Contractor dossier
122 projects on file, including joint ventures this contractor is part of.
Total projects
122
Total budget
₱1.9B
Average progress
96.0%
Completion rate
91.0%
Average risk score
35.6
Medium risk on average, out of 100
Flagged as unusual
5
4.1% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-B | 122 | ₱1.9B | 35.6 | 5 | 96.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 52 | ₱579.5M | 33.9 | 5 | 91.7% |
| Roads | 38 | ₱617.5M | 38.2 | 0 | 99.7% |
| Flood Control and Drainage | 13 | ₱295.2M | 38.8 | 0 | 99.1% |
| Water Provision and Storage | 11 | ₱45.4M | 27.2 | 0 | 100.0% |
| Bridges | 8 | ₱320.5M | 40.9 | 0 | 95.9% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 19E00041RETROFITTING/STRENTHENING OF LUMINTAO BRIDGE ALONG MINDORO WEST COASTAL ROAD, MINDORO OCCIDENTAL | Region IV-B | Region IV-B | Completed | ₱135M | 100% | High risk63 | —-0.025 |
| 25EB0057CONSTRUCTION OF ROAD GOING TO PUBLIC CEMETERY, BARANGAY SAN AGUSTIN, SAN JOSE, OCCIDENTAL MINDORO | Region IV-B | Mindoro Occidental DEO | Completed | ₱4.8M | 100% | High risk62 | —-0.049 |
| 24E00155BASIC INFRASTRUCTURE PROGRAM (BIP)- ACCESS ROAD/S AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF MULTI-PURPOSE BUILDING, BRGY. IV, SAN JOSE, OCCIDENTAL MINDORO | Region IV-B | Region IV-B | On-Going | ₱193.6M | 0% | High risk61 | Flagged0.012 |
| 25EB0042CONSTRUCTION OF ROAD, BARANGAY BARAHAN, SANTA CRUZ, OCCIDENTAL MINDORO | Region IV-B | Mindoro Occidental DEO | Completed | ₱9.6M | 100% | High risk61 | —-0.051 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24E00240LGU HOSPITALS - SAN JOSE DIAGNOSTIC CENTER AND PUBLIC HEALTH, SAN JOSE, OCCIDENTAL MINDORO | Region IV-B | Region IV-B | On-Going | ₱9.6M | 26% | Medium risk53 | Flagged0.034 |
| 24E00217OCCIDENTAL MINDORO STATE COLLEGE- CONST. OF RESEARCH, DEVELOPMENT AND EXTENSION BUILDING WITH OTHER MACHINERY AND EQUIPMENT AND FURNITUIRE AND FIXTURES, MAIN CAMPUS, OCC. MINDORO | Region IV-B | Region IV-B | On-Going | ₱9.8M | 47% | Medium risk53 | Flagged0.028 |
| 24E00242LGU HOSPITALS - STA. CRUZ COMMUNITY HOSPITAL, STA. CRUZ, OCCIDENTAL MINDORO | Region IV-B | Region IV-B | On-Going | ₱28.8M | 0% | Medium risk43 | Flagged0.026 |
| 24E00218OCCIDENTAL MINDORO STATE COLLEGE- CONST. OF LABORATORY BUILDING WITH CLASSROOMS- MAIN CAMPUS, OCC. MINDORO | Region IV-B | Region IV-B | On-Going | ₱14.1M | 73% | Medium risk54 | Flagged0.018 |
| 24E00155BASIC INFRASTRUCTURE PROGRAM (BIP)- ACCESS ROAD/S AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF MULTI-PURPOSE BUILDING, BRGY. IV, SAN JOSE, OCCIDENTAL MINDORO | Region IV-B | Region IV-B | On-Going | ₱193.6M | 0% | High risk61 | Flagged0.012 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 76 | 24EB0086CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), P. JARANILLA ST., SO. PULANG LUPA, BARANGAY SAN NICOLAS, SABLAYAN, OCCIDENTAL MINDORO | Region IV-B | Mindoro Occidental DEO | Completed | ₱4.8M | 100% | Medium risk35 | —-0.083 |
| 77 | 24EB0084CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARRANGAY HALL), BARANGAY LAGNAS, SABLAYAN, OCCIDENTAL MINDORO | Region IV-B | Mindoro Occidental DEO | Completed | ₱4.8M | 100% | Medium risk35 | —-0.083 |
| 78 | 25EB0039CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION 1, SANTA CRUZ, OCCIDENTAL MINDORO | Region IV-B | Mindoro Occidental DEO | On-Going | ₱4.8M | 44% | Medium risk35 | —-0.033 |
| 79 | 21EB0084CONSTRUCTION OF TWO-STOREY MULTI-PURPOSE BUILDING IN PINAGTURILAN NATIONAL HIGH SCHOOL, BARANGAY PINAGTURILAN, SANTA CRUZ, OCCIDENTAL MINDORO | Region IV-B | Mindoro Occidental DEO | Completed | ₱4.8M | 100% | Medium risk35 | —-0.082 |
| 80 | 18EB0163CLUSTER 2018-LIP:LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTIONOF VARIOUS MULTI-PURPOSE BUILDING (DAYCARE CENTER): A) BRGY. CABACAO, ABRA DE ILOG, B) BARANGAY LABANGAN, POBLACION, SAN JOSE, C) BARANGAY MANGARIN, SAN JOSE, D) BARANGAY PAG-ASA, SAN JOSE, OCCIDEN | Region IV-B | Mindoro Occidental DEO | Completed | ₱5.4M | 100% | Medium risk35 | —-0.080 |
