47 projects on file, including joint ventures this contractor is part of.
Total projects
47
Total budget
₱296.6M
Average progress
99.8%
Completion rate
87.2%
Average risk score
36.6
Medium risk on average, out of 100
Flagged as unusual
1
2.1% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Negros Island Region | 47 | ₱296.6M | 36.6 | 1 | 99.8% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 22 | ₱89.4M | 33.0 | 0 | 100.0% |
| Roads | 20 | ₱181.5M | 39.0 | 1 | 99.5% |
| Water Provision and Storage | 3 | ₱21.9M | 37.2 | 0 | 100.0% |
| GAA 2025 SSP | 1 | ₱2M | 81.1 | 0 | 100.0% |
| Flood Control and Drainage | 1 | ₱2M | 22.3 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25RG0043BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MANSEJE, BINDOY, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱2M | 100% | High risk81 | —-0.016 |
| 25GL0120CONCRETING OF BRGY. LIMA-LIMA FMR, BRGY. LIMA-LIMA, ISABELA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | On-Going | ₱14.9M | 100% | High risk66 | Flagged0.012 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25GL0120CONCRETING OF BRGY. LIMA-LIMA FMR, BRGY. LIMA-LIMA, ISABELA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | On-Going | ₱14.9M | 100% | High risk66 | Flagged0.012 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 19GM0049CONSTRUCTION OF ROAD, SITIO HONASAN TO SITIO POLO, BRGY. 1, ILOG, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱9.4M | 100% | Medium risk44 | —-0.091 |
| 27 | 24GL0077CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 1, HIMAMAYLAN, NEGROS OCCDIENTAL | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱5.2M | 100% | Medium risk43 | —-0.087 |
| 28 | 25GL0089CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY BUENAVISTA, HIMAMAYLAN CITY, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | On-Going | ₱5.4M | 100% | Medium risk43 | —-0.062 |
| 29 | 23HJ0066BASIC INFRASTRUCTURE PROGRAM: EVACUATION CENTERS/ QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION OF EVACUATION CENTERS / COVERED COURT, BULADO, GUIHULNGAN CITY, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱5M | 100% | Medium risk43 | —-0.086 |
| 30 | 24GL0120CONSTRUCTION OF 1-STOREY 2 CLASSROOM SCHOOL BUILDING IN DON ANGEL LOCSIN ELEMENTARY SCHOOL, BARANGAY ENCLARO, BINALBAGAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | Completed | ₱5M | 100% | Medium risk37 | —-0.046 |
| 31 | 24HJ0108CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN JIMALALUD NATIONAL SCIENCE HIGH SCHOOL, BRGY. SOUTH POBLACION, JIMALALUD, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱5.4M | 100% | Medium risk35 | —-0.043 |
| 32 | 23GM0061CONSTRUCTION/REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTOR SYSTEM - RAINWATER COLLECTOR IN PUBLIC FACILITIES | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱2.3M | 100% | Low risk23 | —-0.050 |
| 33 | 19GM0037CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF BRGY. CALUBANG ROAD, ILOG, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱2.8M | 100% | Low risk23 | —-0.089 |
| 34 | 22HJ0014CONSTRUCTION OF FLOOD CONTROL ALONG BATERIA RIVER (UPSTREAM), STA. 0+000 - STA. 0+100, GUIHULNGAN CITY, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱2M | 100% | Low risk22 | —-0.064 |
| 35 | 24HJ0014BASIC INFRASTRUCTURE PROGRAM: EVACUATION CENTERS/ QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT/EVACUATION CENTER), BARANGAY CANLAHAO, JIMALALUD, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱2M | 100% | Low risk21 | —-0.085 |
| 36 | 19HJ0073CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) MANTAHAO, NALUNDAN, BINDOY, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱3M | 100% | Low risk21 | —-0.086 |
| 37 | 22HJ0022CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MABUNGA, GUIHULNGAN CITY, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱4M | 100% | Low risk21 | —-0.086 |
| 38 | 21GM0006CONSTRUCTION OF MULTI PURPOSE BUILDING - CONSTRUCTION OF MULTI PURPOSE BUILDING (TOURISM CENTER), BRGY. DANCALAN, ILOG, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱3M | 100% | Low risk20 | —-0.087 |
| 39 | 22HJ0021CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY CANLUTO, BINDOY, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱2M | 100% | Low risk20 | —-0.086 |
| 40 | 19GM0036CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), TUYOM ELEMENTARY SCHOOL, BRGY. TUYOM, CAUAYAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱2.4M | 100% | Low risk20 | —-0.084 |
| 41 | 19GM0030(RE-BIDDING) CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), LUMBIA ELEMENTARY SCHOOL, BRGY. LUMBIA, CAUAYAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱2.4M | 100% | Low risk20 | —-0.084 |
| 42 | 22HJ0103REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-TERTIARY ROADS, MABINAY-AYUNGON ROAD K0120+083-K0120+108, BRGY. BAN-BAN, AYUNGON, NEGROS OCCIDENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱1.4M | 100% | Low risk18 | —-0.086 |
| 43 | 22HJ0105REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS, MABINAY-AYUNGON ROAD K0112+555 - K0112+580, BRGY. BAN-BAN, AYUNGON, NEGROS OCCIDENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱1.4M | 100% | Low risk18 | —-0.087 |
| 44 | 22HJ0095REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS, MABINAY-AYUNGON ROAD K0109+945 -K0109+988, BRGY. MABATO, AYUNGON, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱632K | 100% | Low risk18 | —-0.085 |
| 45 | 22HJ0096REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS, MABINAY-AYUNGON ROAD K0111+693 -K0111+708, BRGY. BAN-BAN, AYUNGON, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱658K | 100% | Low risk18 | —-0.086 |
| 46 | 23HJ0146IMPROVEMENT OF MUNICIPAL GYM SOUTH POBLACIONJIMALALUDNEGROS ORIENTAL | Negros Island Region | Negros Oriental 1st DEO | Completed | ₱2.4M | 100% | Low risk13 | —-0.046 |
| 47 | 18GM0161CONSTRUCTION OF ONE (1) UNIT ONE (1) STOREY REGULAR WORKSHOP AT GUILJUNGAN NHS-ABACA EXT., CAUAYAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 3rd DEO | Completed | ₱3M | 100% | Low risk13 | —-0.044 |