Contractor dossier
125 projects on file, including joint ventures this contractor is part of.
Total projects
125
Total budget
₱7.8B
Average progress
93.6%
Completion rate
75.2%
Average risk score
55.0
Medium risk on average, out of 100
Flagged as unusual
32
25.6% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region III | 72 | ₱3.8B | 45.8 | 3 | 98.5% |
| Cordillera Administrative Region | 20 | ₱961.9M | 55.8 | 11 | 100.0% |
| Region VII | 8 | ₱869.6M | 92.9 | 8 | 66.7% |
| Region XI | 8 | ₱672.4M | 76.3 | 5 | 91.8% |
| Region X | 4 | ₱477.7M | 76.9 | 2 | 58.1% |
| Region IX | 4 | ₱118.2M | 64.0 | 1 | 62.0% |
| Region IV-A | 4 | ₱315.1M | 60.9 | 1 | 91.8% |
| Region XII | 2 | ₱276.9M | 49.1 | 0 | 100.0% |
| Region XIII | 1 | ₱96.4M | 92.5 | 1 | 90.0% |
| National Capital Region | 1 | ₱72.3M | 54.6 | 0 | 100.0% |
| Region II | 1 | ₱89.9M | 52.1 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 56 | ₱3.3B | 46.3 | 5 | 95.2% |
| Flood Control and Drainage | 32 | ₱1.7B | 50.0 | 8 | 98.5% |
| GAA 2025 SSP | 10 | ₱936.4M | 95.6 | 10 | 72.1% |
| Bridges | 9 | ₱316.3M | 46.7 | 0 | 100.0% |
| Buildings and Facilities | 7 | ₱376.5M | 54.0 | 0 | 100.0% |
| OTHER | 6 | ₱484.5M | 77.2 | 4 | 92.8% |
| GAA 2025 OO-2 | 3 | ₱385.3M | 93.1 | 3 | 77.7% |
| GAA 2025 OO-1 | 2 | ₱238.8M | 93.3 | 2 | 51.8% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25HB0112CONVERGENCE & SPECIAL SUPPORT PROGRAM - SPECIAL FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF ROAD SAFETY DEVICES, INFORMATIVE SIGNS AND SOLAR LIGHTING - SECONDARY ROADS - THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD | Region VII | Bohol 3rd DEO | On-Going | ₱93.6M | 60% | High risk96 | Flagged0.031 |
| 25HB0114CONVERGENCE AND SPECIAL SUPPORT PROGRAM SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 INSTALLATION OF ROAD SAFETY DEVICES, INFORMATION SIGNS AND SOLAR LIGHTING - SECONDARY ROADS - THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL R | Region VII | Bohol 3rd DEO | On-Going | ₱95.1M | 67% | High risk96 | Flagged0.029 |
| 25HB0110CONVERGENCE & SPECIAL SUPPORT PROGRAM - SPECIAL FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF ROAD SAFETY DEVICES, INFORMATIVE SIGNS AND SOLAR LIGHTING - SECONDARY ROADS - THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD ( | Region VII | Bohol 3rd DEO | On-Going | ₱93.6M | 76% | High risk96 | Flagged0.027 |
| 25HB0113CONVERGENCE AND SPECIAL SUPPORT PROGRAM SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 INSTALLATION OF ROAD SAFETY DEVICES, INFORMATIVE SIGNS AND SOLAR LIGHTING - SECONDARY ROADS - THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL R | Region VII | Bohol 3rd DEO | On-Going | ₱95.1M | 76% | High risk96 | Flagged0.027 |
| 25HB0115CONVERGENCE AND SPECIAL SUPPORT PROGRAM SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 INSTALLATION OF ROAD SAFETY DEVICES, INFORMATIVE SIGNS AND SOLAR LIGHTING - SECONDARY ROADS - THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL R | Region VII | Bohol 3rd DEO | On-Going | ₱95.1M | 77% | High risk96 | Flagged0.027 |
