Opening the dossier…
Opening the dossier…
Contractor dossier
95 projects on file, including joint ventures this contractor is part of.
Total projects
95
Total budget
₱1.6B
Average progress
92.6%
Completion rate
83.2%
Average risk score
44.2
Medium risk on average, out of 100
Flagged as unusual
4
4.2% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region IX | 93 | ₱1.6B | 44.2 | 4 | 92.5% |
| Region X | 1 | ₱8.3M | 44.5 | 0 | 100.0% |
| Negros Island Region | 1 | ₱9.8M | 44.3 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Buildings and Facilities | 31 | ₱116.3M | 30.4 | 0 | 92.7% |
| Roads | 30 | ₱640.6M | 49.3 | 2 | 93.1% |
| Flood Control and Drainage | 18 | ₱526.5M | 53.0 | 1 | 88.8% |
| Water Provision and Storage | 7 | ₱53.7M | 46.9 | 0 | 100.0% |
| Bridges | 7 | ₱135.5M | 46.8 | 0 | 100.0% |
| OTHER | 2 | ₱97.4M | 83.2 | 1 | 67.1% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24JA0163CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PUTIK RIVER, (PUTIK SECTION), ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱88.1M | 34% | High risk90 | Flagged0.074 |
| 16JF0047ASSET PRESERVATION OF NATIONAL ROADS - CONSTRUCTION/ UPGRADING REHABILITATION OF DRAINAGE ALONG NAT'L RD. - TERTIARY (S01143MN) IPIL-MAGDAUP WHARF RD., (K2014+(-483)-K2014+640) Z.S | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱9.4M | 100% | High risk76 | —-0.030 |
| 24JA0164CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TUMAGA RIVER, (GUIWAN SECTION), ZAMBOANGA CITY, PACKAGE 2 | Region IX | Zamboanga City 2nd DEO | On-Going | ₱90.5M | 0% | High risk75 | Flagged0.052 |
| 24JA0152CONSTRUCTION OF TETUAN-SANTA CATALINA ROAD (ESTRADA SECTION), ZAMBOANGA CITY PHASE 1 | Region IX | Zamboanga City 2nd DEO | On-Going | ₱57.8M | 0% | High risk69 | Flagged0.034 |
| 17JI0012REHABILITATION OF FLOOD CONTROL STRUCTURE (REVETMENT WALL, K1763+663 - K1763+750) ALONG IMELDA-BAYOG- KUMALARANG-LAPUYAN-MARGOSATUBIG ROAD, BARANGAY PILAR, DIPLAHAN, ZAMBOANGA SIBUGAY 1ST LD | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱9.3M | 100% | High risk64 | —-0.044 |
| 24J00130REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS - LANAO - PAGADIAN- ZAMBOANGA CITY ROAD | Region IX | Region IX | On-Going | ₱57.8M | 94% | High risk62 | —-0.040 |
| 22JI0003ROAD WIDENING -TERTIARY ROADS - JCT IMELDA-ALICIA RD - K1765 + 619.00 - K1766 + 525.00, K1768 + 066.00 - K1769 + 170.00 | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱57.8M | 100% | High risk61 | —-0.073 |
| 23JI0013CONSTRUCTION OF FLOOD CONTROL STRUCTURE (REVETMENT WALL) ALONG SIBUGUEY RIVER (UPSTREAM), BARANGAY SAMPOLI B, DIPLAHAN, ZAMBOANGA SIBUGAY (PACKAGE 2) | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱57.8M | 100% | High risk61 | —-0.072 |
| 17JI0004CLUSTER 4 - CONSTRUCTION OF MULTI-PURPOSE BUILDING IN THE MUNICIPALITY OF PAYAO, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱5.9M | 100% | High risk60 | —-0.057 |
| 25JI0086CONCRETING OF BRGY. NANAN FMR, BRGY. NANAN, PAYAO, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | On-Going | ₱19.9M | 44% | High risk60 | Flagged0.036 |
| 24JF0007CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TUPILAC RIVER (PHASE IV), R.T. LIM, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱57.7M | 100% | High risk60 | —-0.071 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24JA0163CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PUTIK RIVER, (PUTIK SECTION), ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱88.1M | 34% | High risk90 | Flagged0.074 |
