Contractor dossier
261 projects on file, including joint ventures this contractor is part of.
Total projects
261
Total budget
₱3.6B
Average progress
96.2%
Completion rate
82.4%
Average risk score
41.0
Medium risk on average, out of 100
Flagged as unusual
5
1.9% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 258 | ₱3.5B | 40.9 | 5 | 96.1% |
| Negros Island Region | 2 | ₱87.2M | 47.5 | 0 | 100.0% |
| Region VII | 1 | ₱4.9M | 46.9 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 91 | ₱1.9B | 44.7 | 2 | 95.5% |
| Buildings and Facilities | 64 | ₱319.5M | 34.9 | 1 | 94.2% |
| Flood Control and Drainage | 45 | ₱824.3M | 43.8 | 0 | 95.6% |
| Water Provision and Storage | 45 | ₱62.1M | 29.1 | 0 | 100.0% |
| Bridges | 7 | ₱109.8M | 48.5 | 0 | 100.0% |
| OTHER | 4 | ₱214.5M | 79.9 | 1 | 98.7% |
| GAA 2025 OO-1 | 3 | ₱97.9M | 91.9 | 0 | 96.6% |
| GAA 2025 SSP | 1 | ₱19.8M | 95.6 | 1 | 100.0% |
| GAA 2025 OO-2 | 1 | ₱48.9M | 91.7 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25IE0049ROAD CONCRETING BARANGAY SAMBULAWAN, VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱19.8M | 100% | High risk96 | Flagged0.003 |
| 25IE0015NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, STO. ROSARIO-VILLABA DIVERSION ROAD, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱48.9M | 93% | High risk94 | —-0.007 |
| 25IE0009CONSTRUCTION OF SEAWALL, PHASE 2, BARANGAY BANGKAL, VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱48.9M | 100% | High risk92 | —-0.022 |
| 25IE0003REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE SECONDARY ROADS, CALUBIAN JCT-SN ISIDRO-TABANGO-VILLABA-PALOMPON RD., K1010+183 K1010+249, K1010+341 K1010+364 | Region VIII | Leyte 3rd DEO | On-Going | ₱24.4M | 100% | High risk91 | —-0.011 |
| 25IE0027ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDES-SECONDARY ROADS LEMON-LEYTE-BILIRAN RD K0987+477 K0987+532 | Region VIII | Leyte 3rd DEO | On-Going | ₱24.5M | 98% | High risk90 | —-0.010 |
| 23I00116ASSET PRESERVATION - CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - TERTIARY ROADS CABUNGA-AN - TABUNOK - CONSUEGRA RD K1030+000 - K1031+050, LEYTE 3RD LD | Region VIII | Region VIII | On-Going | ₱94.1M | 95% | High risk83 | Flagged0.018 |
| 25IE0023ACCESS ROAD LEADING TO SILAD PORT, VILLABA, LEYTE (NEW ROUTE) | Region VIII | Leyte 3rd DEO | On-Going | ₱67.5M | 100% | High risk81 | —-0.008 |
| 22IE0040CONSTRUCTION OF DAJA DAKU-TAGLAWIGAN RD.SAN ISIDRO, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱47.9M | 100% | High risk79 | —-0.040 |
| 24IE0105CONSTRUCTION OF MULTI-PURPOSE BUILDING, (LIBRARY BUILDING) SB BUILDING, BARANGAY VELOSO, CALUBIAN, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱4.9M | 100% | High risk77 | —-0.039 |
| 25IC0084CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MILAGROSA, STA. FE, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱6.7M | 25% | High risk66 | —-0.011 |
| 23IM0080CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PHASE 2, CAMANSIHAY, TACLOBAN CITY, LEYTE | Region VIII | Tacloban City DEO | Completed | ₱110.6M | 100% | High risk64 | —-0.065 |
| 24IC0067CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONSTRUCTION OF FLOOD CONTROL ALONG BINAHAAN RIVER, BRGY. SAN JOAQUIN, PALO, LEYTE | Region VIII | Leyte 1st DEO | Completed | ₱96.4M | 100% | High risk63 | —-0.068 |
