Contractor dossier
13 projects on file, including joint ventures this contractor is part of.
Total projects
13
Total budget
₱129.9M
Average progress
77.0%
Completion rate
30.8%
Below 70%
Average risk score
55.1
Medium risk on average, out of 100
Flagged as unusual
4
30.8% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VI | 13 | ₱129.9M | 55.1 | 4 | 77.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 6 | ₱44.6M | 45.2 | 2 | 52.9% |
| Roads | 4 | ₱65.7M | 45.1 | 0 | 98.9% |
| GAA 2025 SSP | 2 | ₱9.9M | 93.2 | 2 | 95.1% |
| OTHER | 1 | ₱9.8M | 78.2 | 0 | 98.2% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25GB0023CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SINUNDULAN, SAN REMIGIO, ANTIQUE | Region VI | Antique DEO | On-Going | ₱4.9M | 90% | High risk93 | Flagged0.015 |
| 25GB0055CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO APONG, BARANGAY CABLADAN, SIBALOM,ANTIQUE | Region VI | Antique DEO | On-Going | ₱4.9M | 100% | High risk93 | Flagged0.010 |
| 25GB0045CONSTRUCTION OF CONCRETE ROAD-BRGY. CAMANCIJAN- BRGY. ALOJIPAN ROAD LEADING TO MT. MADIA-AS CULASI, ANTIQUE | Region VI | Antique DEO | On-Going | ₱9.8M | 98% | High risk78 | —-0.007 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24GB0121CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN SAN RAMON PRIMARY SCHOOL BARANGAY SAN RAMON, | Region VI | Antique DEO | On-Going | ₱5M | 0% | Medium risk43 | Flagged0.036 |
| 24GB0119CONSTRUCTION OF 1-STOREY 4-CLASSROOM SCHOOL BUILDING IN ANINGALAN INTEGRATED FARM SCHOOL, BARANGAY A | Region VI | Antique DEO | On-Going | ₱9.9M | 0% | Medium risk42 | Flagged0.033 |
| 25GB0023CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SINUNDULAN, SAN REMIGIO, ANTIQUE | Region VI | Antique DEO | On-Going | ₱4.9M | 90% | High risk93 | Flagged0.015 |
| 25GB0055CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO APONG, BARANGAY CABLADAN, SIBALOM,ANTIQUE | Region VI | Antique DEO | On-Going | ₱4.9M | 100% | High risk93 | Flagged0.010 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25GB0023CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SINUNDULAN, SAN REMIGIO, ANTIQUE | Region VI | Antique DEO | On-Going | ₱4.9M | 90% | High risk93 | Flagged0.015 |
| 2 | 25GB0055CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO APONG, BARANGAY CABLADAN, SIBALOM,ANTIQUE | Region VI | Antique DEO | On-Going | ₱4.9M | 100% | High risk93 | Flagged0.010 |
| 3 | 25GB0045CONSTRUCTION OF CONCRETE ROAD-BRGY. CAMANCIJAN- BRGY. ALOJIPAN ROAD LEADING TO MT. MADIA-AS CULASI, ANTIQUE | Region VI | Antique DEO | On-Going | ₱9.8M | 98% | High risk78 | —-0.007 |
| 4 | 25GB0024CONSTRUCTION OF EVACUATION CENTER, BARANGAY SAN JUAN, SIBALOM, ANTIQUE | Region VI | Antique DEO | On-Going | ₱4.9M | 97% | Medium risk47 | —-0.053 |
| 5 | 24GB0105REHABILITATION OF MULTI-PURPOSE BUILDING (MUNICIPAL BUILDING) SAN REMIGIO, ANTIQUE | Region VI | Antique DEO | On-Going | ₱9.9M | 90% | Medium risk46 | —-0.039 |
| 6 | 24GB0026CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY OSORIO 1, MUNICIPALITY OF SAN REMIGIO, ANTIQUE | Region VI | Antique DEO | Completed | ₱4.9M | 100% | Medium risk46 | —-0.084 |
| 7 | 25GB0061CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (MUNICIPAL BUILDING), BARANGAY POBLACION, SAN REMIGIO , ANTIQUE | Region VI | Antique DEO | On-Going | ₱9.9M | 30% | Medium risk46 | —-0.030 |
| 8 | 25GB0004RECONSTRUCTION TO CONCRETE PAVEMENT - ILOILO-ANTIQUE RD, K0100+084 - K0101+846, SAN JOSE - SIBALOM, ANTIQUE | Region VI | Antique DEO | Completed | ₱28.6M | 100% | Medium risk46 | —-0.085 |
| 9 | 24GB0082CONSTRUCTION OF ROADS ALONG BRGY.CADOLDOLAN AND BRGY. BONGBONGAN I (SITIO BUGA) SIBALOM, ANTIQUE | Region VI | Antique DEO | Completed | ₱19.8M | 100% | Medium risk45 | —-0.086 |
| 10 | 25GB0030CONSTRUCTION OF CONCRETE ROAD INCLUDING DRAINAGE AND SLOPE PROTECTION-BRGY. SAN RAMON-BRGY. LATAZON-BRGY. LIBERATO ROAD CONNECTING TO ILOILO-ANTIQUE ROAD, PUBLIC MARKET OF LAUA-AN AND TO PROCESSING & PACKAGING PLANT OF MUSCOVADO SUGAR IN SUPPORT OF AGRIBU | Region VI | Antique DEO | On-Going | ₱9.8M | 96% | Medium risk45 | —-0.057 |
| 11 | 25GB0029INSTALLATION OF SOLAR STREETLIGHTS ALONG ILOILO-ANTIQUE ROAD (S00338PN)-K0098+000-K0099+000,ANTIQUE | Region VI | Antique DEO | Completed | ₱7.5M | 100% | Medium risk45 | —-0.086 |
| 12 | 24GB0121CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN SAN RAMON PRIMARY SCHOOL BARANGAY SAN RAMON, | Region VI | Antique DEO | On-Going | ₱5M | 0% | Medium risk43 | Flagged0.036 |
| 13 | 24GB0119CONSTRUCTION OF 1-STOREY 4-CLASSROOM SCHOOL BUILDING IN ANINGALAN INTEGRATED FARM SCHOOL, BARANGAY A | Region VI | Antique DEO | On-Going | ₱9.9M | 0% | Medium risk42 | Flagged0.033 |