8 projects on file, including joint ventures this contractor is part of.
Total projects
8
Total budget
₱81.3M
Average progress
87.5%
Completion rate
75.0%
Average risk score
55.1
Medium risk on average, out of 100
Flagged as unusual
1
12.5% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 8 | ₱81.3M | 55.1 | 1 | 87.5% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 5 | ₱27.1M | 49.3 | 0 | 100.0% |
| Roads | 2 | ₱46.3M | 49.5 | 0 | 50.0% |
| GAA 2025 SSP | 1 | ₱7.8M | 95.1 | 1 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25ID0010CONSTRUCTION OF CONCRETE ROAD, SITIO TAYUD, BARANGAY AMAHIT, BARUGO, LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱7.8M | 100% | High risk95 | Flagged0.004 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25ID0010CONSTRUCTION OF CONCRETE ROAD, SITIO TAYUD, BARANGAY AMAHIT, BARUGO, LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱7.8M | 100% | High risk95 | Flagged0.004 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25ID0010CONSTRUCTION OF CONCRETE ROAD, SITIO TAYUD, BARANGAY AMAHIT, BARUGO, LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱7.8M | 100% | High risk95 | Flagged0.004 |
| 2 | 24IC0183CONCRETING OF BRGY. PILIT TO BRGY. SAN MIGUELAY FMR PHASE II, BRGY. PILIT AND BRGY. SAN MIGUELAY, STA. FE, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱21.9M | 100% | Medium risk51 | —-0.040 |
| 3 | 22IC0042CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN RICARDO, BABATNGON, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱5.9M | 100% | Medium risk50 | —-0.097 |
| 4 | 24ID0110CONSTRUCTION OF MULTI-PURPOSE BUILDING,(BARANGAY HALL) BRGY. 1, JARO,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱4.9M | 100% | Medium risk50 | —-0.097 |
| 5 | 23IC0065CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 2, BRGY. LIBTONG, SAN MIGUEL, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱6.3M | 100% | Medium risk50 | —-0.097 |
| 6 | 24ID0111CONSTRUCTION OF MULTI-PURPOSE BUILDING,BRGY.CABACUNGAN, DULAG,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱4.9M | 100% | Medium risk50 | —-0.096 |
| 7 | 25IC0008ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - STA FE-PASTRANA-DAGAMI RD - K0925 + (-358) - K0925 + (-158), K0925 + 760 - K0925 + 860, K0926 + 200 - K0926 + 506, STA. FE, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱24.5M | 0% | Medium risk49 | —-0.029 |
| 8 | 23ID0080CONSTRUCTION OF 1STY2CL SCHOOL BUILDING VISARES NATIONAL HIGH SCHOOL,CAPOOCAN,LEYTE | Region VIII | Leyte 2nd DEO | Completed | ₱5M | 100% | Medium risk46 | —-0.055 |