Contractor dossier
95 projects on file, including joint ventures this contractor is part of.
Total projects
95
Total budget
₱5.1B
Average progress
96.4%
Completion rate
85.3%
Average risk score
52.1
Medium risk on average, out of 100
Flagged as unusual
4
4.2% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Region VIII | 93 | ₱5B | 52.1 | 4 | 96.3% |
| National Capital Region | 2 | ₱91.5M | 48.8 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Flood Control and Drainage | 50 | ₱2.7B | 50.4 | 0 | 99.9% |
| Roads | 36 | ₱2B | 51.0 | 0 | 92.8% |
| OTHER | 5 | ₱343.6M | 83.5 | 4 | 84.7% |
| Buildings and Facilities | 4 | ₱75.2M | 43.0 | 0 | 100.0% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24I00394CONSTRUCTION OF MULTI-PURPOSE BUILDING (DORMITORY) - EASTERN VISAYAS STATE UNIVERSITY | Region VIII | Region VIII | On-Going | ₱39.8M | 29% | High risk90 | Flagged0.063 |
| 24I00118CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DAGUITAN - MARABONG RIVER, BARANGAY SABANG, DULAG, LEYTE | Region VIII | Region VIII | On-Going | ₱139.2M | 96% | High risk83 | Flagged0.018 |
| 24IG0027CONSTRUCTION OF ACCESS ROAD LEADING TO INAYUPAN PEAK, LEYTE | Region VIII | Leyte 5th DEO | On-Going | ₱49.3M | 100% | High risk82 | —-0.000 |
| 24ID0034FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF BINAHAAN FLOOD CONTROL STRUCTURE BINAHAAN RIVER BASIN,PASTRANA,LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱66.9M | 100% | High risk81 | Flagged0.004 |
| 24ID0040FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF BINAHAAN FLOOD CONTROL STRUCTURE BINAHAAN RIVER BASIN(UPSTREAM),BRGY. ABRE,DAGAMI,LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱48.5M | 98% | High risk81 | Flagged0.003 |
| 23I00014CONSTRUCTION OF CARIGARA TIDE EMBANKMENT, CARIGARA, LEYTE | Region VIII | Region VIII | Completed | ₱123.5M | 100% | High risk64 | —-0.061 |
| 23IM0048CONSTRUCTION OF SHORE PROTECTION, OLD ROAD, PHASE 2, TACLOBAN CITY | Region VIII | Tacloban City DEO | Completed | ₱96.3M | 100% | High risk64 | —-0.069 |
| 24I00039NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - JAVIER BY-PASS ROAD, LEYTE | Region VIII | Region VIII | On-Going | ₱175.3M | 96% | High risk64 | —-0.027 |
| 22I00051CONSTRUCTION OF DAGUITAN - MARABONG FLOOD CONTROL STRUCTURE, SABANG, DULAG, LEYTE | Region VIII | Region VIII | Completed | ₱96M | 100% | High risk63 | —-0.067 |
| 22I00052NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BURAUEN BYPASS ROAD, LEYTE | Region VIII | Region VIII | Completed | ₱139.2M | 100% | High risk63 | —-0.072 |
| 22I00047CONSTRUCTION OF MALITBOGAY FLOOD CONTROL STRUCTURE AND DRAINAGE SYSTEM, DAGUITAN RIVER BASIN, MALITBOGAY, BURAUEN, LEYTE | Region VIII | Region VIII | On-Going | ₱96.2M | 96% | High risk62 | —-0.008 |
| 21I00015CONSTRUCTION OF CARIGARA TIDE EMBANKMENT, STA. 0+150 - STA. 0+283, CARIGARA, LEYTE | Region VIII | Region VIII | Completed | ₱92.5M | 100% | High risk61 | —-0.049 |