| 24JA0164CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TUMAGA RIVER, (GUIWAN SECTION), ZAMBOANGA CITY, PACKAGE 2 | Region IX | Zamboanga City 2nd DEO | On-Going | ₱90.5M | 0% | High risk75 | Flagged0.052 |
| 25JI0086CONCRETING OF BRGY. NANAN FMR, BRGY. NANAN, PAYAO, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | On-Going | ₱19.9M | 44% | High risk60 | Flagged0.036 |
| 24JA0152CONSTRUCTION OF TETUAN-SANTA CATALINA ROAD (ESTRADA SECTION), ZAMBOANGA CITY PHASE 1 | Region IX | Zamboanga City 2nd DEO | On-Going | ₱57.8M | 0% | High risk69 | Flagged0.034 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24JA0163CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PUTIK RIVER, (PUTIK SECTION), ZAMBOANGA CITY | Region IX | Zamboanga City 2nd DEO | On-Going | ₱88.1M | 34% | High risk90 | Flagged0.074 |
| 2 | 16JF0047ASSET PRESERVATION OF NATIONAL ROADS - CONSTRUCTION/ UPGRADING REHABILITATION OF DRAINAGE ALONG NAT'L RD. - TERTIARY (S01143MN) IPIL-MAGDAUP WHARF RD., (K2014+(-483)-K2014+640) Z.S | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱9.4M | 100% | High risk76 | —-0.030 |
| 3 | 24JA0164CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TUMAGA RIVER, (GUIWAN SECTION), ZAMBOANGA CITY, PACKAGE 2 | Region IX | Zamboanga City 2nd DEO | On-Going | ₱90.5M | 0% | High risk75 | Flagged0.052 |
| 4 | 24JA0152CONSTRUCTION OF TETUAN-SANTA CATALINA ROAD (ESTRADA SECTION), ZAMBOANGA CITY PHASE 1 | Region IX | Zamboanga City 2nd DEO | On-Going | ₱57.8M | 0% | High risk69 | Flagged0.034 |
| 5 | 17JI0012REHABILITATION OF FLOOD CONTROL STRUCTURE (REVETMENT WALL, K1763+663 - K1763+750) ALONG IMELDA-BAYOG- KUMALARANG-LAPUYAN-MARGOSATUBIG ROAD, BARANGAY PILAR, DIPLAHAN, ZAMBOANGA SIBUGAY 1ST LD | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱9.3M | 100% | High risk64 | —-0.044 |
| 6 | 24J00130REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS - LANAO - PAGADIAN- ZAMBOANGA CITY ROAD | Region IX | Region IX | On-Going | ₱57.8M | 94% | High risk62 | —-0.040 |
| 7 | 22JI0003ROAD WIDENING -TERTIARY ROADS - JCT IMELDA-ALICIA RD - K1765 + 619.00 - K1766 + 525.00, K1768 + 066.00 - K1769 + 170.00 | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱57.8M | 100% | High risk61 | —-0.073 |
| 8 | 23JI0013CONSTRUCTION OF FLOOD CONTROL STRUCTURE (REVETMENT WALL) ALONG SIBUGUEY RIVER (UPSTREAM), BARANGAY SAMPOLI B, DIPLAHAN, ZAMBOANGA SIBUGAY (PACKAGE 2) | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱57.8M | 100% | High risk61 | —-0.072 |
| 9 | 17JI0004CLUSTER 4 - CONSTRUCTION OF MULTI-PURPOSE BUILDING IN THE MUNICIPALITY OF PAYAO, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱5.9M | 100% | High risk60 | —-0.057 |
| 10 | 25JI0086CONCRETING OF BRGY. NANAN FMR, BRGY. NANAN, PAYAO, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | On-Going | ₱19.9M | 44% | High risk60 | Flagged0.036 |
| 11 | 24JF0007CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TUPILAC RIVER (PHASE IV), R.T. LIM, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱57.7M | 100% | High risk60 | —-0.071 |