| 22I00085ACCESS ROAD AND/OR BRIDGES FROM THE NATIONAL ROAD LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF LOCAL ACCESS ROAD, LEYTE, LEYTE 3RD LD | Region VIII | Region VIII | Completed | ₱95.9M | 100% | High risk60 | —-0.076 |
| 25IE0057ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - CABUNGA-AN TABUNOK - CONSUEGRA RD. K1030+600-K1031+000, LEYTE,LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱96.4M | 37% | High risk60 | —-0.037 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24IC0170CONCRETING OF BRGY. SAN ANTONIO FARM FMR, BRGY. SAN ANTONIO FARM, ALANGALANG, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱11.9M | 0% | Medium risk45 | Flagged0.025 |
| 25IC0192CONCRETING OF FMR AT BRGY. PINARIGUSAN TO LIPASAN FALLS, SAN MIGUEL, LEYTE | Region VIII | Leyte 1st DEO | On-Going | ₱14.9M | 0% | Medium risk52 | Flagged0.020 |
| 24IE0096CONSTRUCTION OF 1 UNIT 2-STOREY 8-CLASSROOM SCHOOL BUILDING, CALUBIAN SOUTH CENTRAL SCHOOL IN CALUBIAN LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱24.8M | 0% | Medium risk54 | Flagged0.019 |
| 23I00116ASSET PRESERVATION - CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - TERTIARY ROADS CABUNGA-AN - TABUNOK - CONSUEGRA RD K1030+000 - K1031+050, LEYTE 3RD LD | Region VIII | Region VIII | On-Going | ₱94.1M | 95% | High risk83 | Flagged0.018 |
| 25IE0049ROAD CONCRETING BARANGAY SAMBULAWAN, VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | On-Going | ₱19.8M | 100% | High risk96 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 201 | 22IE0083CLUSTER 1 CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), CAMPUROG ELEMENTARY SCHOOL, CAMPUROG, VILLABA, LEYTE, CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), SAMBULAWAN ELEMENTARY SCHOOL, SAMBULAWAN, VILLABA, LEYTE & CONSTRUCTION OF RAINWATER | Region VIII | Leyte 3rd DEO | Completed | ₱838K | 100% | Low risk23 | —-0.062 |
| 202 | 19IE0148CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS)RAFAELITO CABANAS MARTINEZ NATIONAL HIGH SCHOOL, CALUBIAN, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱197K | 100% | Low risk23 | —-0.060 |
| 203 | 19IE0147CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS)FELIX CANEJA LAFUENTE NATIONAL HIGH SCHOOL, CALUBIAN, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱197K | 100% | Low risk23 | —-0.060 |
| 204 | 19IE0146CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS)CARUYUCAN ELEMENTARY SCHOOL, CALUBIAN, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱197K | 100% | Low risk23 | —-0.060 |
| 205 | 19IE0145CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS) JUBAY ELEMENTARY SCHOOL, CALUBIAN LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱197K | 100% | Low risk23 | —-0.060 |
| 206 | 24IE0044CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY SAN FRANCISCO, VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱2M | 100% | Low risk23 | —-0.097 |
| 207 | 21IE0116CLUSTER 5 CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), JUAN V. DELANTAR NATIONAL HIGH SCHOOL, CONSUEGRA, LEYTE, LEYTE, CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), LIBAS ELEMENTARY SCHOOL, LIBAS, LEYTE, LEYTE, CONSTRUCTION OF RAINWATER COL | Region VIII | Leyte 3rd DEO | Completed | ₱787.6K | 100% | Low risk23 | —-0.063 |
| 208 | 23IE0076CLUSTER 1 CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), NEW BALANAC ELEMENTARY SCHOOL, BRGY. NEW BALANAC, VILLABA, LEYTE; CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), SULPA ELEMENTARY SCHOOL, BRGY. SULPA, VILLABA, LEYTE; CONSTRUCTION OF RAI | Region VIII | Leyte 3rd DEO | Completed | ₱1.1M | 100% | Low risk23 | —-0.062 |