| 22I00049CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - ACCESS ROAD LEADING TO CALUMPIJAN ISLAND AND COASTAL ROAD DIVING SPOT, CAPOOCAN, LEYTE | Region VIII | Region VIII | Completed | ₱92.8M | 100% | High risk60 | —-0.074 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 24I00394CONSTRUCTION OF MULTI-PURPOSE BUILDING (DORMITORY) - EASTERN VISAYAS STATE UNIVERSITY | Region VIII | Region VIII | On-Going | ₱39.8M | 29% | High risk90 | Flagged0.063 |
| 24I00118CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DAGUITAN - MARABONG RIVER, BARANGAY SABANG, DULAG, LEYTE | Region VIII | Region VIII | On-Going | ₱139.2M | 96% | High risk83 | Flagged0.018 |
| 24ID0034FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF BINAHAAN FLOOD CONTROL STRUCTURE BINAHAAN RIVER BASIN,PASTRANA,LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱66.9M | 100% | High risk81 | Flagged0.004 |
| 24ID0040FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF BINAHAAN FLOOD CONTROL STRUCTURE BINAHAAN RIVER BASIN(UPSTREAM),BRGY. ABRE,DAGAMI,LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱48.5M | 98% | High risk81 | Flagged0.003 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 1 | 24I00394CONSTRUCTION OF MULTI-PURPOSE BUILDING (DORMITORY) - EASTERN VISAYAS STATE UNIVERSITY | Region VIII | Region VIII | On-Going | ₱39.8M | 29% | High risk90 | Flagged0.063 |
| 2 | 24I00118CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DAGUITAN - MARABONG RIVER, BARANGAY SABANG, DULAG, LEYTE | Region VIII | Region VIII | On-Going | ₱139.2M | 96% | High risk83 | Flagged0.018 |
| 3 | 24IG0027CONSTRUCTION OF ACCESS ROAD LEADING TO INAYUPAN PEAK, LEYTE | Region VIII | Leyte 5th DEO | On-Going | ₱49.3M | 100% | High risk82 | —-0.000 |
| 4 | 24ID0034FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF BINAHAAN FLOOD CONTROL STRUCTURE BINAHAAN RIVER BASIN,PASTRANA,LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱66.9M | 100% | High risk81 | Flagged0.004 |
| 5 | 24ID0040FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF BINAHAAN FLOOD CONTROL STRUCTURE BINAHAAN RIVER BASIN(UPSTREAM),BRGY. ABRE,DAGAMI,LEYTE | Region VIII | Leyte 2nd DEO | On-Going | ₱48.5M | 98% | High risk81 | Flagged0.003 |
| 6 | 23I00014CONSTRUCTION OF CARIGARA TIDE EMBANKMENT, CARIGARA, LEYTE | Region VIII | Region VIII | Completed | ₱123.5M | 100% | High risk64 | —-0.061 |
| 7 | 23IM0048CONSTRUCTION OF SHORE PROTECTION, OLD ROAD, PHASE 2, TACLOBAN CITY | Region VIII | Tacloban City DEO | Completed | ₱96.3M | 100% | High risk64 | —-0.069 |
| 8 | 24I00039NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - JAVIER BY-PASS ROAD, LEYTE | Region VIII | Region VIII | On-Going | ₱175.3M | 96% | High risk64 | —-0.027 |
| 9 | 22I00051CONSTRUCTION OF DAGUITAN - MARABONG FLOOD CONTROL STRUCTURE, SABANG, DULAG, LEYTE | Region VIII | Region VIII | Completed | ₱96M | 100% | High risk63 | —-0.067 |
| 10 | 22I00052NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BURAUEN BYPASS ROAD, LEYTE | Region VIII | Region VIII | Completed | ₱139.2M | 100% | High risk63 | —-0.072 |
| 11 | 22I00047CONSTRUCTION OF MALITBOGAY FLOOD CONTROL STRUCTURE AND DRAINAGE SYSTEM, DAGUITAN RIVER BASIN, MALITBOGAY, BURAUEN, LEYTE | Region VIII | Region VIII | On-Going | ₱96.2M | 96% | High risk62 | —-0.008 |
