Opening the dossier…
Opening the dossier…
Contractor dossier
72 projects on file, including joint ventures this contractor is part of.
Total projects
72
Total budget
₱1.5B
Average progress
99.2%
Completion rate
95.8%
Average risk score
36.2
Medium risk on average, out of 100
Flagged as unusual
1
1.4% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IV-B | 72 | ₱1.5B | 36.2 | 1 | 99.2% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 25 | ₱616.3M | 38.5 | 0 | 100.0% |
| Buildings and Facilities | 24 | ₱270.9M | 27.2 | 0 | 100.0% |
| Flood Control and Drainage | 12 | ₱415.8M | 42.0 | 0 | 97.0% |
| Bridges | 10 | ₱153M | 39.7 | 0 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱21.5M | 91.4 | 1 | 78.8% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25EE0045WIDENING OF PERMANENT BRIDGES- KAYLUBONG BRIDGE II (B00232PW) ALONG PUERTO PRINCESA NORTH ROAD, TAYTAY, PALAWAN | Region IV-B | Palawan 1st DEO | On-Going | ₱21.5M | 79% | High risk91 | Flagged0.013 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25EE0045WIDENING OF PERMANENT BRIDGES- KAYLUBONG BRIDGE II (B00232PW) ALONG PUERTO PRINCESA NORTH ROAD, TAYTAY, PALAWAN | Region IV-B | Palawan 1st DEO | On-Going | ₱21.5M | 79% | High risk91 | Flagged0.013 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 51 | 18EG0033CONSTRUCTION OF MULTI-PURPOSE BUILDING (TOURIST COMFORT STATION), BRGY BABUYAN, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱4.9M | 100% | Medium risk33 | —-0.067 |
| 52 | 22EG0046CONSTRUCTION OF MULTI-PURPOSE BUILDING B AT BARANGAY STA. MONICA, CITY OF PUERTO PRINCESA, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱4.9M | 100% | Medium risk32 | —-0.067 |
| 53 | 22EG0043CONSTRUCTION OF MULTI-PURPOSE BUILDING A AT BARANGAY STA. MONICA, CITY OF PUERTO PRINCESA, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱4.9M | 100% | Medium risk32 | —-0.067 |
| 54 | 18EE0247CONSTRUCTION OF TWO-STOREY 8 CLASSROOMS (4 REG. WORKSHOP) BATO NATIONALHIGH SCHOOL TAYTAY, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱15.7M | 100% | Medium risk32 | —-0.029 |
| 55 | 18EF0207CONST. OF 2STY 2CL RW, TARUSAN NHS, BATARAZA, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱9.1M | 100% | Medium risk31 | —-0.018 |
| 56 | 18EF0208CONST. OF 2STY 2CL SCI. LAB. & 2CL ICT LAB.TARUSAN NHS, BATARAZA, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱8.9M | 100% | Medium risk31 | —-0.018 |
| 57 | 18EG0131CONSTRUCTION OF 2STY12CL, LANGOGAN NHS, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱22.6M | 100% | Medium risk30 | —-0.025 |
| 58 | 18EF0148CONST. OF 2STY 10CL, SOFRONIO ESPAÑOLA CS,SOFRONIO, ESPAÑOLA, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱19.7M | 100% | Low risk30 | —-0.018 |
| 59 | 18EF0151CONST. OF 2-UNITS 2STY 2CL RW, ABO-ABO NATIONAL HIGH SCHOOL, SOFRONIO ESPAÑOLA, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱17.8M | 100% | Low risk30 | —-0.019 |
| 60 | 18EF0149CONST. OF 2STY 10CL., MAASIN ELEM. SCHOOL, QUEZON, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱20.4M | 100% | Low risk30 | —-0.019 |
| 61 | 18EF0164CONST. OF 2STY 2CL SCI. LAB & 2CL. ICT LAB. MAASIN NATIONAL HGH SCHOOL (BERNAS NHS), BROOKE'S POINT, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱17M | 100% | Low risk30 | —-0.018 |
| 62 | 18EF0169CONST. OF 2STY 2CL. SCI. LAB & 2CL ICT LAB., QUEZON, NHS, QUEZON, PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱16.9M | 100% | Low risk30 | —-0.019 |
| 63 | 18EF0182CONST. OF 2STY 1CL SCI. LAB & ICL ICT LAB, TABURI NATIONAL HIGH SCHOOL, RIZAL (MARCOS), PALAWAN | Region IV-B | Palawan 2nd DEO | Completed | ₱9.1M | 100% | Low risk28 | —-0.022 |
| 64 | 18EG0075CONCRETING OF T. PAREDES INTERIOR ROAD ALONG ABAD SANTOS EXTENSION, STA. 000+000.00-STA. 000+081.44 - STA. 000+000.00-STA. 000+076.51, BRGY. BAGONG SIKAT, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱1.9M | 100% | Low risk19 | —-0.068 |
| 65 | 19EG0126CONCRETING OF PUROK KAPALARAN - PUROK MALIGAYA, BRGY. LUZVIMINDA FMR, STA. 00+000.00 - STA. 0+190.00, BRGY. LUZVIMINDA, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱4.5M | 100% | Low risk18 | —-0.013 |
| 66 | 18EG0020CONSTRUCTION OF 3 CLASSROOM AT PALAWAN STATE UNIVERSITY- SAN RAFAEL CAMPUS, BRGY. SAN RAFAEL, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱3M | 100% | Low risk17 | —-0.067 |
| 67 | 18EG0062CONCRETING OF NIA ACCESS ROAD, STA. MONICA, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱976.3K | 100% | Low risk17 | —-0.066 |
| 68 | 21EG0007CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY SAN ISIDRO (SEASIDE), CITY OF PUERTO PRINCESA, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱2M | 100% | Low risk16 | —-0.066 |
| 69 | 18EE0356COMPLETION OF TWO-STOREY 8 CLASSROOMS (4 REG. WORKSHOP) BATO NATIONALHIGH SCHOOL TAYTAY, PALAWAN | Region IV-B | Palawan 1st DEO | Completed | ₱3.8M | 100% | Low risk11 | —-0.023 |
| 70 | 18EG0120CONSTRUCTION OF UNIQUE WORKSHOP, BACUNGAN NHS, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱3M | 100% | Low risk11 | —-0.021 |
| 71 | 18EG0161COMPLETION OF 2STY12CL, LANGOGAN NHS, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱2.5M | 100% | Low risk10 | —-0.027 |
| 72 | 18EG0153COMPLETION OF UNIQUE WORKSHOP, BACUNGAN NHS, PUERTO PRINCESA CITY, PALAWAN | Region IV-B | Palawan 3rd DEO | Completed | ₱640.4K | 100% | Low risk7 | —-0.018 |