| 81 | 18EB0054NATIONAL BUILDING PROGRAM MULTIPURPOSE/ FACILITIES, CONSTRUCTION OF EVACUATION CENTER, BRGY. STA. NINO, SABLAYAN, OCCIDENTAL MINDORO | Region IV-B | Mindoro Occidental DEO | Completed | ₱4.8M | 100% | Medium risk35 | —-0.083 |
| 82 | 24EB0065CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 6, PALUAN, OCCIDENTAL MINDORO | Region IV-B | Mindoro Occidental DEO | Completed | ₱4.9M | 100% | Medium risk34 | —-0.081 |
| 83 | 24EB0110CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN IRIRON ELEMENTARY SCHOOL, BARANGAY IRIRON, CALINTAAN, OCCIDENTAL MINDORO | Region IV-B | Mindoro Occidental DEO | Completed | ₱5M | 100% | Medium risk34 | —-0.043 |
| 84 | 23EB0050CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY GUITNA, LOOC, OCCIDENTAL MINDORO | Region IV-B | Mindoro Occidental DEO | Completed | ₱4.9M | 100% | Medium risk34 | —-0.080 |
| 85 | 22EA0196CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT TORRIJOS WHITE BEACH, BRGY. POCTOY, TORRIJOS, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱4.8M | 100% | Medium risk34 | —-0.085 |
| 86 | 22EA0075CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LABO, SANTA CRUZ, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱6.8M | 100% | Medium risk34 | —-0.087 |
| 87 | 22EA0035CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BAGUIDBIRIN, SANTA CRUZ, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱6.8M | 100% | Medium risk34 | —-0.087 |
| 88 | 22EA0094CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POCTOY, TORRIJOS, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱6.8M | 100% | Medium risk34 | —-0.087 |
| 89 | 22EA0170CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. PILI, BOAC, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱6.7M | 100% | Medium risk34 | —-0.086 |
| 90 | 22EA0158CONSTRUCTION OF MULTI-PURPOSE BUILDING AT DAYKITIN ELEMENTARY SCHOOL, BARANGAY DAYKITIN, BUENAVISTA, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱6.8M | 100% | Medium risk34 | —-0.088 |
| 91 | 24EA0007CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LIBJO, SANTA CRUZ, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱6.8M | 100% | Medium risk34 | —-0.087 |
| 92 | 23EA0115CONSTRUCTION OF ROAD, BRGY. TAWIRAN, SANTA CRUZ, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱4.8M | 100% | Medium risk34 | —-0.038 |
| 93 | 22EA0045CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BANAHAW POBLACION, SANTA CRUZ, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱6.8M | 100% | Medium risk34 | —-0.087 |
| 94 | 22EA0078CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LUSOK, SANTA CRUZ, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱6.8M | 100% | Medium risk34 | —-0.088 |
| 95 | 24EB0107CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN BULACAN ELEMENTARY SCHOOL, BARANGAY BULACAN, LOOC, OCCIDENTAL MINDORO | Region IV-B | Mindoro Occidental DEO | Completed | ₱5M | 100% | Medium risk33 | —-0.040 |
| 96 | 23EA0075CONCRETING OF BRGY. KILO KILO FMR, BRGY. KILOKILO, SANTA CRUZ, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱11.9M | 100% | Medium risk33 | —-0.040 |
| 97 | 22EA0276CONCRETING OF BRGY. LABO FMR, BRGY. LABO SANTA CRUZ, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱12.4M | 100% | Medium risk33 | —-0.040 |
| 98 | 22EA0255CONCRETING OF BRGY. SAN ANTONIO FMR PHASE 2, BRGY. SAN ANTONIO, SANTA CRUZ, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱12.4M | 100% | Medium risk33 | —-0.041 |
| 99 | 21EA0154CONCRETING OF BRGY. PUTING BUHANGIN FMR, BRGY. PUTING BUHANGIN, MOGPOG, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱12.4M | 100% | Medium risk33 | —-0.041 |
| 100 | 21EA0152CONCRETING OF BRGY. DOLORES TO BRGY. DATING BAYAN FMR, BRGY. DOLORES AND BRGY. DATING BAYAN, STA. CRUZ, MARINDUQUE | Region IV-B | Marinduque DEO | Completed | ₱12.4M | 100% | Medium risk33 | —-0.041 |