| 12 | 21I00015CONSTRUCTION OF CARIGARA TIDE EMBANKMENT, STA. 0+150 - STA. 0+283, CARIGARA, LEYTE | Region VIII | Region VIII | Completed | ₱92.5M | 100% | High risk61 | —-0.049 |
| 13 | 22I00049CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - ACCESS ROAD LEADING TO CALUMPIJAN ISLAND AND COASTAL ROAD DIVING SPOT, CAPOOCAN, LEYTE | Region VIII | Region VIII | Completed | ₱92.8M | 100% | High risk60 | —-0.074 |
| 14 | 24I00005NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BURAUEN BYPASS ROAD, PACKAGE 1, LEYTE | Region VIII | Region VIII | On-Going | ₱94.3M | 89% | Medium risk60 | —-0.038 |
| 15 | 19I00143REPAIR/REHABILITATION/IMPROVEMENT OF ROAD SLIPPED/SHOULDER SLIPPED ALONG DAANG MAHARLIKA, K0862+750, BRGY. LAYGAYUN, PINABACDAO, SAMAR | Region VIII | Region VIII | Completed | ₱67.9M | 100% | Medium risk59 | —-0.032 |
| 16 | 22I00062NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/NEW ROADS - JARO - RUBAS - ORMOC ROAD JARO SIDE, LEYTE, LEYTE 2ND LD | Region VIII | Region VIII | Completed | ₱106M | 100% | Medium risk59 | —-0.071 |
| 17 | 19ID0043NETWORK DEVELOPMENT -PAVING OF UNPAVED ROADS-TERTIARY ROADS,BURAUEN-MAHAGNAO RD.-K0989+000-K0989+195, K0991+763-K0993+425 | Region VIII | Leyte 2nd DEO | Completed | ₱96.5M | 100% | Medium risk59 | —-0.084 |
| 18 | 17ID0055NETWORK DEVELOPMENT-IMPROVEMENT/WIDENING OF NATIONAL ROADS - TERTIARY, BAGAHUPI-BABATNGON-STA. CRUZ-BARUGO-CARIGARA ROAD S00069LT K0938+900 - K0940+871 | Region VIII | Leyte 2nd DEO | Completed | ₱45.9M | 100% | Medium risk57 | —-0.060 |
| 19 | 23I00027CONSTRUCTION OF STORM SURGE PROTECTION: TIDE EMBANKMENT, SUBSECTION 6.13, BARANGAY STO. NIÑO, TANAUAN, LEYTE | Region VIII | Region VIII | Completed | ₱89.5M | 100% | Medium risk56 | —-0.069 |
| 20 | 24I00114NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CAPOOCAN-LEYTE, LEYTE COASTAL ROAD, LEYTE | Region VIII | Region VIII | On-Going | ₱72.6M | 91% | Medium risk55 | —-0.047 |
| 21 | 19IG0056NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - ABUYOG-SILAGO ROAD - K0987+106-K0987+332, K0987+351-K0988+425, K0988+451-K0989+604 | Region VIII | Leyte 5th DEO | Completed | ₱72.4M | 100% | Medium risk55 | —-0.088 |
| 22 | 21I00065NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS / NEW ROADS BURAUEN - ALBUERA ROAD (BURAUEN SIDE), BURAUEN, LEYTE | Region VIII | Region VIII | Completed | ₱89.3M | 100% | Medium risk55 | —-0.085 |
| 23 | 20I00012CONSTRUCTION OF CARIGARA TIDE EMBANKMENT, STA. 0+000 - STA. 0+150, CARIGARA, LEYTE | Region VIII | Region VIII | Completed | ₱88.9M | 100% | Medium risk55 | —-0.066 |
| 24 | 23I00003NETWORK DEVELOPMENT - CONSTRUCTION OF BYPASS AND DIVERSION ROADS - BURAUEN BYPASS ROAD, LEYTE, LEYTE 2ND LD | Region VIII | Region VIII | Completed | ₱72.2M | 100% | Medium risk54 | —-0.085 |
| 25 | 17IG0007IMPROVEMENT/WIDENING OF NATIONAL ROADS - LA PAZ - JAVIER - BITO ROAD K0070+250 - K0071+000, K0076+000 - K0076+524, JAVIER, LEYTE | Region VIII | Leyte 5th DEO | Completed | ₱28.1M | 100% | Medium risk54 | —-0.059 |