Opening the dossier…
Opening the dossier…
Contractor dossier
69 projects on file, including joint ventures this contractor is part of.
Total projects
69
Total budget
₱1.6B
Average progress
87.0%
Completion rate
85.5%
Average risk score
38.3
Medium risk on average, out of 100
Flagged as unusual
7
10.1% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 34 | ₱843.7M | 31.1 | 1 | 99.9% |
| Region I | 28 | ₱374M | 45.1 | 6 | 68.1% |
| Region II | 7 | ₱349.8M | 46.0 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 28 | ₱287.6M | 40.0 | 5 | 78.6% |
| Buildings and Facilities | 25 | ₱264M | 27.1 | 0 | 100.0% |
| Flood Control and Drainage | 12 | ₱885.3M | 51.8 | 0 | 83.4% |
| Bridges | 2 | ₱24.3M | 48.0 | 1 | 53.0% |
| GAA 2025 SSP | 1 | ₱96.5M | 95.4 | 1 | 95.0% |
| Water Provision and Storage | 1 | ₱9.8M | 33.6 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25CE0211CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ILOG BALIWAG RIVER, BARANGAY SAN ANTONIO, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | On-Going | ₱96.5M | 95% | High risk95 | Flagged0.006 |
| 23BJ0051BASIC INFRASTRUCTURE PROGRAM-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES CONSTRUCTION OF FLOOD CONTROL STRUCTURES AT SITIO PAITUG SECTION, SAN FABIAN, KAYAPA, NUEVA VIZCAYA | Region II | Nueva Vizcaya 2nd DEO | Completed | ₱98M | 100% | High risk61 | —-0.055 |
| 23BJ0033CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF FLOOD CONTROL STRUCTURES AT BALILING-CALITLITAN SECTION, STA. FE, NUEVA VIZCAYA | Region II | Nueva Vizcaya 2nd DEO | Completed | ₱96.5M | 100% | High risk61 | —-0.057 |
| 23BJ0032CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF FLOOD CONTROL STRUCTURES AT COMON-LATAR SECTION, ARITAO, NUEVA VIZCAYA | Region II | Nueva Vizcaya 2nd DEO | Completed | ₱96.5M | 100% | High risk60 | —-0.057 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24AI0306CONSTRUCTION OF FARM-TO-MARKET ROAD IN KASKASYA RD., BRGY. SAN ISIDRO, SAN NICOLAS | Region I | Pangasinan 3rd DEO | On-Going | ₱5.4M | 0% | Medium risk45 | Flagged0.029 |
| 24AI0309CONSTRUCTION OF FARM-TO-MARKET ROAD IN BRGY. SAN FELIPE WEST, SAN NICOLAS | Region I | Pangasinan 3rd DEO | On-Going | ₱5.2M | 0% | Medium risk45 | Flagged0.029 |
| 24AI0310CONSTRUCTION OF FARM-TO-MARKET ROAD IN BRGY. CACABUGAOAN, SAN NICOLAS | Region I | Pangasinan 3rd DEO | On-Going | ₱985K | 0% | Medium risk30 | Flagged0.028 |
| 24AI0277CONCRETING OF PUROK 3 AND 4 RD BRGY. SINABAAN, UMINGAN, PANGASINAN | Region I | Pangasinan 3rd DEO | On-Going | ₱3M | 0% | Medium risk37 | Flagged0.027 |
| 24AI0276CONCRETING OF BRGY. LA PAZ FARM TO MARKET ROAD, UMINGAN, PANGASINAN | Region I | Pangasinan 3rd DEO | On-Going | ₱8.8M | 0% | Medium risk46 | Flagged0.027 |
| 23AI0117WIDENING OF PERMANENT BRIDGES-ABARABAR-PALAGANAS BRIDGE (B01618LZ) ALONG BINALONAN-ASINGAN-SANTA MARIA ROAD | Region I | Pangasinan 3rd DEO | On-Going | ₱12.7M | 6% | Medium risk48 | Flagged0.018 |
| 25CE0211CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ILOG BALIWAG RIVER, BARANGAY SAN ANTONIO, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | On-Going | ₱96.5M | 95% | High risk95 | Flagged0.006 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25CE0211CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ILOG BALIWAG RIVER, BARANGAY SAN ANTONIO, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | On-Going | ₱96.5M | 95% | High risk95 | Flagged0.006 |
| 2 | 23BJ0051BASIC INFRASTRUCTURE PROGRAM-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES CONSTRUCTION OF FLOOD CONTROL STRUCTURES AT SITIO PAITUG SECTION, SAN FABIAN, KAYAPA, NUEVA VIZCAYA | Region II | Nueva Vizcaya 2nd DEO | Completed | ₱98M | 100% | High risk61 | —-0.055 |
| 3 | 23BJ0033CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF FLOOD CONTROL STRUCTURES AT BALILING-CALITLITAN SECTION, STA. FE, NUEVA VIZCAYA | Region II | Nueva Vizcaya 2nd DEO | Completed | ₱96.5M | 100% | High risk61 | —-0.057 |
| 4 | 23BJ0032CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF FLOOD CONTROL STRUCTURES AT COMON-LATAR SECTION, ARITAO, NUEVA VIZCAYA | Region II | Nueva Vizcaya 2nd DEO | Completed | ₱96.5M | 100% | High risk60 | —-0.057 |
