Contractor dossier
904 projects on file, including joint ventures this contractor is part of.
Total projects
904
Total budget
₱55.2B
Average progress
95.2%
Completion rate
85.4%
Average risk score
48.4
Medium risk on average, out of 100
Flagged as unusual
54
6.0% of their projects
Risk mix
Exhibit A
| Region | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Negros Island Region | 200 | ₱8.9B | 48.7 | 9 | 97.6% |
| Region XI | 187 | ₱9.1B | 47.0 | 3 | 99.1% |
| Region IV-B | 170 | ₱16.7B | 50.6 | 18 | 92.7% |
| Region XII | 118 | ₱7.9B | 37.1 | 2 | 99.9% |
| Region VII | 44 | ₱3.6B | 67.6 | 12 | 74.1% |
| Region I | 31 | ₱995.1M | 46.7 | 1 | 100.0% |
| Region VI | 29 | ₱1.5B | 51.6 | 2 | 96.5% |
| Region XIII | 27 | ₱970.7M | 43.1 | 0 | 99.6% |
| Region X | 25 | ₱959.8M | 38.3 | 0 | 100.0% |
| Region IV-A | 17 | ₱1.4B | 71.2 | 4 | 53.1% |
| Region V | 17 | ₱1.5B | 61.0 | 1 | 87.1% |
| Region IX | 16 | ₱441.2M | 47.3 | 0 | 99.3% |
| National Capital Region | 11 | ₱401M | 48.1 | 0 | 99.4% |
| Region VIII | 5 | ₱176.3M | 44.9 | 0 | 100.0% |
| Region III | 4 | ₱431.7M | 75.3 | 2 | 53.5% |
| Cordillera Administrative Region | 3 | ₱167.5M | 54.4 | 0 | 100.0% |
Exhibit B
| Category | Projects | Total budget | Avg risk | Flagged | Avg progress |
|---|---|---|---|---|---|
| Roads | 338 | ₱21.3B | 47.5 | 2 | 97.1% |
| Flood Control and Drainage | 318 | ₱25B | 53.4 | 33 | 91.8% |
| Buildings and Facilities | 138 | ₱3.1B | 32.9 | 1 | 98.8% |
| Bridges | 53 | ₱824.6M | 36.8 | 0 | 100.0% |
| OTHER | 35 | ₱3.4B | 72.0 | 7 | 97.9% |
| GAA 2025 SSP | 10 | ₱938.1M | 95.3 | 10 | 60.4% |
| Water Provision and Storage | 5 | ₱40.3M | 36.5 | 0 | 100.0% |
| GAA 2025 OO-2 | 4 | ₱348.9M | 93.5 | 0 | 90.0% |
| Bridges, Roads | 2 | ₱217.5M | 60.5 | 0 | 100.0% |
| GAA 2025 OO-1 | 1 | ₱139.7M | 92.8 | 1 | 3.9% |
Exhibit C · High-risk projects
Ranked by risk score, then anomaly score. Showing up to 20.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 25GN0079CONSTRUCTION OF SHORELINE PROTECTION ALONG GUIMARAS STRAIT - BRGY. ZONE 1, PULUPANDAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 4th DEO | On-Going | ₱98.9M | 69% | High risk96 | Flagged0.023 |
| 25GN0076CONSTRUCTION OF SHORELINE PROTECTION ALONG GUIMARAS STRAIT - BRGY. ZONE 3 TO BRGY. ZONE 1, PULUPANDAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 4th DEO | On-Going | ₱98.9M | 75% | High risk96 | Flagged0.021 |
| 25CP0067CONVERG. AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATL. ROADS LEADING TO MAJOR/ STRAT. PUBLIC BLDGS./FACILITIES-CONST. OF ROAD, PHASE I, SITIO TUBIGAN - SITIO CALUMPIT, BRGY. | Region III | Bulacan 3rd DEO | On-Going | ₱142.5M | 20% | High risk96 | Flagged0.035 |
| 25RI0073CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES: CONSTRUCTION OF DORMITORY IN NEGROS ORIENTAL STATE UNIVERSITY - SIATON CAMPUS, SIATON, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 3rd DEO | On-Going | ₱96.4M | 26% | High risk96 | Flagged0.039 |
| 25FD0083CONSTRUCTION OF ROAD, BARANGAY TIBLE, LUPI, CAMARINES SUR | Region V | Camarines Sur 1st DEO | On-Going | ₱139.4M | 35% | High risk95 | Flagged0.030 |
| 25CL0220CONSTRUCTION OF PROTECTIVE DIKE ALONG LAUIS RIVER, CANDELARIA, ZAMBALES (PHASE 1) | Region III | Zambales 1st DEO | On-Going | ₱97.6M | 62% | High risk95 | Flagged0.025 |
