13 | 25FH0056BASIC INFRASTRUCTURE PROGRAM (BIP) - FLODD MITIGATION STRUCTURE PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BUHI RIVER, BARANGAY BUHI, SAN MIGUEL, CATANDUANES | Region V | Catanduanes DEO | On-Going | ₱4.8M | 93% | Medium risk48 | —-0.053 |
| 14 | 20FH0017NETWORK DEVELOPMENT-ROAD WIDENING SECONDARY ROADS, CATANDUANES CIRCUM. ROAD K0005+902-K0006+077, K0006+083-K0006+500 | Region V | Catanduanes DEO | Completed | ₱31.5M | 100% | Medium risk47 | —-0.098 |
| 15 | 23FH0012BASIC INFRASTRUCTURE PROGRAM(BIP)-ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD AT MANAMBRAG, SAN ANDRES, CATANDUANES | Region V | Catanduanes DEO | Completed | ₱9.9M | 100% | Medium risk47 | —-0.099 |
| 16 | 23FH0028BASIC INFRASTRUCTURE PROGRAM ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDING/FACILITIES - CONSTRUCTION OF BARANGAY ROAD, CABUGAO, BATO, CATANDUANES | Region V | Catanduanes DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.098 |
| 17 | 23FH0055CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTORS - WATER SUPPLY SYSTEM, CONSTRUCTION OF SOLAR WATER SYSTEM, GIGMOTO, CATANDUANES. | Region V | Catanduanes DEO | Completed | ₱9.8M | 100% | Medium risk46 | —-0.063 |
| 18 | 23FH0024SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF GUINSAANAN-ABIHAO ROAD VIA SITIO ABACA, BARANGAY GUINSAANAN-ABIHAO | Region V | Catanduanes DEO | Completed | ₱29.4M | 100% | Medium risk46 | —-0.098 |
| 19 | 23FH0056CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTORS - WATER SUPPLY SYSTEM, CONSTRUCTION OF SOLAR WATER SYSTEM, BARAS, CATANDUANES. | Region V | Catanduanes DEO | Completed | ₱9.8M | 100% | Medium risk45 | —-0.063 |
| 20 | 24FH0008BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BIDDINGS/FACILITIES-CONSTRUCTION OF ROAD, BARANGAY MAGSAYSAY TO BARANGAY BUGAO, BAGAMANOC, CATANDUANES | Region V | Catanduanes DEO | Completed | ₱4.8M | 100% | Medium risk45 | —-0.095 |
| 21 | 19FH0086CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE, BARAS-GIGMOTO-VIGA ROAD K0027+100 - K0027+350 | Region V | Catanduanes DEO | Completed | ₱11M | 100% | Medium risk45 | —-0.099 |
| 22 | 16FH0098CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, REHAB./MAJOR REPAIR OF PERMANENT BRIDGES, SAN VICENTE BR.(B00059CN) ALONG BARAS-GIGMOTO-VIGA RD., SAN VICENTE, GIGMOTO, CATANDUANES | Region V | Catanduanes DEO | Completed | ₱13.7M | 100% | Medium risk44 | —-0.033 |
| 23 | 17FH0015CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGE KANPAWIKAN BRIDGE (B00049CN) ALONG JCT. CATANDUANES CIRCUMFERENTIAL RD-PANGANIBAN-SABLOYON RD., PANGANIBAN, CATANDUANES | Region V | Catanduanes DEO | Completed | ₱9.8M | 100% | Medium risk44 | —-0.033 |
| 24 | 21FH0145CONSTRUCTION OF SLOPE PROTECTION, MABATO NATIONAL HIGH SCHOOL (SMRDHS ANNEX), SAN MIGUEL, CATANDUANES | Region V | Catanduanes DEO | Completed | ₱6.4M | 100% | Medium risk43 | —-0.035 |
| 25 | 21FH0106CONCRETING OF SITIO DALAGANGAN TO SITIO HALE HALE, BRGY. AGBAN FMR, BRGY. AGBAN, BARAS, CATANDUANES | Region V | Catanduanes DEO | Completed | ₱9.8M | 100% | Medium risk42 | —-0.044 |