| 25HB0111CONVERGENCE & SPECIAL SUPPORT PROGRAM - SPECIAL FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF ROAD SAFETY DEVICES, INFORMATIVE SIGNS AND SOLAR LIGHTING - SECONDARY ROADS - THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD ( | Region VII | Bohol 3rd DEO | On-Going | ₱93.6M | 89% | High risk96 | Flagged0.022 |
| 25H00088CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, REHABILITATION OF CALAPE-PANGGANGAN ROAD IN BOHOL | Region VII | Region VII | On-Going | ₱163.3M | 23% | High risk96 | Flagged0.049 |
| 25LI0040INSTALLATION /APPLICATION OF ROAD SAFETY FACILITIES (PAVEMENT MARKINGS, ROAD SIGNS) ALONG MONTEVISTA - DNAS ROAD - K1413+(-602) - K1413+000, K1414+189-K1415+539, K1416+000 -K1422+945, K1422+961 - K1425+961, K1425+1007-K1428+776,K1428+812-K1429+406, | Region XI | Davao de Oro 2nd DEO | On-Going | ₱48.2M | 99% | High risk95 | Flagged0.009 |
| 25CG0068BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (DHVSU ANNEX), PHASE II, MALINO, CITY OF SAN FERNANDO, PAMPANGA | Region III | Pampanga 1st DEO | On-Going | ₱141.3M | 83% | High risk95 | Flagged0.018 |
| 25JF0018CONSTRUCTION OF ROAD LEADING TO BRGY. POBLACION - BRGY. DALANGIN - BRGY. DALANGIN MUSLIM - BRGY. ACHASOL - BRGY. SAN ANTONIO - BRGY. TUGOP - BRGY. BANGCO - BRGY. KALAWIT, TITAY, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | On-Going | ₱17.8M | 72% | High risk94 | Flagged0.021 |
| 25LI0084CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AGUSAN RIVER, PHASE 1, PUROK 7A TO 8, BARANGAY POBLACION, MONKAYO, DAVAO DE ORO | Region XI | Davao de Oro 2nd DEO | On-Going | ₱144.5M | 64% | High risk93 | Flagged0.016 |
| 25LI0073CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AGUIBAWA RIVER LEADING TO AGUSAN RIVER, PHASE 2, BARANGAY BANTACAN, NEW BATAAN, DAVAO DE ORO | Region XI | Davao de Oro 2nd DEO | On-Going | ₱144.5M | 79% | High risk93 | Flagged0.012 |
| 25KK0047PREVENTIVE MAINTENANCE - PRIMARY ROADS - BUTUAN CITY-CAGAYAN DE ORO CITY-ILIGAN CITY RD - K1298 + 000 - K1301 + 210 | Region X | Misamis Oriental 1st DEO | On-Going | ₱143.3M | 39% | High risk93 | Flagged0.021 |
| 25KK0048PREVENTIVE MAINTENANCE - PRIMARY ROADS - BUTUAN CITY-CAGAYAN DE ORO CITY-ILIGAN CITY RD - K1308 + 814 - K1311 + 395 | Region X | Misamis Oriental 1st DEO | On-Going | ₱95.5M | 64% | High risk93 | Flagged0.007 |
| 25NI0032CONSTRUCTION OF BANK REVETMENT ALONG HINATUAN RIVER (MALIXI SECTION), MALIXI, TAGBINA, SURIGAO DEL SUR | Region XIII | Surigao del Sur 2nd DEO | On-Going | ₱96.4M | 90% | High risk92 | Flagged0.004 |
| 24LA0136CONSTRUCTION OF ROAD, ARAIBO TO LAS ARENAS, PANTUKAN, DAVAO DE ORO | Region XI | Davao de Oro 1st DEO | On-Going | ₱82M | 92% | High risk89 | Flagged0.069 |
| 24CB0137CONSTRUCTION OF FLOOD CONTROL DIKE AT PANTINGAN RIVER (PHASE II), PILAR, BATAAN | Region III | Bataan 2nd DEO | On-Going | ₱108.1M | 98% | High risk88 | Flagged0.052 |
| 25CK0097INSTALLATION OF ROAD SAFETY DEVICES, INFORMATION SIGNS AND SOLAR LIGHTING - PRIMARY ROAD ALONG MANILA NORTH ROAD (CAPAS AND BAMBAN SECTION), CAPAS AND BAMBAN, TARLAC | Region III | Tarlac 2nd DEO | On-Going | ₱98M | 100% | High risk75 | —-0.033 |