| 25GL0093CONSTRUCTION OF BINALBAGAN RIVER BANK SLOPE PROTECTION (DOWNSTREAM OF ALICANTE BRIDGE) ALONG JCT BAGONAWA - LA CASTELLANA - ISABELA RD, LEFT BANK, STA 30+030 - 30+180, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | On-Going | ₱99M | 96% | High risk95 | Flagged0.014 |
| 25GN0075CONSTRUCTION OF LOCAL ACCESS ROAD WITH SLOPE PROTECTION STRUCTURE AT SITIO CAVAN, BARANGAY TAPONG, PULUPANDAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 4th DEO | On-Going | ₱74.2M | 46% | High risk95 | Flagged0.023 |
| 25GN0077CONSTRUCTION OF SLOPE PROTECTION STRUCTURES ALONG BAGO RIVER, PUROK MASIM-ONG, BARANGAY UBAY, PULUPANDAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 4th DEO | On-Going | ₱19.8M | 98% | High risk95 | Flagged0.005 |
| 25EH0022CONSTRUCTION OF CAUSEWAY ALONG PUNTA, LOOC, ROMBLON, TABLAS ISLAND, ROMBLON | Region IV-B | Romblon DEO | On-Going | ₱71.3M | 76% | High risk94 | Flagged0.019 |
| 25GN0050CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG PATIC CREEK, VALLADOLID, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 4th DEO | On-Going | ₱95.5M | 81% | High risk94 | —-0.009 |
| 25HO0012ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF REVETMENT WALL ALONG GINATILAN RIVER (RIGHT SIDE), BARANG | Region VII | Cebu 7th DEO | On-Going | ₱95.1M | 99% | High risk94 | —-0.011 |
| 25GL0061CONSTRUCTION OF GUINTUBHAN RIVER BANK SLOPE PROTECTION STRUCTURE UPSTREAM (RIGHT BANK) OF GUINTUBHAN BRIDGE, BARANGAY 2, ISABELA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | On-Going | ₱96.5M | 92% | High risk94 | —-0.012 |
| 25E00137CONSTRUCTION OF MISSING LINKS/NEW ROADS- ODIONGAN EAST-WEST ROAD, ODIONGAN, ROMBLON | Region IV-B | Region IV-B | On-Going | ₱139.7M | 4% | High risk93 | Flagged0.033 |
| 25GL0062CONSTRUCTION OF BINALBAGAN RIVER BANK SLOPE PROTECTION STRUCTURE ALONG JCT. BAGONAWA - LA CASTELLANA - ISABELA ROAD, PHASE 2, BARANGAY 5 POBLACION, ISABELA, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | On-Going | ₱61.8M | 88% | High risk92 | —-0.015 |
| 23GL0125CONSTRUCTION OF BINALBAGAN RIVERBANK SLOPE PROTECTION AT PUROK TUWAY AND PUROK PUNAW, BARANGAY CANMOROS, BINALBAGAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | On-Going | ₱48.3M | 100% | High risk87 | Flagged0.047 |
| 23HO0270CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF RIVERBANK PROTECTION ALONG TALABA RIVER SITIO CANSIBOG, BARANG | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.082 |
| 23HO0271CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF RIVERBANK PROTECTION ALONG TALABA RIVER, BARANGAY TUPAS, RONDA, CEBU ( | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.082 |
| 23HO0256CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF RIVERBANK PROTECTION AT BALA RIVER (DOWNSTREAM RIGHT SIDE), MO | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.082 |
| 23HO0272CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF RIVERBANK PROTECTION ALONG TALABA RIVER (SITIO CANSIBOG - SITI | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.082 |
Exhibit D · Unusual projects
Ranked by anomaly score. Showing up to 20. Red rings on the map mark flagged projects.
| Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|
| 23HO0270CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF RIVERBANK PROTECTION ALONG TALABA RIVER SITIO CANSIBOG, BARANG | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.082 |
| 23HO0271CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF RIVERBANK PROTECTION ALONG TALABA RIVER, BARANGAY TUPAS, RONDA, CEBU ( | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.082 |
| 23HO0256CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF RIVERBANK PROTECTION AT BALA RIVER (DOWNSTREAM RIGHT SIDE), MO | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.082 |
| 23HO0272CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF RIVERBANK PROTECTION ALONG TALABA RIVER (SITIO CANSIBOG - SITI | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.082 |
| 23HO0255CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF RIVERBANK PROTECTION AT BALA RIVER (DOWNSTREAM LEFT SIDE), MOAL | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.082 |
| 23HO0288CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF RIVERBANK PROTECTION AT BALA RIVER (UPSTREAM RIGHT | Region VII | Cebu 7th DEO | On-Going | ₱94.5M | 0% | High risk87 | Flagged0.072 |
| 23HO0313CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BALA RIVER, SITIO LAWAAN (UPSTRE | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.072 |
| 23HO0311CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BALA RIVER, SITIO KANDUONG (DOWN | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.072 |
| 23HO0310CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BALA RIVER, SITIO KANDUONG (DOWN | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.072 |
| 23HO0287CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF RIVERBANK PROTECTION AT BALA RIVER (UPSTREAM LEFT | Region VII | Cebu 7th DEO | On-Going | ₱94.5M | 0% | High risk87 | Flagged0.072 |
| 23HO0312CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BALA RIVER, SITIO LAWAAN (UPSTRE | Region VII | Cebu 7th DEO | On-Going | ₱94.6M | 0% | High risk87 | Flagged0.072 |
| 21L00110CONSTRUCTION OF ROAD (INCLUDING BRIDGE), BUTAY, BARANGAY PICHON, CARAGA, DAVAO ORIENTAL | Region XI | Region XI | On-Going | ₱122.3M | 93% | High risk80 | Flagged0.051 |
| 23GL0125CONSTRUCTION OF BINALBAGAN RIVERBANK SLOPE PROTECTION AT PUROK TUWAY AND PUROK PUNAW, BARANGAY CANMOROS, BINALBAGAN, NEGROS OCCIDENTAL | Negros Island Region | Negros Occidental 2nd DEO | On-Going | ₱48.3M | 100% | High risk87 | Flagged0.047 |
| 25RI0073CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES: CONSTRUCTION OF DORMITORY IN NEGROS ORIENTAL STATE UNIVERSITY - SIATON CAMPUS, SIATON, NEGROS ORIENTAL | Negros Island Region | Negros Oriental 3rd DEO | On-Going | ₱96.4M | 26% | High risk96 | Flagged0.039 |
| 24E00195SUSTAINABLE INFRASTRUCTRE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COPASTAL ROAD, PHASE 2, STA. MARIA, TABLAS ISLAND, ROMBLON | Region IV-B | Region IV-B | On-Going | ₱241.2M | 80% | High risk83 | Flagged0.037 |
| 25CP0067CONVERG. AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATL. ROADS LEADING TO MAJOR/ STRAT. PUBLIC BLDGS./FACILITIES-CONST. OF ROAD, PHASE I, SITIO TUBIGAN - SITIO CALUMPIT, BRGY. | Region III | Bulacan 3rd DEO | On-Going | ₱142.5M | 20% | High risk96 | Flagged0.035 |
| 24E00193SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD, PHASE 2, BRGY. TUGDAN, TABLAS ISLAND, ROMBLON | Region IV-B | Region IV-B | On-Going | ₱241.2M | 87% | High risk83 | Flagged0.034 |
| 24E00099FLOOD MANAGEMENT PROGRAM- CONST./MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONST. OF DUBDUBAN FLOOD CONTROL STRUCTURE (UPSTREAM), SAN AGUSTIN, TABLAS ISLAND, ROMBLON | Region IV-B | Region IV-B | On-Going | ₱241.2M | 87% | High risk83 | Flagged0.034 |
| 25E00137CONSTRUCTION OF MISSING LINKS/NEW ROADS- ODIONGAN EAST-WEST ROAD, ODIONGAN, ROMBLON | Region IV-B | Region IV-B | On-Going | ₱139.7M | 4% | High risk93 | Flagged0.033 |
| 25FD0083CONSTRUCTION OF ROAD, BARANGAY TIBLE, LUPI, CAMARINES SUR | Region V | Camarines Sur 1st DEO | On-Going | ₱139.4M | 35% | High risk95 | Flagged0.030 |
Exhibit E · Evidence locker
Sorted by risk score.
