Opening the dossier…
Opening the dossier…
Contractor dossier
31 projects on file, including joint ventures this contractor is part of.
Total projects
31
Total budget
₱1.1B
Average progress
92.4%
Completion rate
77.4%
Average risk score
43.7
Medium risk on average, out of 100
Flagged as unusual
6
19.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-B | 31 | ₱1.1B | 43.7 | 6 | 92.4% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Bridges | 15 | ₱395.3M | 36.4 | 0 | 99.7% |
| Buildings and Facilities | 7 | ₱54.1M | 33.1 | 0 | 100.0% |
| Roads | 5 | ₱507.2M | 46.3 | 2 | 66.5% |
| GAA 2025 OO-1 | 2 | ₱112M | 92.2 | 2 | 72.0% |
| OTHER | 2 | ₱81.3M | 81.1 | 2 | 96.4% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25EF0028WIDENING OF PERMANENT BRIDGES CALATEGAS BR. (B00046PW) ALONG PPSR, NARRA, PALAWAN | Region IV-B | Palawan 2nd DEO | On-Going | ₱65.2M | 59% | High risk93 | Flagged0.024 |
| 25EF0007WIDENING OF PERMANENT BRIDGES-TAGDIDILI BR.(B00371PW) ALONG PPSR, BROOKE'S POINT, PALAWAN | Region IV-B | Palawan 2nd DEO | On-Going | ₱46.8M | 85% | High risk91 | Flagged0.019 |
| 24EF0084CONST. OF SCHOOL BLDG., PUNANG ES BLDG. IN SOFRONIO ESPANOLA, PAL., SOFRONIO ESPANOLA, PAL. | Region IV-B | Palawan 2nd DEO | On-Going | ₱19.9M | 96% | High risk84 | Flagged0.068 |
| 24EF0052WIDENING OF PERMANENT BRIDGES MALANAP BR. (B00061PW) ALONG PUERTO PRINCESA SOUTH RD, SOFRONIO ESPANOLA, PALAWAN | Region IV-B | Palawan 2nd DEO | On-Going | ₱61.4M | 96% | High risk78 | Flagged0.025 |
| 25E00257SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- CONST. OF CABIGAAN-APURAWAN CROSS COUNTRY ROAD PACKAGE B, STA. 4+160.00-STA. 4+860.00, ABORLAN, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱232.8M | 0% | High risk63 | Flagged0.042 |
| 25E00251SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- CONST. OF SANDOVAL-PAJO-(IGANG-IGANG)-SARONG-OCAYAN ROAD PACKAGE F, BATARAZA, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱232.8M | 32% | High risk63 | Flagged0.012 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24EF0084CONST. OF SCHOOL BLDG., PUNANG ES BLDG. IN SOFRONIO ESPANOLA, PAL., SOFRONIO ESPANOLA, PAL. | Region IV-B | Palawan 2nd DEO | On-Going | ₱19.9M | 96% | High risk84 | Flagged0.068 |
| 25E00257SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- CONST. OF CABIGAAN-APURAWAN CROSS COUNTRY ROAD PACKAGE B, STA. 4+160.00-STA. 4+860.00, ABORLAN, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱232.8M | 0% | High risk63 | Flagged0.042 |
| 24EF0052WIDENING OF PERMANENT BRIDGES MALANAP BR. (B00061PW) ALONG PUERTO PRINCESA SOUTH RD, SOFRONIO ESPANOLA, PALAWAN | Region IV-B | Palawan 2nd DEO | On-Going | ₱61.4M | 96% | High risk78 | Flagged0.025 |
| 25EF0028WIDENING OF PERMANENT BRIDGES CALATEGAS BR. (B00046PW) ALONG PPSR, NARRA, PALAWAN | Region IV-B | Palawan 2nd DEO | On-Going | ₱65.2M | 59% | High risk93 | Flagged0.024 |
| 25EF0007WIDENING OF PERMANENT BRIDGES-TAGDIDILI BR.(B00371PW) ALONG PPSR, BROOKE'S POINT, PALAWAN | Region IV-B | Palawan 2nd DEO | On-Going | ₱46.8M | 85% | High risk91 | Flagged0.019 |
| 25E00251SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- CONST. OF SANDOVAL-PAJO-(IGANG-IGANG)-SARONG-OCAYAN ROAD PACKAGE F, BATARAZA, PALAWAN | Region IV-B | Region IV-B | On-Going | ₱232.8M | 32% | High risk63 | Flagged0.012 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 26 | 24EG0082CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN CABIGAAN ELEMENTARY SCHOOL, BARANGAY CABIGAAN, MUNICIPALITY OF ABORLAN, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱5.7M | 100% | Low risk28 | —-0.021 |
| 27 | 20EF0032RETROFITTING OF PERMANENT BRIDGE TAGLUMOT BR. (B00162PW) ALONG PPSR JCT. (ABO-ABO)-QUEZON RD., QUEZON, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱3.9M | 100% | Low risk23 | —-0.035 |
| 28 | 20EF0063RETROFITTING OF PERMANENT BRIDGES MALLAG BR. (BOO350PW) ALONG PALAWAN CIRCUMFERENTIAL RD., RIZAL, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱3.9M | 100% | Low risk23 | —-0.034 |
| 29 | 20EG0032REHABILITATION/ MAJOR REPAIR OF PERMANENT BRIDGES - MENTIS BR. (B00093PW) ALONG PUERTO PRINCESA NORTH RD, PUERTO PRINCESA CITY | Region IV-B | Palawan 3rd DEO | Completed | ₱3.9M | 100% | Low risk22 | —-0.040 |
| 30 | 22EF0099RETROFITTING OF BRIDGE, BRGY. TARITIEN, NARRA, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱4M | 100% | Low risk22 | —-0.037 |
| 31 | 20EG0006REHABILITATION/ MAJOR REPAIR OF PERMANENT BRIDGES, MARUYUGON BR. (B00092PW) ALONG PUERTO PRINCESA NORTH RD, PUERTO PRINCESA CITY | Region IV-B | Palawan 3rd DEO | Completed | ₱1.5M | 100% | Low risk17 | —-0.037 |