| 18DN0069OO1-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-TERTIARY ROADS-MARIKINA-INFANTA ROAD, K0026+512-K0027+000, K0027+000-K0027+663, K0027+663-K0027+812, K0027+812-K0027+899, K0032+400-K0033+165, ANTIPOLO CITY, 2ND LD | Region IV-A | Rizal 1st DEO | Completed | ₱93M | 100% | High risk75 | —-0.030 |
| 25CK0077ASSET PRESERVATION PROGRAM: PREVENTIVE MAINTENANCE - TERTIARY ROADS ALONG TARLAC - ZAMBALES ROAD, PACKAGE 4, K0116+168 TO K0117+780, CAPAS, TARLAC | Region III | Tarlac 2nd DEO | On-Going | ₱93.6M | 90% | High risk75 | —-0.030 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24LA0136CONSTRUCTION OF ROAD, ARAIBO TO LAS ARENAS, PANTUKAN, DAVAO DE ORO | Region XI | Davao de Oro 1st DEO | On-Going | ₱82M | 92% | High risk89 | Flagged0.069 |
| 24CB0137CONSTRUCTION OF FLOOD CONTROL DIKE AT PANTINGAN RIVER (PHASE II), PILAR, BATAAN | Region III | Bataan 2nd DEO | On-Going | ₱108.1M | 98% | High risk88 | Flagged0.052 |
| 25H00088CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, REHABILITATION OF CALAPE-PANGGANGAN ROAD IN BOHOL | Region VII | Region VII | On-Going | ₱163.3M | 23% | High risk96 | Flagged0.049 |
| 24HB0183CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SIPAG- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES CONSTRUCTION OF NAPO - CAYACAY FLOOD CONTROL STRUCTURE, NAPO, ALICIA, BOHOL STA. 0+100 -STA.0+120 -SECTION 1; STA.0+388 | Region VII | Bohol 3rd DEO | On-Going | ₱140.4M | 65% | High risk72 | Flagged0.049 |
| 17D00057MFO-1 NATIONAL ROAD NETWORK SERVICES, NETWORK DEVELOPMENT, IMPROVEMENT.WIDENING OF NATIONAL ROADS-SECONDARY ROADS- STA.. ROSA-ULAT-TAGAYTAY ROAD, K0062+461.00 - K0065+505.00, CAVITE | Region IV-A | Region IV-A | On-Going | ₱132.2M | 67% | High risk72 | Flagged0.042 |
| 25HB0112CONVERGENCE & SPECIAL SUPPORT PROGRAM - SPECIAL FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF ROAD SAFETY DEVICES, INFORMATIVE SIGNS AND SOLAR LIGHTING - SECONDARY ROADS - THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD | Region VII | Bohol 3rd DEO | On-Going | ₱93.6M | 60% | High risk96 | Flagged0.031 |
| 25HB0114CONVERGENCE AND SPECIAL SUPPORT PROGRAM SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 INSTALLATION OF ROAD SAFETY DEVICES, INFORMATION SIGNS AND SOLAR LIGHTING - SECONDARY ROADS - THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL R | Region VII | Bohol 3rd DEO | On-Going | ₱95.1M | 67% | High risk96 | Flagged0.029 |
| 25HB0115CONVERGENCE AND SPECIAL SUPPORT PROGRAM SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 INSTALLATION OF ROAD SAFETY DEVICES, INFORMATIVE SIGNS AND SOLAR LIGHTING - SECONDARY ROADS - THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL R | Region VII | Bohol 3rd DEO | On-Going | ₱95.1M | 77% | High risk96 | Flagged0.027 |
| 25HB0113CONVERGENCE AND SPECIAL SUPPORT PROGRAM SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 INSTALLATION OF ROAD SAFETY DEVICES, INFORMATIVE SIGNS AND SOLAR LIGHTING - SECONDARY ROADS - THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL R | Region VII | Bohol 3rd DEO | On-Going | ₱95.1M | 76% | High risk96 | Flagged0.027 |
| 25HB0110CONVERGENCE & SPECIAL SUPPORT PROGRAM - SPECIAL FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF ROAD SAFETY DEVICES, INFORMATIVE SIGNS AND SOLAR LIGHTING - SECONDARY ROADS - THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD ( | Region VII | Bohol 3rd DEO | On-Going | ₱93.6M | 76% | High risk96 | Flagged0.027 |