| 12 | 16JF0057CONST./ COMPLETION/ REHAB OF BUILDINGS AND OTHER STRUCTURES (CLUSTERED) A.) COMPLETION OF MPB ( STAGE OF COVERED COURT AND MARKET) BRGY. TILUBOG, NAGA, Z.S B.) CONST. OF MPB (COVERED COURT) BRGY. SIOLAN, KAB. Z.C C.) CONST. OF MPB (STAGE AND BLEACHER) KAB | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱5.9M | 100% | Medium risk59 | —-0.058 |
| 13 | 24JI0022CONSTRUCTION OF ROAD, BARANGAY LUMPANAC TO BARANGAY NANAN, IMELDA, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | On-Going | ₱49.5M | 85% | Medium risk58 | —-0.045 |
| 14 | 23JF0008ROAD WIDENING - PRIMARY ROADS - LANAO - PAGADIAN - ZAMBOANGA CITY RD. K1792 + 488.66 - K1792 + 820.00, K1795 + 920.00 - K1797 + 410.92 | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱53.5M | 100% | Medium risk58 | —-0.083 |
| 15 | 24JI0013CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - NATIONAL ROAD JUNCTION LEADING TO MALI LITTLE BAGUIO ECO TOURISM PARK, IMELDA, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | On-Going | ₱29.3M | 82% | Medium risk54 | —-0.041 |
| 16 | 20JG0055CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - CONSTRUCTION OF CONCRETE ROAD NRJ LEADING TO TUBO-TUBO BEACH, BAGANIAN, TABINA, ZAMBOANGA DEL SUR | Region IX | Zamboanga del Sur 2nd DEO | Completed | ₱14.5M | 100% | Medium risk54 | —-0.082 |
| 17 | 22JI0014CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - NATIONAL ROAD JUNCTION LEADING TO MALI LITTLE BAGUIO ECO TOURISM PARK, IMELDA, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱29.2M | 100% | Medium risk54 | —-0.085 |
| 18 | 19JF0124CONSTRUCTION OF PROVINCIAL RD. CONNECTING BRGY. CANACAN, SININAN, BANKER, TAMPILISAN, DIAMPAK & SIOLAN, KABASALAN, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱29.4M | 100% | Medium risk53 | —-0.085 |
| 19 | 22JF0053CONSTRUCTION OF ACCESS ROAD LEADING TO POBLACION TITAY-DALANGIN-DALANGIN MUSLIM-ACHASOL-SAN ANTONIO-TUGOP-BANCO-BOUDARY KALAWIT (PHASE IV), ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱29.2M | 100% | Medium risk53 | —-0.084 |
| 20 | 20JI0052CONSTRUCTION OF FLOOD CONTROL STRUCTURE (REVETMENT WALL) ALONG SIBUGUEY RIVER, 0+000-0+167, DIPLAHAN, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱19.6M | 100% | Medium risk53 | —-0.074 |
| 21 | 25JI0057CONSTRUCTION OF MULTI PURPOSE BUILDING, REBOCON, MALANGAS, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | On-Going | ₱4.9M | 28% | Medium risk52 | —-0.030 |
| 22 | 25JC0068CONSTRUCTION OF DRAINAGE STRUCTURE - CONSTRUCTION OF DRAINAGE CANAL (BOX CULVERT), BRGY. LITOLET, SIAYAN, ZAMBOANGA DEL NORTE | Region IX | Zamboanga del Norte 2nd DEO | On-Going | ₱4.9M | 47% | Medium risk52 | —-0.022 |
| 23 | 22JF0011CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TUPILAC RIVER (PHASE III), R.T. LIM, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱29.1M | 100% | Medium risk52 | —-0.071 |
| 24 | 23JI0017CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - NATIONAL ROAD JUNCTION LEADING TO MALI LITTLE BAGUIO ECO TOURISM PARK, IMELDA, ZAMBOANGA SIBUGAY | Region IX | Zamboanga Sibugay 1st DEO | Completed | ₱9.8M | 100% | Medium risk52 | —-0.086 |
| 25 | 23JF0006REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - IPIL - LILOY - SINDANGAN RD. K2000 + 560 - K2000 +860, K2004 + 095 - K2004 + 220, K2004 +560 - K2004 + 600, K2004 + 640 - K2004 + 650, K2005 + 000 - K2005 + | Region IX | Zamboanga Sibugay 2nd DEO | Completed | ₱40M | 100% | Medium risk52 | —-0.083 |