| # | Contract | Region | Province / DEO | Status | Budget | Progress | Risk | Anomaly |
|---|---|---|---|---|---|---|---|---|
| 626 | 18AF0097CONST OF 4 STRY 4 CL (TVL PLUS CORRIDOR) (BEFF 2018 BATCH 1) PRES ELPIDIO QUIRINO NAT HIGH SCHL, AGO | Region I | La Union 2nd DEO | Completed | ₱26.5M | 100% | Medium risk43 | —-0.036 |
| 627 | 18NC0069ROAD WIDENING OF NATIONAL ROADS ALONG DAANG MAHARLIKA (AGUSAN-DAVAO SECTION) INCL ROW (S00439MJN) K1338+748.00 - K1340+228, BUNAWAN, AGUSAN DEL SUR | Region XIII | Agusan del Sur 2nd DEO | Completed | ₱55.3M | 100% | Medium risk43 | —-0.072 |
| 628 | 18AF0094CONST OF 4 STRY 4 CL (TVL PLUS CORRIDOR) (BEFF 2018 BATCH 1) DON EULOGIO DE GUZMAN MNHS, BAUANG, LU | Region I | La Union 2nd DEO | Completed | ₱27.1M | 100% | Medium risk43 | —-0.034 |
| 629 | 18AF0096CONST OF 4 STRY 4 CL (TVL PLUS CORRIDOR) (BEFF 2018 BATCH 1), PARINGAO NAT HIGH SCHL, BAUANG, LU | Region I | La Union 2nd DEO | Completed | ₱26.5M | 100% | Medium risk43 | —-0.035 |
| 630 | 18M00027ROAD WIDENING AWANG UPI-LEBAK-KALAMANSIG-PALIMBANG-SARANGANI ROAD, K1935+634-K1936+134, K1936+266-K1937+120, K1937+250-K1939+064, K1939+193-K1939+500, SULTAN KUDARAT | Region XII | Region XII | Completed | ₱96M | 100% | Medium risk43 | —-0.043 |
| 631 | 19AF0062NETWORK DEV. OFF CARRIAGEWAY IMPROVEMENT SECONDARY RDS, AGOO-BAGUIO CITY RD, K0250+556 | Region I | La Union 2nd DEO | Completed | ₱11.5M | 100% | Medium risk43 | —-0.089 |
| 632 | 20NH0014CONSTRUCTION OF DIKE REVETMENT ALONG TAGO RIVER BASIN (GAMUT SECTION), TAGO, SURIGAO DEL SUR | Region XIII | Surigao del Sur 1st DEO | Completed | ₱77.2M | 100% | Medium risk43 | —-0.057 |
| 633 | 18NC0068OFF CARRAGEWAY IMPROVEMENT ALONG DAANG MAHARLIKA (AGUSAN-DAVAO SECTION) (S00439MN) K1306+550 - K1307+471; K1308+496 - K1308+619; K1308+619 - K1309+112; K1309+112; K1309+183; K1309+311 - K1310+482, SAN FRANCISCO, AGUSAN DEL SUR | Region XIII | Agusan del Sur 2nd DEO | Completed | ₱55.5M | 100% | Medium risk43 | —-0.078 |
| 634 | 20M00056CONSTRUCTION OF CONCRETE ROAD - ROAD FROM NHJ-BRGY. KADI-BRGY. BUGSO-SITIO BALITE- SITIO SAPALE AND CROSSING BUGSO-LANDFILL IN SUPPORT TO AGRIBUSINESS ESTABLISHMENT, STA. 0001+200-STA. 0003+080, SENATOR NINOY AQUINO, SULTAN KUDARAT | Region XII | Region XII | Completed | ₱101.2M | 100% | Medium risk43 | —-0.075 |
| 635 | 18M00026CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE SNA-LEBAK-KALAMANSIG ROAD, K1899+303-K1899+435 SULTAN KUDARAT | Region XII | Region XII | Completed | ₱57.6M | 100% | Medium risk43 | —-0.036 |
| 636 | 21M00035CONSTRUCTION OF CONCRETE ROAD - TUKA-BAI SARIPINANG ROAD IN BAGUMBAYAN SK IN SUPPORT OF AGRI-BASED INDUSTRIES: PINEAPPLE COFFEE, RUBBER, CORN AND MUSCOVADO PROCESSING PLANT, STA. 3+030 - STA. 5+200, | Region XII | Region XII | Completed | ₱100.8M | 100% | Medium risk42 | —-0.070 |
| 637 | 20M00028PAVING OF UNPAVED ROADS - DEMOLOC - LITTLE BAGUIO-ALABEL ROAD- K1692+615-K1693+195, ALABEL, SARANGANI. | Region XII | Region XII | Completed | ₱101.5M | 100% | Medium risk42 | —-0.072 |
