Opening the dossier…
Opening the dossier…
Contractor dossier
8 projects on file, including joint ventures this contractor is part of.
Total projects
8
Total budget
₱247.4M
Average progress
98.6%
Completion rate
62.5%
Below 70%
Average risk score
46.3
Medium risk on average, out of 100
Flagged as unusual
2
25.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region XI | 6 | ₱224.8M | 47.6 | 2 | 98.1% |
| Region X | 1 | ₱14.9M | 44.8 | 0 | 100.0% |
| Region XIII | 1 | ₱7.7M | 39.5 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 4 | ₱114.8M | 46.0 | 2 | 99.3% |
| Flood Control and Drainage | 2 | ₱115.1M | 49.2 | 0 | 95.5% |
| Water Provision and Storage | 1 | ₱9.8M | 48.3 | 0 | 100.0% |
| Bridges | 1 | ₱7.7M | 39.5 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
Nothing to report.
No high-risk projects here.
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24LD0217CONSTRUCTION OF ROAD FROM BARANGAY SINARAGAN, MATANAO TO BARANGAY KIBUAYA, HAGONOY, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱46.3M | 97% | Medium risk49 | Flagged0.007 |
| 24LD0216CONSTRUCTION OF ROAD FROM BARANGAY LAPU-LABAO TO BARANGAY MALABANG, HAGONOY, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱46.3M | 100% | Medium risk49 | Flagged0.005 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24LD0069CONSTRUCTION OF FLOOD CONTROL STRUCTURE (BRIDGE SECTION) AT BARANGAY NEW CLARIN-PULANG LUPA, BANSALAN, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱67.6M | 100% | Medium risk51 | —-0.072 |
| 2 | 24LD0217CONSTRUCTION OF ROAD FROM BARANGAY SINARAGAN, MATANAO TO BARANGAY KIBUAYA, HAGONOY, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱46.3M | 97% | Medium risk49 | Flagged0.007 |
| 3 | 24LD0216CONSTRUCTION OF ROAD FROM BARANGAY LAPU-LABAO TO BARANGAY MALABANG, HAGONOY, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱46.3M | 100% | Medium risk49 | Flagged0.005 |
| 4 | 23LD0074CONSTRUCTION OF SOLAR WATER SYSTEM, MUNICIPALITY OF PADADA, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱9.8M | 100% | Medium risk48 | —-0.055 |
| 5 | 25LD0046CONSTRUCTION OF REVETMENT, DIGOS RIVER, BARANGAY RUPARAN- BARANGAY APLAYA, DIGOS CITY, DAVAO DEL SUR | Region XI | Davao del Sur DEO | On-Going | ₱47.5M | 91% | Medium risk47 | —-0.038 |
| 6 | 24KL0080CONSTRUCTION OF ROAD, SITIO ALOG, JASAAN, MISAMIS ORIENTAL | Region X | Misamis Oriental 2nd DEO | Completed | ₱14.9M | 100% | Medium risk45 | —-0.096 |
| 7 | 22LD0098CONSTRUCTION OF FARM-TO-MILL ROAD, BRGY. MAHAYAHAY, HAGONOY, DAVAO DEL SUR | Region XI | Davao del Sur DEO | Completed | ₱7.4M | 100% | Medium risk41 | —-0.030 |
| 8 | 22NH0024RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES BUNAWAN BR. (B00692MN) ALONG SURIGAO-DAVAO COASTAL ROAD, TANDAG CITY, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱7.7M | 100% | Medium risk39 | —-0.041 |