| 25HB0111CONVERGENCE & SPECIAL SUPPORT PROGRAM - SPECIAL FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF ROAD SAFETY DEVICES, INFORMATIVE SIGNS AND SOLAR LIGHTING - SECONDARY ROADS - THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD ( | Region VII | Bohol 3rd DEO | On-Going | ₱93.6M | 89% | High risk96 | Flagged0.022 |
| 25JF0018CONSTRUCTION OF ROAD LEADING TO BRGY. POBLACION - BRGY. DALANGIN - BRGY. DALANGIN MUSLIM - BRGY. ACHASOL - BRGY. SAN ANTONIO - BRGY. TUGOP - BRGY. BANGCO - BRGY. KALAWIT, TITAY, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | On-Going | ₱17.8M | 72% | High risk94 | Flagged0.021 |
| 25KK0047PREVENTIVE MAINTENANCE - PRIMARY ROADS - BUTUAN CITY-CAGAYAN DE ORO CITY-ILIGAN CITY RD - K1298 + 000 - K1301 + 210 | Region X | Misamis Oriental 1st DEO | On-Going | ₱143.3M | 39% | High risk93 | Flagged0.021 |
| 25CG0068BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (DHVSU ANNEX), PHASE II, MALINO, CITY OF SAN FERNANDO, PAMPANGA | Region III | Pampanga 1st DEO | On-Going | ₱141.3M | 83% | High risk95 | Flagged0.018 |
| 25LI0084CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AGUSAN RIVER, PHASE 1, PUROK 7A TO 8, BARANGAY POBLACION, MONKAYO, DAVAO DE ORO | Region XI | Davao de Oro 2nd DEO | On-Going | ₱144.5M | 64% | High risk93 | Flagged0.016 |
| 24CK0178REHABILITATION OF DIKE ALONG RIO CHICO RIVER, RIGHT BANK, PACKAGE 3, MACALONG SECTION, STA. 1 + 799 - STA. 2 + 271, LA PAZ, TARLAC | Region III | Tarlac 2nd DEO | On-Going | ₱96.5M | 100% | High risk69 | Flagged0.015 |
| 17PA0101REHABILITATION & IMPROVEMENT OF DEMET-NORO FLOOD CONTROL, BARANGAY DEMET-NORO, LA PAZ, ABRA | Cordillera Administrative Region | Abra DEO | Completed | ₱46.9M | 100% | Medium risk52 | Flagged0.012 |
| 25LI0073CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AGUIBAWA RIVER LEADING TO AGUSAN RIVER, PHASE 2, BARANGAY BANTACAN, NEW BATAAN, DAVAO DE ORO | Region XI | Davao de Oro 2nd DEO | On-Going | ₱144.5M | 79% | High risk93 | Flagged0.012 |
| 17PA0079CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF SAGSAGPAT-POBLACION FLOOD CONTROL, VILLAVICIOSA, ABRA | Cordillera Administrative Region | Abra DEO | Completed | ₱44.3M | 100% | Medium risk50 | Flagged0.011 |
| 17PA0069REPAIR/REHABILITATION AND IMPROVEMENT OF POBLACION FLOOD CONTROL, LA PAZ, ABRA | Cordillera Administrative Region | Abra DEO | Completed | ₱45.8M | 100% | Medium risk50 | Flagged0.009 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 25HB0112CONVERGENCE & SPECIAL SUPPORT PROGRAM - SPECIAL FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF ROAD SAFETY DEVICES, INFORMATIVE SIGNS AND SOLAR LIGHTING - SECONDARY ROADS - THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD | Region VII | Bohol 3rd DEO | On-Going | ₱93.6M | 60% | High risk96 | Flagged0.031 |
| 2 | 25HB0114CONVERGENCE AND SPECIAL SUPPORT PROGRAM SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 INSTALLATION OF ROAD SAFETY DEVICES, INFORMATION SIGNS AND SOLAR LIGHTING - SECONDARY ROADS - THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL R | Region VII | Bohol 3rd DEO | On-Going | ₱95.1M | 67% | High risk96 | Flagged0.029 |