| 638 | 21MG0096CONSTRUCTION OF CONCRETE ROAD, JCT. SURALLAH-LAKE SEBU-MAITUM ROAD-LUHIB-LAMFUGON-TASIMAN BYPASS ROAD-STA.4+770.31-8+140, LAKE SEBU, SOUTH COTABATO | Region XII | South Cotabato 2nd DEO | Completed | ₱93.6M | 100% | Medium risk42 | —-0.077 |
| 639 | 21AF0056NETWORK DEV PROG RD WIDENING - PRI RDS - MNR, K0232+696 - K0233+000, AGOO, LU | Region I | La Union 2nd DEO | Completed | ₱9.4M | 100% | Medium risk42 | —-0.088 |
| 640 | 20MH0009ROAD WIDENING ALONG ISULAN JCT. - NINOY AQUINO ROAD - K1788+000 - K1791+526 BAGUMBAYAN, SULTAN KUDARAT | Region XII | Sultan Kudarat 2nd DEO | Completed | ₱96.5M | 100% | Medium risk42 | —-0.076 |
| 641 | 18MC0059ROAD WIDENING ALONG MATALAM-M'LANG-BAGONTAPAY ROAD, NORTH COTABATO | Region XII | Cotabato 2nd DEO | Completed | ₱96.5M | 100% | Medium risk42 | —-0.077 |
| 642 | 21M00016CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE DEMOLOC-LITTLE BAGUIO ALABEL RD K1673+059 K1673+162, K1673+607-K1673+642, K1674+626 K1674+673, K1674+908-K1674+942, ALABEL, SARANGANI | Region XII | Region XII | Completed | ₱99M | 100% | Medium risk42 | —-0.057 |
| 643 | 18AF0102CONST OF 2 STRY 8 CL SCHL BLDG (BEFF 2018 BATCH 1) SAN JULIAN I/, AGOO, LU | Region I | La Union 2nd DEO | Completed | ₱15.6M | 100% | Medium risk42 | —-0.044 |
| 644 | 18EH0098CONSTRUCTION/REPAIR/REHABILITATION OF ILAYA BULI RIVER CONTROL, SITIO ILAYA, BRGY. BULI, SAN AGUSTIN, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱47.4M | 100% | Medium risk42 | —-0.074 |
| 645 | 19EH0039CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF PANIQUE FLOOD CONTROL STRUCTURE, STA. 000 + 000.00 - VSTA. 000 + 409.20 (L/S), PANIQUE, ODIONGAN, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱47.9M | 100% | Medium risk42 | —-0.075 |
| 646 | 20M00029CONSTRUCTION OF CONCRETE ROAD MALALAG- KIAYAP-ZION-BATIAN ROAD LEADING TO ZION-BATIAN ECOSITES, STA. 2+329 STA. 6+529, BRGY. BATIAN. MAITUM, SARANGANI | Region XII | Region XII | Completed | ₱101.3M | 100% | Medium risk42 | —-0.072 |
| 647 | 18EH0059CONSTRUCTION OF BACHAWAN (I-LAYA) FLOOD CONTROL STRUCTURE ALONG TABLAS CIRCUMFERENTIAL ROAD, BACHAWAN, SAN AGUSTIN, ROMBLON | Region IV-B | Romblon DEO | Completed | ₱48.4M | 100% | Medium risk42 | —-0.070 |
| 648 | 23LG0118CONSTRUCTION OF 2STY10CL WITH ICT & SL, FRANCISCO HINAYON ES, MATI, DAVAO ORIENTAL | Region XI | Davao Oriental 2nd DEO | Completed | ₱31.9M | 100% | Medium risk42 | —-0.029 |
| 649 | 23LG0093CONCRETING OF BRGY. TAGBOA FMR, BRGY. TAGBOA, LUPON, DAVAO ORIENTAL | Region XI | Davao Oriental 2nd DEO | Completed | ₱9.6M | 100% | Medium risk42 | —-0.024 |
| 650 | 18M00028ROAD WIDENING SNA LEBAK-KALAMANSIG ROAD, K1852+161-K1852+837, K1853+000-K1853+701, K1853+871-K1854+760, K1855+760-K1857+460, SULTAN KUDARAT | Region XII | Region XII | Completed | ₱86.7M | 100% | Medium risk42 | —-0.044 |