| 5 | 24CE0016REHABILITATION OF DIKE ALONG TALAVERA RIVER, BARANGAY CONCEPCION TO SAN AGUSTIN, SANTO DOMINGO, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱95.5M | 100% | Medium risk56 | —-0.078 |
| 6 | 24CE0015REHABILITATION OF DIKE ALONG TALAVERA RIVER, BARANGAY DOLORES, SANTO DOMINGO, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱95.5M | 100% | Medium risk56 | —-0.078 |
| 7 | 23CE0042CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG LABONG RIVER, BRGY. POBLACION SUR, LICAB, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱96.5M | 100% | Medium risk55 | —-0.077 |
| 8 | 23CE0082REHABILITATION OF DIKE ALONG TALAVERA RIVER, BRGY. POBLACION SUR, TALAVERA, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱99M | 100% | Medium risk55 | —-0.076 |
| 9 | 23CE0052REHABILITATION OF DIKE ALONG TALAVERA RIVER, BRGY. SAN AGUSTIN, STO. DOMINGO, NUEVA ECIJA | Region III | Nueva Ecija 1st DEO | Completed | ₱96.5M | 100% | Medium risk55 | —-0.078 |
| 10 | 21A00253LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF MULTI-PURPOSE BUILDING, SAN CARLOS CITY, PANGASINAN | Region I | Pangasinan 4th DEO | Completed | ₱29.7M | 100% | Medium risk53 | —-0.081 |
| 11 | 22AI0168REHABILITATION OF ANTONIO P. VILLAR GYMNASIUM, BRGY. POBLACION, STO. TOMAS, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱4.9M | 100% | Medium risk52 | —-0.089 |
| 12 | 25AI0066CONSTRUCTION/IMPROVEMENT OF AGNO RIVER SLOPE BANK PROTECTION WORKS ALONG AGNO AND ALLIED RIVERS, ROSALES, PANGASINAN (PACKAGE B) | Region I | Pangasinan 3rd DEO | On-Going | ₱48.2M | 1% | Medium risk51 | —-0.009 |
| 13 | 25AI0065CONSTRUCTION/IMPROVEMENT OF AGNO RIVER SLOPE BANK PROTECTION WORKS ALONG AGNO AND ALLIED RIVERS, ROSALES, PANGASINAN (PACKAGE A) | Region I | Pangasinan 3rd DEO | On-Going | ₱48.2M | 1% | Medium risk51 | —-0.009 |
| 14 | 23AI0117WIDENING OF PERMANENT BRIDGES-ABARABAR-PALAGANAS BRIDGE (B01618LZ) ALONG BINALONAN-ASINGAN-SANTA MARIA ROAD | Region I | Pangasinan 3rd DEO | On-Going | ₱12.7M | 6% | Medium risk48 | Flagged0.018 |
| 15 | 22AI0021REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, MACALONG BR. (B00725LZ) ALONG MANILA NORTH RD | Region I | Pangasinan 3rd DEO | Completed | ₱11.6M | 100% | Medium risk48 | —-0.053 |
| 16 | 22AI0193CONSTRUCTION OF TWO (2) STOREY, FOUR (4) CLASSROOM SCHOOL BUILDING ERNESTING GONZALES CENTRAL SCHOOL AT STO. TOMAS, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱15.4M | 100% | Medium risk46 | —-0.045 |
| 17 | 22AI0065CONSTRUCTION OF PEDESTRIAN OVERPASS, BINALONAN, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱19.5M | 100% | Medium risk46 | —-0.088 |
| 18 | 25AI0055CONSTRUCTION OF ROAD, STO. TOMAS, PANGASINAN | Region I | Pangasinan 3rd DEO | On-Going | ₱9.7M | 0% | Medium risk46 | —-0.024 |
| 19 | 22AI0022CONSTRUCTION OF PEDESTRIAN OVERPASS, URDANETA, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱19.3M | 100% | Medium risk46 | —-0.087 |
| 20 | 22AI0062CONSTRUCTION OF PEDESTRIAN OVERPASS, VILLASIS, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱19.5M | 100% | Medium risk46 | —-0.088 |
| 21 | 22AI0026REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS, CARMEN JUNCTION-MANAT ROAD, K0 172+(-697)-K0 172+000, K0 173+000-KO 173+699 | Region I | Pangasinan 3rd DEO | Completed | ₱19.3M | 100% | Medium risk46 | —-0.089 |
| 22 | 24AI0276CONCRETING OF BRGY. LA PAZ FARM TO MARKET ROAD, UMINGAN, PANGASINAN | Region I | Pangasinan 3rd DEO | On-Going | ₱8.8M | 0% | Medium risk46 | Flagged0.027 |
| 23 | 23AI0008CONSTRUCTION OF ROAD, LUNA ESTE-LUNA WESTE, UMINGAN, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱9.9M | 100% | Medium risk45 | —-0.091 |
| 24 | 23AI0002CONSTRUCTION OF ROAD, CALAPUGAN, NATIVIDAD, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱8.8M | 100% | Medium risk45 | —-0.090 |
| 25 | 23AI0046CONSTRUCTION OF ROAD, BARANGAY TOMBOD, VILLASIS, PANGASINAN | Region I | Pangasinan 3rd DEO | Completed | ₱6.9M | 100% | Medium risk45 | —-0.090 |