| 3 | 25HB0110CONVERGENCE & SPECIAL SUPPORT PROGRAM - SPECIAL FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF ROAD SAFETY DEVICES, INFORMATIVE SIGNS AND SOLAR LIGHTING - SECONDARY ROADS - THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD ( | Region VII | Bohol 3rd DEO | On-Going | ₱93.6M | 76% | High risk96 | Flagged0.027 |
| 4 | 25HB0113CONVERGENCE AND SPECIAL SUPPORT PROGRAM SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 INSTALLATION OF ROAD SAFETY DEVICES, INFORMATIVE SIGNS AND SOLAR LIGHTING - SECONDARY ROADS - THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL R | Region VII | Bohol 3rd DEO | On-Going | ₱95.1M | 76% | High risk96 | Flagged0.027 |
| 5 | 25HB0115CONVERGENCE AND SPECIAL SUPPORT PROGRAM SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 INSTALLATION OF ROAD SAFETY DEVICES, INFORMATIVE SIGNS AND SOLAR LIGHTING - SECONDARY ROADS - THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL R | Region VII | Bohol 3rd DEO | On-Going | ₱95.1M | 77% | High risk96 | Flagged0.027 |
| 6 | 25HB0111CONVERGENCE & SPECIAL SUPPORT PROGRAM - SPECIAL FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF ROAD SAFETY DEVICES, INFORMATIVE SIGNS AND SOLAR LIGHTING - SECONDARY ROADS - THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD ( | Region VII | Bohol 3rd DEO | On-Going | ₱93.6M | 89% | High risk96 | Flagged0.022 |
| 7 | 25H00088CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, REHABILITATION OF CALAPE-PANGGANGAN ROAD IN BOHOL | Region VII | Region VII | On-Going | ₱163.3M | 23% | High risk96 | Flagged0.049 |
| 8 | 25LI0040INSTALLATION /APPLICATION OF ROAD SAFETY FACILITIES (PAVEMENT MARKINGS, ROAD SIGNS) ALONG MONTEVISTA - DNAS ROAD - K1413+(-602) - K1413+000, K1414+189-K1415+539, K1416+000 -K1422+945, K1422+961 - K1425+961, K1425+1007-K1428+776,K1428+812-K1429+406, | Region XI | Davao de Oro 2nd DEO | On-Going | ₱48.2M | 99% | High risk95 | Flagged0.009 |
| 9 | 25CG0068BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (DHVSU ANNEX), PHASE II, MALINO, CITY OF SAN FERNANDO, PAMPANGA | Region III | Pampanga 1st DEO | On-Going | ₱141.3M | 83% | High risk95 | Flagged0.018 |
| 10 | 25JF0018CONSTRUCTION OF ROAD LEADING TO BRGY. POBLACION - BRGY. DALANGIN - BRGY. DALANGIN MUSLIM - BRGY. ACHASOL - BRGY. SAN ANTONIO - BRGY. TUGOP - BRGY. BANGCO - BRGY. KALAWIT, TITAY, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | On-Going | ₱17.8M | 72% | High risk94 | Flagged0.021 |
| 11 | 25LI0084CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AGUSAN RIVER, PHASE 1, PUROK 7A TO 8, BARANGAY POBLACION, MONKAYO, DAVAO DE ORO | Region XI | Davao de Oro 2nd DEO | On-Going | ₱144.5M | 64% | High risk93 | Flagged0.016 |
| 12 | 25LI0073CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AGUIBAWA RIVER LEADING TO AGUSAN RIVER, PHASE 2, BARANGAY BANTACAN, NEW BATAAN, DAVAO DE ORO | Region XI | Davao de Oro 2nd DEO | On-Going | ₱144.5M | 79% | High risk93 | Flagged0.012 |