| 209 | 21IE0113CLUSTER 2 CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), LEON ITO ELEMENTARY SCHOOL, POBLACION, TABANGO, LEYTE, CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), MARCELINO R. VELOSO NATIONAL HIGH SCHOOL, POBLACION, TABANGO, LEYTE, CONSTRUCTION OF | Region VIII | Leyte 3rd DEO | Completed | ₱813.4K | 100% | Low risk23 | —-0.063 |
| 210 | 19IE0014CONSTRUCTION OF FLOOD MITIGATION STRUCTURE-CONSTRUCTION OF HINABUYAN FLOOD CONTROL,VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱2.8M | 100% | Low risk23 | —-0.079 |
| 211 | 21IE0100CONSTRUCTION OF LOCAL ACCESS ROAD IN BRGY. LIBASBRGY. LIBAS, LEYTE, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱3.9M | 100% | Low risk23 | —-0.093 |
| 212 | 21IE0046CONSTRUCTION OF MULTIPURPOSE BUILDINGBRGY. CALBUGOS, VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱2M | 100% | Low risk23 | —-0.098 |
| 213 | 19IE0155CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS)CATMON ELEMENTARY SCHOOL, TABANGO, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱197K | 100% | Low risk23 | —-0.060 |
| 214 | 21IE0041CONSTRUCTION OF BARANGAY A. TUMAMAK FLOOD CONTROL, (VILLABA COMPREHENSIVE NATIONAL HIGH SCHOOL), VILLABA, LEYTEVILLABA, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱2.9M | 100% | Low risk23 | —-0.080 |
| 215 | 20IE0054CONSTRUCTION OF CAIGUIT FLOOD CONTROLBRGY. POBLACION DEL NORTE, VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱3.8M | 100% | Low risk22 | —-0.076 |
| 216 | 23IE0112CONSTRUCTION OF 1STY3CL, SANGABON ELEMENTARY SCHOOL, SAN ISIDRO, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱2.4M | 100% | Low risk22 | —-0.053 |
| 217 | 20IE0085CONSTRUCTION OF LOCAL ROADS TO BUSAY FALLS, BRGY. ABIJAO, VILLABA, LEYTEVILLABA, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱2.9M | 100% | Low risk22 | —-0.090 |
| 218 | 19IE0013CONSTRUCTION OF FLOOD MITIGATION STRUCTURE-CONSTRUCTION OF SEAWALL, JORDAN ESVILLABA, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱3.7M | 100% | Low risk22 | —-0.078 |
| 219 | 21IE0039CONSTRUCTION OF BOX CULVERT SPILLWAY, BARANGAY CAHIGAN, VILLABA, LEYTEVILLABA, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱3.9M | 100% | Low risk22 | —-0.080 |
| 220 | 23IE0113CONSTRUCTION OF 1STY1CL, HUGPA ELEMENTARY SCHOOL, SAN ISIDRO, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱2.5M | 100% | Low risk22 | —-0.053 |
| 221 | 19IE0157CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS)CABUNGAHAN ELEMENTARY SCHOOL, VILLABA, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱197K | 100% | Low risk22 | —-0.060 |
| 222 | 21IE0074CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. POBLACION, CALUBIAN, LEYTEBRGY. POBLACION, CALUBIAN, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱1.9M | 100% | Low risk22 | —-0.098 |
| 223 | 19IE0153CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS)YBANES MEMORIAL ELEMENTARY SCHOOL, TABANGO, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱197K | 100% | Low risk22 | —-0.060 |
| 224 | 20IE0079CONSTRUCTION OF MULTIPURPOSE BUILDINGBRGY. INALAD, CALUBIAN, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱1.9M | 100% | Low risk22 | —-0.099 |
| 225 | 20IE0110CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), DON BERNARDO ES, TABANGO, LEYTE | Region VIII | Leyte 3rd DEO | Completed | ₱361.9K | 100% | Low risk21 | —-0.062 |