| 13 | 25KK0047PREVENTIVE MAINTENANCE - PRIMARY ROADS - BUTUAN CITY-CAGAYAN DE ORO CITY-ILIGAN CITY RD - K1298 + 000 - K1301 + 210 | Region X | Misamis Oriental 1st DEO | On-Going | ₱143.3M | 39% | High risk93 | Flagged0.021 |
| 14 | 25KK0048PREVENTIVE MAINTENANCE - PRIMARY ROADS - BUTUAN CITY-CAGAYAN DE ORO CITY-ILIGAN CITY RD - K1308 + 814 - K1311 + 395 | Region X | Misamis Oriental 1st DEO | On-Going | ₱95.5M | 64% | High risk93 | Flagged0.007 |
| 15 | 25NI0032CONSTRUCTION OF BANK REVETMENT ALONG HINATUAN RIVER (MALIXI SECTION), MALIXI, TAGBINA, SURIGAO DEL SUR | Region XIII | Surigao del Sur 2nd DEO | On-Going | ₱96.4M | 90% | High risk92 | Flagged0.004 |
| 16 | 24LA0136CONSTRUCTION OF ROAD, ARAIBO TO LAS ARENAS, PANTUKAN, DAVAO DE ORO | Region XI | Davao de Oro 1st DEO | On-Going | ₱82M | 92% | High risk89 | Flagged0.069 |
| 17 | 24CB0137CONSTRUCTION OF FLOOD CONTROL DIKE AT PANTINGAN RIVER (PHASE II), PILAR, BATAAN | Region III | Bataan 2nd DEO | On-Going | ₱108.1M | 98% | High risk88 | Flagged0.052 |
| 18 | 25CK0097INSTALLATION OF ROAD SAFETY DEVICES, INFORMATION SIGNS AND SOLAR LIGHTING - PRIMARY ROAD ALONG MANILA NORTH ROAD (CAPAS AND BAMBAN SECTION), CAPAS AND BAMBAN, TARLAC | Region III | Tarlac 2nd DEO | On-Going | ₱98M | 100% | High risk75 | —-0.033 |
| 19 | 18DN0069OO1-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-TERTIARY ROADS-MARIKINA-INFANTA ROAD, K0026+512-K0027+000, K0027+000-K0027+663, K0027+663-K0027+812, K0027+812-K0027+899, K0032+400-K0033+165, ANTIPOLO CITY, 2ND LD | Region IV-A | Rizal 1st DEO | Completed | ₱93M | 100% | High risk75 | —-0.030 |
| 20 | 25CK0077ASSET PRESERVATION PROGRAM: PREVENTIVE MAINTENANCE - TERTIARY ROADS ALONG TARLAC - ZAMBALES ROAD, PACKAGE 4, K0116+168 TO K0117+780, CAPAS, TARLAC | Region III | Tarlac 2nd DEO | On-Going | ₱93.6M | 90% | High risk75 | —-0.030 |
| 21 | 24L00058OFF-CARRIAGEWAY IMPROVEMENT: CONSTRUCTION OF TRAFFIC ISLAND - DAANG MAHARLIKA (MN) - K1384+178 - K1386+503, DAVAO DE ORO | Region XI | Region XI | On-Going | ₱24.1M | 100% | High risk73 | Flagged0.008 |
| 22 | 17D00057MFO-1 NATIONAL ROAD NETWORK SERVICES, NETWORK DEVELOPMENT, IMPROVEMENT.WIDENING OF NATIONAL ROADS-SECONDARY ROADS- STA.. ROSA-ULAT-TAGAYTAY ROAD, K0062+461.00 - K0065+505.00, CAVITE | Region IV-A | Region IV-A | On-Going | ₱132.2M | 67% | High risk72 | Flagged0.042 |
| 23 | 24CJ0394CONSTRUCTION OF CAMILING RIVER LEFT BANK, ANOLING 3RD TO PAO 1ST SECTION PACKAGE B, CAMILING, TARLAC | Region III | Tarlac DEO | Completed | ₱67.6M | 100% | High risk72 | —-0.057 |
| 24 | 24HB0183CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SIPAG- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES CONSTRUCTION OF NAPO - CAYACAY FLOOD CONTROL STRUCTURE, NAPO, ALICIA, BOHOL STA. 0+100 -STA.0+120 -SECTION 1; STA.0+388 | Region VII | Bohol 3rd DEO | On-Going | ₱140.4M | 65% | High risk72 | Flagged0.049 |
| 25 | 17PI0088FLOOD CONTROL MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS; REHABILITATION/RESTORATION OF UPPER CHICO RIVER FLOOD -EROSION CONTROL PROJECTS - TIPUNAN MONAMON NORTE - SUYO MONAMON SUR, BAUKO MT. PROVINC | Cordillera Administrative Region | Mountain Province 1st DEO | Completed | ₱89.9M | 100% | High risk71 | —-0.029 |